Notice of Application Accepted For Filing and Soliciting Comments, Protests, and Motions To Intervene, 32322-32323 [E5-2780]

Download as PDF 32322 Federal Register / Vol. 70, No. 105 / Thursday, June 2, 2005 / Notices issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. j. Description of Project: The proposed project would consist of: (1) A proposed impoundment having a surface area of 10 acres and storage capacity of 50 acrefeet and normal water surface elevation of 1670 feet msl, (2) two proposed 48inch-diameter steel penstocks, 18.8mile-long and 4-mile-long, (3) a proposed powerhouse containing two generating units having a total installed capacity of 7.4 MW, (5) a proposed tailrace emptying into the Salton Sea, (6) a proposed 8-mile-long, 12.5 kV transmission line, and (7) appurtenant facilities. The proposed project would have an annual generation of 64,000 MWh. k. Location of Application: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item g above. l. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. m. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely VerDate jul<14>2003 16:54 Jun 01, 2005 Jkt 205001 notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. n. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. o. Proposed Scope of Studies under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. p. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; See 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s web site under ‘‘efiling’’ link. The Commission strongly encourages electronic filing. q. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents PO 00000 Frm 00034 Fmt 4703 Sfmt 4703 must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. r. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Linda Mitry, Deputy Secretary. [FR Doc. E5–2779 Filed 6–1–05; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission Notice of Application Accepted For Filing and Soliciting Comments, Protests, and Motions To Intervene May 25, 2005. Take notice that the following hydroelectric application has been filed with the Commission and is available for public inspection: a. Type of Application: Preliminary Permit. b. Project No.: 12584–000. c. Date filed: April 19, 2005. d. Applicant: Loyalhanna Hydroelectric Company LLC. e. Name and Location of Project: The proposed Loyalhanna Hydroelectric Project would be located at the existing U.S. Corps of Engineers’ Loyalhanna Dam located on Loyalhanna Creek, near the Town of Saltsburg, Westmoreland County, Pennsylvania. The proposed project would utilize federal lands. f. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)—825(r). g. Applicant contact: Mr. Clifford Phillips, Advanced Hydro Solutions LLC, 150 North Miller Road, Suite 450 C, Fairlawn, OH 44333, (330) 869–8451. h. FERC Contact: Tom Papsidero, (202) 502–6002. E:\FR\FM\02JNN1.SGM 02JNN1 Federal Register / Vol. 70, No. 105 / Thursday, June 2, 2005 / Notices i. Deadline for filing comments, protests, and motions to intervene: 60 days from the issuance date of this notice. All documents (original and eight copies) should be filed with Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the Commission’s web site under the ‘‘e-Filing’’ link. The Commission strongly encourages electronic filings. Please include the project number (P– 12584–000) on any comments or motions filed. The Commission’s Rules of Practice and Procedure require all intervenors filing documents with the Commission to serve a copy of that document on each person in the official service list for the project. Further, if an intervenor files comments or documents with the Commission relating to the merits of an issue that may affect the responsibilities of a particular resource agency, they must also serve a copy of the document on that resource agency. j. Description of Project: The proposed project would utilize the existing U.S. Army Corps of Engineers’ Loyalhanna Dam and would consist of: (1) A new 200-foot-long, 10-foot-diameter penstock; (2) a new 50-foot-long, 30foot-wide, 20-foot-high powerhouse containing one or two generating units for a total installed capacity of 2.0–MW; (3) a new exhaust apron; (4) a new 3,960-foot-long, 14.7–kV transmission line; and (5) appurtenant facilities. k. Location of Applications: A copy of the application is available for inspection and reproduction at the Commission in the Public Reference Room or may be viewed on the Commission’s Web site at https:// www.ferc.gov using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, call toll-free 1–866–208– 3676 or e-mail FERCOnlineSupport@ferc.gov. For TTY, call (202) 502–8659. A copy is also available for inspection and reproduction at the address in item g above. l. Individuals desiring to be included on the Commission’s mailing list should so indicate by writing to the Secretary of the Commission. VerDate jul<14>2003 16:54 Jun 01, 2005 Jkt 205001 m. Competing Preliminary Permit— Anyone desiring to file a competing application for preliminary permit for a proposed project must submit the competing application itself, or a notice of intent to file such an application, to the Commission on or before the specified comment date for the particular application (see 18 CFR 4.36). Submission of a timely notice of intent allows an interested person to file the competing preliminary permit application no later than 30 days after the specified comment date for the particular application. A competing preliminary permit application must conform with 18 CFR 4.30(b) and 4.36. m. Competing Development Application—Any qualified development applicant desiring to file a competing development application must submit to the Commission, on or before a specified comment date for the particular application, either a competing development application or a notice of intent to file such an application. Submission of a timely notice of intent to file a development application allows an interested person to file the competing application no later than 120 days after the specified comment date for the particular application. A competing license application must conform with 18 CFR 4.30(b) and 4.36. n. Notice of Intent—A notice of intent must specify the exact name, business address, and telephone number of the prospective applicant, and must include an unequivocal statement of intent to submit, if such an application may be filed, either a preliminary permit application or a development application (specify which type of application). A notice of intent must be served on the applicant(s) named in this public notice. o. Proposed Scope of Studies under Permit—A preliminary permit, if issued, does not authorize construction. The term of the proposed preliminary permit would be 36 months. The work proposed under the preliminary permit would include economic analysis, preparation of preliminary engineering plans, and a study of environmental impacts. Based on the results of these studies, the Applicant would decide whether to proceed with the preparation of a development application to construct and operate the project. p. Comments, Protests, or Motions to Intervene—Anyone may submit comments, a protest, or a motion to PO 00000 Frm 00035 Fmt 4703 Sfmt 4703 32323 intervene in accordance with the requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, .214. In determining the appropriate action to take, the Commission will consider all protests or other comments filed, but only those who file a motion to intervene in accordance with the Commission’s Rules may become a party to the proceeding. Any comments, protests, or motions to intervene must be received on or before the specified comment date for the particular application. Comments, protests and interventions may be filed electronically via the Internet in lieu of paper; See 18 CFR 385.2001 (a)(1)(iii) and the instructions on the Commission’s web site under ‘‘efiling’’ link. The Commission strongly encourages electronic filing. q. Filing and Service of Responsive Documents—Any filings must bear in all capital letters the title ‘‘COMMENTS’’, ‘‘NOTICE OF INTENT TO FILE COMPETING APPLICATION’’, ‘‘COMPETING APPLICATION’’, ‘‘PROTEST’’, or ‘‘MOTION TO INTERVENE’’, as applicable, and the Project Number of the particular application to which the filing refers. Any of the above-named documents must be filed by providing the original and the number of copies provided by the Commission’s regulations to: The Secretary, Federal Energy Regulatory Commission, 888 First Street, NE, Washington, DC 20426. An additional copy must be sent to Director, Division of Hydropower Administration and Compliance, Federal Energy Regulatory Commission, at the above-mentioned address. A copy of any notice of intent, competing application or motion to intervene must also be served upon each representative of the Applicant specified in the particular application. r. Agency Comments—Federal, state, and local agencies are invited to file comments on the described application. A copy of the application may be obtained by agencies directly from the Applicant. If an agency does not file comments within the time specified for filing comments, it will be presumed to have no comments. One copy of an agency’s comments must also be sent to the Applicant’s representatives. Linda Mitry, Deputy Secretary. [FR Doc. E5–2780 Filed 6–1–05; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\02JNN1.SGM 02JNN1

Agencies

[Federal Register Volume 70, Number 105 (Thursday, June 2, 2005)]
[Notices]
[Pages 32322-32323]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-2780]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Application Accepted For Filing and Soliciting 
Comments, Protests, and Motions To Intervene

May 25, 2005.
    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection:
    a. Type of Application: Preliminary Permit.
    b. Project No.: 12584-000.
    c. Date filed: April 19, 2005.
    d. Applicant: Loyalhanna Hydroelectric Company LLC.
    e. Name and Location of Project: The proposed Loyalhanna 
Hydroelectric Project would be located at the existing U.S. Corps of 
Engineers' Loyalhanna Dam located on Loyalhanna Creek, near the Town of 
Saltsburg, Westmoreland County, Pennsylvania. The proposed project 
would utilize federal lands.
    f. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)--825(r).
    g. Applicant contact: Mr. Clifford Phillips, Advanced Hydro 
Solutions LLC, 150 North Miller Road, Suite 450 C, Fairlawn, OH 44333, 
(330) 869-8451.
    h. FERC Contact: Tom Papsidero, (202) 502-6002.

[[Page 32323]]

    i. Deadline for filing comments, protests, and motions to 
intervene: 60 days from the issuance date of this notice.
    All documents (original and eight copies) should be filed with 
Magalie R. Salas, Secretary, Federal Energy Regulatory Commission, 888 
First Street, NE., Washington, DC 20426. Comments, protests and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings. Please include the project 
number (P-12584-000) on any comments or motions filed.
    The Commission's Rules of Practice and Procedure require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person in the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    j. Description of Project: The proposed project would utilize the 
existing U.S. Army Corps of Engineers' Loyalhanna Dam and would consist 
of: (1) A new 200-foot-long, 10-foot-diameter penstock; (2) a new 50-
foot-long, 30-foot-wide, 20-foot-high powerhouse containing one or two 
generating units for a total installed capacity of 2.0-MW; (3) a new 
exhaust apron; (4) a new 3,960-foot-long, 14.7-kV transmission line; 
and (5) appurtenant facilities.
    k. Location of Applications: A copy of the application is available 
for inspection and reproduction at the Commission in the Public 
Reference Room or may be viewed on the Commission's Web site at https://
www.ferc.gov using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. For assistance, call toll-free 1-866-208-3676 or e-mail 
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is 
also available for inspection and reproduction at the address in item g 
above.
    l. Individuals desiring to be included on the Commission's mailing 
list should so indicate by writing to the Secretary of the Commission.
    m. Competing Preliminary Permit--Anyone desiring to file a 
competing application for preliminary permit for a proposed project 
must submit the competing application itself, or a notice of intent to 
file such an application, to the Commission on or before the specified 
comment date for the particular application (see 18 CFR 4.36). 
Submission of a timely notice of intent allows an interested person to 
file the competing preliminary permit application no later than 30 days 
after the specified comment date for the particular application. A 
competing preliminary permit application must conform with 18 CFR 
4.30(b) and 4.36.
    m. Competing Development Application--Any qualified development 
applicant desiring to file a competing development application must 
submit to the Commission, on or before a specified comment date for the 
particular application, either a competing development application or a 
notice of intent to file such an application. Submission of a timely 
notice of intent to file a development application allows an interested 
person to file the competing application no later than 120 days after 
the specified comment date for the particular application. A competing 
license application must conform with 18 CFR 4.30(b) and 4.36.
    n. Notice of Intent--A notice of intent must specify the exact 
name, business address, and telephone number of the prospective 
applicant, and must include an unequivocal statement of intent to 
submit, if such an application may be filed, either a preliminary 
permit application or a development application (specify which type of 
application). A notice of intent must be served on the applicant(s) 
named in this public notice.
    o. Proposed Scope of Studies under Permit--A preliminary permit, if 
issued, does not authorize construction. The term of the proposed 
preliminary permit would be 36 months. The work proposed under the 
preliminary permit would include economic analysis, preparation of 
preliminary engineering plans, and a study of environmental impacts. 
Based on the results of these studies, the Applicant would decide 
whether to proceed with the preparation of a development application to 
construct and operate the project.
    p. Comments, Protests, or Motions to Intervene--Anyone may submit 
comments, a protest, or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211, 
.214. In determining the appropriate action to take, the Commission 
will consider all protests or other comments filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    Comments, protests and interventions may be filed electronically 
via the Internet in lieu of paper; See 18 CFR 385.2001 (a)(1)(iii) and 
the instructions on the Commission's web site under ``e-filing'' link. 
The Commission strongly encourages electronic filing.
    q. Filing and Service of Responsive Documents--Any filings must 
bear in all capital letters the title ``COMMENTS'', ``NOTICE OF INTENT 
TO FILE COMPETING APPLICATION'', ``COMPETING APPLICATION'', 
``PROTEST'', or ``MOTION TO INTERVENE'', as applicable, and the Project 
Number of the particular application to which the filing refers. Any of 
the above-named documents must be filed by providing the original and 
the number of copies provided by the Commission's regulations to: The 
Secretary, Federal Energy Regulatory Commission, 888 First Street, NE, 
Washington, DC 20426. An additional copy must be sent to Director, 
Division of Hydropower Administration and Compliance, Federal Energy 
Regulatory Commission, at the above-mentioned address. A copy of any 
notice of intent, competing application or motion to intervene must 
also be served upon each representative of the Applicant specified in 
the particular application.
    r. Agency Comments--Federal, state, and local agencies are invited 
to file comments on the described application. A copy of the 
application may be obtained by agencies directly from the Applicant. If 
an agency does not file comments within the time specified for filing 
comments, it will be presumed to have no comments. One copy of an 
agency's comments must also be sent to the Applicant's representatives.

Linda Mitry,
Deputy Secretary.
[FR Doc. E5-2780 Filed 6-1-05; 8:45 am]
BILLING CODE 6717-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.