Nuclear Management Company, LLC; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing, 25619-25621 [E5-2378]

Download as PDF Federal Register / Vol. 70, No. 92 / Friday, May 13, 2005 / Notices • Subcommittee on Science and Engineering Indicators • Update on Engineering Education Workshop Closed Committee on Programs & Plans Subcommittee on Polar Issues (8 a.m.– 8:15 a.m.) Room 1235 • Polar icebreakers—future budget issues Committee on Strategy and Budget (11:10 a.m. –11:45 a.m.) Room 1235 • Preliminary Discussion of FY 2007 Budget Executive Committee (12:15 p.m.– 12:30 p.m.) Room 1235 • Director’s Items: Personnel Matters and Future Budgets Thursday, May 26, 2005 Open Committee on Audit & Oversight (9:15 a.m.–11:15 a.m.) Room 1235 • Approval of Minutes • Management Response to OIG Semiannual Report • Discussion of NSF Vision Document: NSB Roles and Responsibilities • Discussion of Draft Outline of NSF Merit Review System Review • The Sarbanes Oxley Act and Implications for the NSF • CFO Update on Plan to Address Reportable Conditions of FY 2004 Audit Closed Session Committee on Programs & Plans (7 a.m.–8:30 a.m.) Room 1235 • Update on RSVP • NSB Information Item: Plan for extending LIGO • NSB Information Item: Renewal of Cooperative Agreement between NSF and IRIS • Reexamination of Priority Order for New Start MREFC Projects Committee on Audit & Oversight (11:15 a.m.–11:45 a.m.) Room 1235 • Pending Investigations Executive Closed Committee on Programs & Plans (8:30 a.m.–9:15 a.m.) Room 1235 • Re-examination of Priority Order for New Start MREFC Projects Plenary Session of the Board (12 noon– 3:30 p.m.) Executive Closed Plenary Session of the Board (12 noon–12:30 p.m.) Room 1235 • Approval of Executive Closed Minutes • Executive Committee Elections • Board Member Proposals VerDate jul<14>2003 19:28 May 12, 2005 Jkt 205001 Closed Plenary Session of the Board (1 p.m.–1:30 p.m.) Room 1235 • Approval of Closed Session Minutes • Closed Committee Reports Open Plenary Session of the Board (1 p.m.–3:30 p.m.) Room 1235 • Approval of Open Session Minutes • Resolution to Close August 2005 Meeting • NSB Chairman’s Report Æ Approval of 2006 Board Meeting Calendar • NSF Director’s Report • Committee Reports Æ 2004 Annual Report of Executive Committee • Overview of Millennium Ecosystem Assessment • Presentations by 2005 Alan T. Waterman and NSB Public Service Awardees Michael P. Crosby, Executive Officer, NSB. [FR Doc. 05–9727 Filed 5–11–05; 1:47 pm] BILLING CODE 7555–01–M NUCLEAR REGULATORY COMMISSION [Docket No. 50–305] Nuclear Management Company, LLC; Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of an amendment to Facility Operating License No. DPR– 43 issued to Nuclear Management Company, LLC (the licensee), for operation of the Kewaunee Nuclear Power Plant located in Kewaunee County, Wisconsin. The proposed amendment would change the Technical Specifications to modify the auxiliary feedwater (AFW) pump suction protection requirements and change the design basis as described in the Updated Safety Analysis Report to revise the functionality of the discharge pressure switches to provide pump runout protection, which requires operator actions to restore the AFW pumps for specific post-accident recovery activities. Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s regulations. PO 00000 Frm 00099 Fmt 4703 Sfmt 4703 25619 The Commission has made a proposed determination that the amendment request involves no significant hazards consideration. Under the Commission’s regulations in Title 10 of the Code of Federal Regulations (10 CFR), Section 50.92, this means that operation of the facility in accordance with the proposed amendment would not (1) involve a significant increase in the probability or consequences of an accident previously evaluated; or (2) create the possibility of a new or different kind of accident from any accident previously evaluated; or (3) involve a significant reduction in a margin of safety. As required by 10 CFR 50.91(a), the licensee has provided its analysis of the issue of no significant hazards consideration, which is presented below: 1. Does the proposed amendment involve a significant increase in the probability or consequences of an accident previously evaluated? Response: No. The proposed amendment does not involve a significant increase in the probability of an accident previously evaluated. The proposed changes are associated with the auxiliary feedwater (AFW) system, which is not an initiator of any accident previously evaluated. The proposed amendment does not involve a significant increase in the consequences of an accident previously evaluated. The mitigation functions assumed in the accident analyses will continue to be performed. Operator actions may be required to assure the AFW pumps are aligned for post-accident recovery operations. With these actions additional consequences are not incurred. Therefore, operation of the facility in accordance [with] the proposed amendment would not involve a significant increase in the probability or consequences of any accident previously evaluated. 2. Does the proposed amendment create the possibility of a new or different kind of accident from any accident previously evaluated? Response: No. The AFW system is being modified by adding suction pressure switches to protect the AFW pumps from damage due to a loss of normal suction. The addition of the suction pressure switches and the associated circuitry does not introduce new failure modes or effects. The evaluation of the new suction pressure trip circuit design concluded the new suction pressure trip circuit is similar to the existing discharge pressure trip circuit design and therefore, no new failure modes or effects are introduced. In addition, the AFW system is being modified by altering the function of the discharge pressure trip channel to provide pump runout protection. Operator actions may be required to assure the AFW pumps are aligned for post-accident recovery operations. With these actions, the accident recovery operations can be performed and a new or different kind of accident is not E:\FR\FM\13MYN1.SGM 13MYN1 25620 Federal Register / Vol. 70, No. 92 / Friday, May 13, 2005 / Notices created. The proposed amendment ensures that the AFW system continues to performs its intended safety function. Therefore, operation of the facility in accordance with the proposed amendment does not create the possibility of a new or different kind of accident from any previously evaluated. 3. Does the proposed amendment involve a significant reduction in a margin of safety? Response: No. The modifications to the AFW System and the associated Technical Specifications will ensure that the AFW system is capable of performing its intended safety function. In addition, the margin of safety in the accident analyses is not affected by the proposed changes. The manual actions that may be required to restart an AFW pump and throttle AFW flow during the cooldown/recovery phase of the event do not significantly impact the margin of safety. Therefore, the proposed amendment does not involve a significant reduction in a margin of safety. The NRC staff has reviewed the licensee’s analysis and, based on this review, it appears that the three standards of 10 CFR 50.92(c) are satisfied. Therefore, the NRC staff proposes to determine that the amendment request involves no significant hazards consideration. The Commission is seeking public comments on this proposed determination. Any comments received within 30 days after the date of publication of this notice will be considered in making any final determination. Normally, the Commission will not issue the amendment until the expiration of 60 days after the date of publication of this notice. The Commission may issue the license amendment before expiration of the 60day period provided that its final determination is that the amendment involves no significant hazards consideration. In addition, the Commission may issue the amendment prior to the expiration of the 30-day comment period should circumstances change during the 30-day comment period such that failure to act in a timely way would result, for example in derating or shutdown of the facility. Should the Commission take action prior to the expiration of either the comment period or the notice period, it will publish in the Federal Register a notice of issuance. Should the Commission make a final No Significant Hazards Consideration Determination, any hearing will take place after issuance. The Commission expects that the need to take this action will occur very infrequently. Written comments may be submitted by mail to the Chief, Rules and Directives Branch, Division of VerDate jul<14>2003 15:59 May 12, 2005 Jkt 205001 Administrative Services, Office of Administration, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, and should cite the publication date and page number of this Federal Register notice. Written comments may also be delivered to Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Documents may be examined, and/or copied for a fee, at the NRC’s Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. The filing of requests for hearing and petitions for leave to intervene is discussed below. Within 60 days after the date of publication of this notice, the licensee may file a request for a hearing with respect to issuance of the amendment to the subject facility operating license and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene. Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission’s ‘‘Rules of Practice for Domestic Licensing Proceedings’’ in 10 CFR Part 2. Interested persons should consult a current copy of 10 CFR 2.309, which is available at the Commission’s PDR, located at One White Flint North, Public File Area O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/ reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is filed by the above date, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board will issue a notice of a hearing or an appropriate order. As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: (1) The PO 00000 Frm 00100 Fmt 4703 Sfmt 4703 name, address and telephone number of the requestor or petitioner; (2) the nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The petition must also identify the specific contentions which the petitioner/ requestor seeks to have litigated at the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner/requestor shall provide a brief explanation of the bases for the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner/requestor must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petition must include sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner to relief. A petitioner/requestor who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to participate fully in the conduct of the hearing. If a hearing is requested, the Commission will make a final determination on the issue of no significant hazards consideration. The final determination will serve to decide when the hearing is held. If the final determination is that the amendment request involves no significant hazards consideration, the Commission may issue the amendment and make it immediately effective, notwithstanding the request for a hearing. Any hearing held would take place after issuance of the amendment. If the final determination is that the amendment request involves a significant hazards consideration, any hearing held would take place before the issuance of any amendment. E:\FR\FM\13MYN1.SGM 13MYN1 Federal Register / Vol. 70, No. 92 / Friday, May 13, 2005 / Notices Nontimely requests and/or petitions and contentions will not be entertained absent a determination by the Commission or the presiding officer of the Atomic Safety and Licensing Board that the petition, request and/or the contentions should be granted based on a balancing of the factors specified in 10 CFR 2.309(c)(1)(i)–(viii). A request for a hearing or a petition for leave to intervene must be filed by: (1) First class mail addressed to the Office of the Secretary of the Commission, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, Attention: Rulemaking and Adjudications Staff; (2) courier, express mail, and expedited delivery services: Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and Adjudications Staff; (3) E-mail addressed to the Office of the Secretary, U.S. Nuclear Regulatory Commission, HEARINGDOCKET@NRC.GOV; or (4) facsimile transmission addressed to the Office of the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC, Attention: Rulemakings and Adjudications Staff at (301) 415–1101, verification number is (301) 415–1966. A copy of the request for hearing and petition for leave to intervene should also be sent to the Office of the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555– 0001, and it is requested that copies be transmitted either by means of facsimile transmission to 301–415–3725 or by email to OGCMailCenter@nrc.gov. A copy of the request for hearing and petition for leave to intervene should also be sent to Bradley D. Jackson, Esq., Foley and Lardner, P.O. Box 1497, Madison, WI 53701–1497, attorney for the licensee. For further details with respect to this action, see the application for amendment dated May 5, 2005, which is available for public inspection at the Commission’s PDR, located at One White Flint North, File Public Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https:// www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS, should contact the NRC PDR Reference staff by telephone at 1–800– 397–4209, 301–415–4737, or by e-mail to pdr@nrc.gov. VerDate jul<14>2003 15:59 May 12, 2005 Jkt 205001 Dated at Rockville, Maryland, this 9th day of May, 2005. Carl F. Lyon, Project Manager, Section 1 Project Directorate III , Division of Licensing Project Management, Office of Nuclear Reactor Regulation. [FR Doc. E5–2378 Filed 5–12–05; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–266 & 50–301] Nuclear Management Company, LLC; Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a Hearing The U.S. Nuclear Regulatory Commission (the Commission) is considering issuance of an amendment to Facility Operating License Nos. DPR– 24 and DPR–27, issued to Nuclear Management Company, LLC (NMC or the licensee), for operation of the Point Beach Nuclear Plant (PBNP), Units 1 and 2 located in Two Rivers, WI. The proposed amendment would alter the PBNP Final Safety Analysis Report (FSAR) to include a reactor vessel head drop event. Before issuance of the proposed license amendment, the Commission will have made findings required by the Atomic Energy Act of 1954, as amended (the Act), and the Commission’s regulations. Within 60 days after the date of publication of this notice, the licensee may file a request for a hearing with respect to issuance of the amendment to the subject facility operating license and any person whose interest may be affected by this proceeding and who wishes to participate as a party in the proceeding must file a written request for a hearing and a petition for leave to intervene. Requests for a hearing and a petition for leave to intervene shall be filed in accordance with the Commission’s ‘‘Rules of Practice for Domestic Licensing Proceedings’’ in 10 CFR part 2. Interested persons should consult a current copy of 10 CFR 2.309, which is available at the Commission’s PDR, located at One White Flint North, Public File Area 01F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible from the Agencywide Documents Access and Management System’s (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/ reading-rm/doc-collections/cfr/. If a request for a hearing or petition for leave to intervene is filed by the above PO 00000 Frm 00101 Fmt 4703 Sfmt 4703 25621 date, the Commission or a presiding officer designated by the Commission or by the Chief Administrative Judge of the Atomic Safety and Licensing Board Panel, will rule on the request and/or petition; and the Secretary or the Chief Administrative Judge of the Atomic Safety and Licensing Board will issue a notice of a hearing or an appropriate order. As required by 10 CFR 2.309, a petition for leave to intervene shall set forth with particularity the interest of the petitioner/requestor in the proceeding, and how that interest may be affected by the results of the proceeding. The petition should specifically explain the reasons why intervention should be permitted with particular reference to the following general requirements: (1) The name, address and telephone number of the requestor or petitioner; (2) the nature of the requestor’s/petitioner’s right under the Act to be made a party to the proceeding; (3) the nature and extent of the requestor’s/petitioner’s property, financial, or other interest in the proceeding; and (4) the possible effect of any decision or order which may be entered in the proceeding on the requestor’s/petitioner’s interest. The petition must also identify the specific contentions which the petitioner/ requestor seeks to have litigated at the proceeding. Each contention must consist of a specific statement of the issue of law or fact to be raised or controverted. In addition, the petitioner/requestor shall provide a brief explanation of the bases for the contention and a concise statement of the alleged facts or expert opinion which support the contention and on which the petitioner intends to rely in proving the contention at the hearing. The petitioner must also provide references to those specific sources and documents of which the petitioner is aware and on which the petitioner intends to rely to establish those facts or expert opinion. The petition must include sufficient information to show that a genuine dispute exists with the applicant on a material issue of law or fact. Contentions shall be limited to matters within the scope of the amendment under consideration. The contention must be one which, if proven, would entitle the petitioner/requestor to relief. A petitioner/requestor who fails to satisfy these requirements with respect to at least one contention will not be permitted to participate as a party. Those permitted to intervene become parties to the proceeding, subject to any limitations in the order granting leave to intervene, and have the opportunity to E:\FR\FM\13MYN1.SGM 13MYN1

Agencies

[Federal Register Volume 70, Number 92 (Friday, May 13, 2005)]
[Notices]
[Pages 25619-25621]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-2378]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-305]


Nuclear Management Company, LLC; Notice of Consideration of 
Issuance of Amendment to Facility Operating License, Proposed No 
Significant Hazards Consideration Determination, and Opportunity for a 
Hearing

    The U.S. Nuclear Regulatory Commission (the Commission) is 
considering issuance of an amendment to Facility Operating License No. 
DPR-43 issued to Nuclear Management Company, LLC (the licensee), for 
operation of the Kewaunee Nuclear Power Plant located in Kewaunee 
County, Wisconsin.
    The proposed amendment would change the Technical Specifications to 
modify the auxiliary feedwater (AFW) pump suction protection 
requirements and change the design basis as described in the Updated 
Safety Analysis Report to revise the functionality of the discharge 
pressure switches to provide pump runout protection, which requires 
operator actions to restore the AFW pumps for specific post-accident 
recovery activities.
    Before issuance of the proposed license amendment, the Commission 
will have made findings required by the Atomic Energy Act of 1954, as 
amended (the Act), and the Commission's regulations.
    The Commission has made a proposed determination that the amendment 
request involves no significant hazards consideration. Under the 
Commission's regulations in Title 10 of the Code of Federal Regulations 
(10 CFR), Section 50.92, this means that operation of the facility in 
accordance with the proposed amendment would not (1) involve a 
significant increase in the probability or consequences of an accident 
previously evaluated; or (2) create the possibility of a new or 
different kind of accident from any accident previously evaluated; or 
(3) involve a significant reduction in a margin of safety. As required 
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue 
of no significant hazards consideration, which is presented below:

    1. Does the proposed amendment involve a significant increase in 
the probability or consequences of an accident previously evaluated?
    Response: No.
    The proposed amendment does not involve a significant increase 
in the probability of an accident previously evaluated. The proposed 
changes are associated with the auxiliary feedwater (AFW) system, 
which is not an initiator of any accident previously evaluated.
    The proposed amendment does not involve a significant increase 
in the consequences of an accident previously evaluated. The 
mitigation functions assumed in the accident analyses will continue 
to be performed. Operator actions may be required to assure the AFW 
pumps are aligned for post-accident recovery operations. With these 
actions additional consequences are not incurred.
    Therefore, operation of the facility in accordance [with] the 
proposed amendment would not involve a significant increase in the 
probability or consequences of any accident previously evaluated.
    2. Does the proposed amendment create the possibility of a new 
or different kind of accident from any accident previously 
evaluated?
    Response: No.
    The AFW system is being modified by adding suction pressure 
switches to protect the AFW pumps from damage due to a loss of 
normal suction. The addition of the suction pressure switches and 
the associated circuitry does not introduce new failure modes or 
effects. The evaluation of the new suction pressure trip circuit 
design concluded the new suction pressure trip circuit is similar to 
the existing discharge pressure trip circuit design and therefore, 
no new failure modes or effects are introduced. In addition, the AFW 
system is being modified by altering the function of the discharge 
pressure trip channel to provide pump runout protection. Operator 
actions may be required to assure the AFW pumps are aligned for 
post-accident recovery operations. With these actions, the accident 
recovery operations can be performed and a new or different kind of 
accident is not

[[Page 25620]]

created. The proposed amendment ensures that the AFW system 
continues to performs its intended safety function.
    Therefore, operation of the facility in accordance with the 
proposed amendment does not create the possibility of a new or 
different kind of accident from any previously evaluated.
    3. Does the proposed amendment involve a significant reduction 
in a margin of safety?
    Response: No.
    The modifications to the AFW System and the associated Technical 
Specifications will ensure that the AFW system is capable of 
performing its intended safety function. In addition, the margin of 
safety in the accident analyses is not affected by the proposed 
changes. The manual actions that may be required to restart an AFW 
pump and throttle AFW flow during the cooldown/recovery phase of the 
event do not significantly impact the margin of safety.
    Therefore, the proposed amendment does not involve a significant 
reduction in a margin of safety.

    The NRC staff has reviewed the licensee's analysis and, based on 
this review, it appears that the three standards of 10 CFR 50.92(c) are 
satisfied. Therefore, the NRC staff proposes to determine that the 
amendment request involves no significant hazards consideration.
    The Commission is seeking public comments on this proposed 
determination. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendment until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment 
involves no significant hazards consideration. In addition, the 
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day 
comment period such that failure to act in a timely way would result, 
for example in derating or shutdown of the facility. Should the 
Commission take action prior to the expiration of either the comment 
period or the notice period, it will publish in the Federal Register a 
notice of issuance. Should the Commission make a final No Significant 
Hazards Consideration Determination, any hearing will take place after 
issuance. The Commission expects that the need to take this action will 
occur very infrequently.
    Written comments may be submitted by mail to the Chief, Rules and 
Directives Branch, Division of Administrative Services, Office of 
Administration, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001, and should cite the publication date and page number of 
this Federal Register notice. Written comments may also be delivered to 
Room 6D59, Two White Flint North, 11545 Rockville Pike, Rockville, 
Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays. Documents may 
be examined, and/or copied for a fee, at the NRC's Public Document Room 
(PDR), located at One White Flint North, Public File Area O1 F21, 11555 
Rockville Pike (first floor), Rockville, Maryland.
    The filing of requests for hearing and petitions for leave to 
intervene is discussed below.
    Within 60 days after the date of publication of this notice, the 
licensee may file a request for a hearing with respect to issuance of 
the amendment to the subject facility operating license and any person 
whose interest may be affected by this proceeding and who wishes to 
participate as a party in the proceeding must file a written request 
for a hearing and a petition for leave to intervene. Requests for a 
hearing and a petition for leave to intervene shall be filed in 
accordance with the Commission's ``Rules of Practice for Domestic 
Licensing Proceedings'' in 10 CFR Part 2. Interested persons should 
consult a current copy of 10 CFR 2.309, which is available at the 
Commission's PDR, located at One White Flint North, Public File Area 
O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland. 
Publicly available records will be accessible from the Agencywide 
Documents Access and Management System's (ADAMS) Public Electronic 
Reading Room on the Internet at the NRC Web site, https://www.nrc.gov/
reading-rm/doc-collections/cfr/. If a request for a hearing or petition 
for leave to intervene is filed by the above date, the Commission or a 
presiding officer designated by the Commission or by the Chief 
Administrative Judge of the Atomic Safety and Licensing Board Panel, 
will rule on the request and/or petition; and the Secretary or the 
Chief Administrative Judge of the Atomic Safety and Licensing Board 
will issue a notice of a hearing or an appropriate order.
    As required by 10 CFR 2.309, a petition for leave to intervene 
shall set forth with particularity the interest of the petitioner in 
the proceeding, and how that interest may be affected by the results of 
the proceeding. The petition should specifically explain the reasons 
why intervention should be permitted with particular reference to the 
following general requirements: (1) The name, address and telephone 
number of the requestor or petitioner; (2) the nature of the 
requestor's/petitioner's right under the Act to be made a party to the 
proceeding; (3) the nature and extent of the requestor's/petitioner's 
property, financial, or other interest in the proceeding; and (4) the 
possible effect of any decision or order which may be entered in the 
proceeding on the requestor's/petitioner's interest. The petition must 
also identify the specific contentions which the petitioner/requestor 
seeks to have litigated at the proceeding.
    Each contention must consist of a specific statement of the issue 
of law or fact to be raised or controverted. In addition, the 
petitioner/requestor shall provide a brief explanation of the bases for 
the contention and a concise statement of the alleged facts or expert 
opinion which support the contention and on which the petitioner 
intends to rely in proving the contention at the hearing. The 
petitioner/requestor must also provide references to those specific 
sources and documents of which the petitioner is aware and on which the 
petitioner intends to rely to establish those facts or expert opinion. 
The petition must include sufficient information to show that a genuine 
dispute exists with the applicant on a material issue of law or fact. 
Contentions shall be limited to matters within the scope of the 
amendment under consideration. The contention must be one which, if 
proven, would entitle the petitioner to relief. A petitioner/requestor 
who fails to satisfy these requirements with respect to at least one 
contention will not be permitted to participate as a party.
    Those permitted to intervene become parties to the proceeding, 
subject to any limitations in the order granting leave to intervene, 
and have the opportunity to participate fully in the conduct of the 
hearing.
    If a hearing is requested, the Commission will make a final 
determination on the issue of no significant hazards consideration. The 
final determination will serve to decide when the hearing is held. If 
the final determination is that the amendment request involves no 
significant hazards consideration, the Commission may issue the 
amendment and make it immediately effective, notwithstanding the 
request for a hearing. Any hearing held would take place after issuance 
of the amendment. If the final determination is that the amendment 
request involves a significant hazards consideration, any hearing held 
would take place before the issuance of any amendment.

[[Page 25621]]

    Nontimely requests and/or petitions and contentions will not be 
entertained absent a determination by the Commission or the presiding 
officer of the Atomic Safety and Licensing Board that the petition, 
request and/or the contentions should be granted based on a balancing 
of the factors specified in 10 CFR 2.309(c)(1)(i)-(viii).
    A request for a hearing or a petition for leave to intervene must 
be filed by: (1) First class mail addressed to the Office of the 
Secretary of the Commission, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001, Attention: Rulemaking and Adjudications 
Staff; (2) courier, express mail, and expedited delivery services: 
Office of the Secretary, Sixteenth Floor, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and 
Adjudications Staff; (3) E-mail addressed to the Office of the 
Secretary, U.S. Nuclear Regulatory Commission, HEARINGDOCKET@NRC.GOV; 
or (4) facsimile transmission addressed to the Office of the Secretary, 
U.S. Nuclear Regulatory Commission, Washington, DC, Attention: 
Rulemakings and Adjudications Staff at (301) 415-1101, verification 
number is (301) 415-1966. A copy of the request for hearing and 
petition for leave to intervene should also be sent to the Office of 
the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001, and it is requested that copies be transmitted either by 
means of facsimile transmission to 301-415-3725 or by email to 
OGCMailCenter@nrc.gov. A copy of the request for hearing and petition 
for leave to intervene should also be sent to Bradley D. Jackson, Esq., 
Foley and Lardner, P.O. Box 1497, Madison, WI 53701-1497, attorney for 
the licensee.
    For further details with respect to this action, see the 
application for amendment dated May 5, 2005, which is available for 
public inspection at the Commission's PDR, located at One White Flint 
North, File Public Area O1 F21, 11555 Rockville Pike (first floor), 
Rockville, Maryland. Publicly available records will be accessible from 
the Agencywide Documents Access and Management System's (ADAMS) Public 
Electronic Reading Room on the Internet at the NRC Web site, https://
www.nrc.gov/reading-rm/adams.html. Persons who do not have access to 
ADAMS or who encounter problems in accessing the documents located in 
ADAMS, should contact the NRC PDR Reference staff by telephone at 1-
800-397-4209, 301-415-4737, or by e-mail to pdr@nrc.gov.

    Dated at Rockville, Maryland, this 9th day of May, 2005.
Carl F. Lyon,
Project Manager, Section 1 Project Directorate III , Division of 
Licensing Project Management, Office of Nuclear Reactor Regulation.
[FR Doc. E5-2378 Filed 5-12-05; 8:45 am]
BILLING CODE 7590-01-P