Southern Nuclear Operating Company; Vogtle Electric Generating Plant, Units 1 and 2; Exemption, 22928-22929 [E5-2109]
Download as PDF
22928
Federal Register / Vol. 70, No. 84 / Tuesday, May 3, 2005 / Notices
NUCLEAR REGULATORY
COMMISSION
[Docket Nos. 50–424 and 50–425]
Southern Nuclear Operating Company;
Vogtle Electric Generating Plant, Units
1 and 2; Exemption
1.0
Background
The Southern Nuclear Operating
Company (SNC or the licensee) is the
holder of Facility Operating License
Nos. NPF–68 and NPF–81 that
authorizes operation of Vogtle Electric
Generating Plant (VEGP), Units 1 and 2.
The license provides, among other
things, that the facility is subject to all
rules, regulations, and orders of the
Nuclear Regulatory Commission (NRC,
the Commission) now or hereafter in
effect.
The facility consists of two
pressurized-water reactors located in
Burke County, Georgia.
2.0
Request/Action
Section IV.F.2.b and c of Appendix E,
to Title 10 of the Code of Federal
Regulations (10 CFR) Part 50 requires
the licensee at each site to conduct an
exercise of its onsite emergency plans
and offsite emergency plans biennially
with full participation by each offsite
authority having a role under the plan.
During such biennial full participation
exercises, the NRC evaluates onsite and
the Federal Emergency Management
Agency (FEMA) evaluates offsite
emergency preparedness activities,
including interaction with it’s various
State and local emergency management
agencies. SNC’s previously scheduled
full-participation exercise at VEGP was
successfully conducted during the week
of June 12, 2002.
The licensee had scheduled a fullparticipation exercise for September
2004, however, FEMA requested that
the exercise be postponed to enable the
Georgia Emergency Management
Agency to respond to multiple
hurricanes. FEMA subsequently
consulted with the States of Georgia and
South Carolina, and in a letter to the
Georgia Emergency Management
Agency dated November 23, 2004,
FEMA approved rescheduling the fullparticipation exercise to February 2005.
Under the current regulations, the
licensee would have had until
December 31, 2004, to complete it’s next
full-participation exercise.
By letter dated December 10, 2004,
the licensee requested an exemption
from Section IV.F.2.e of Appendix E to
10 CFR part 50 regarding the
requirement to conduct a biennial fullparticipation exercise. The NRC staff
VerDate jul<14>2003
15:43 May 02, 2005
Jkt 205001
determined that the requirements of
Section IV.F.2.e are not applicable to the
circumstances of the licensee’s request
and, accordingly, no exemption from
those requirements is being granted.
However, the NRC staff has determined
that the requirements of Appendix E to
10 CFR part 50, Sections IV.F.2.b and
2.c are applicable to the circumstances
of the licensee’s request and that an
exemption from those requirements is
appropriate.
3.0 Discussion
The Commission, pursuant to 10 CFR
50.12(a)(1), may grant exemptions from
the requirements of 10 CFR part 50 that
are authorized by law, will not present
an undue risk to public health and
safety, and are consistent with the
common defense and security. The
Commission, however, pursuant to 10
CFR 50.12(a)(2), will not consider
granting an exemption unless special
circumstances are present. Under 10
CFR 50.12(a)(2)(ii), special
circumstances are present when
application of the regulation in the
particular circumstances would not
serve the underlying purpose of the rule
or is not necessary to achieve the
underlying purpose of the rule. Under
10 CFR 50.12(a)(2)(v), special
circumstances are present whenever the
exemption would provide only
temporary relief from the applicable
regulation and the licensee or applicant
has made good faith efforts to comply
with the regulation.
The underlying purpose for
conducting a biennial full-participation
exercise is to ensure that emergency
organization personnel are familiar with
their duties and to test the adequacy of
emergency plans. In order to
accommodate scheduling of a full
participation exercise, the NRC has
allowed licensees to schedule the
exercises at any time during the
calendar biennium. Conducting the
VEGP full-participation exercise in
calendar year 2005 as proposed places
the exercise past the previously
scheduled biennial calender year of
2004.
Since the last full-participation
exercise conducted at VEGP, Units 1
and 2 on June 12, 2002, VEGP
conducted two annual Full Scale Plume
Phase exercises on November 5, 2003,
and June 30, 2004, and an off-hour/
unannounced exercise on November 8,
2004. Six other emergency plan drills
have also been conducted since June
2002. The NRC staff considers that the
intent of this requirement is met by
having conducted these series of
exercises and drills. The NRC staff
considers that these measures are
PO 00000
Frm 00088
Fmt 4703
Sfmt 4703
adequate to maintain an acceptable level
of emergency preparedness during this
period, satisfying the underlying
purpose of the rule. Therefore, the
special circumstances of 10 CFR
50.12(a)(2)(ii) are satisfied.
The licensee also stated in its letter
dated December 10, 2004, that only
temporary relief from the regulation is
requested for the exemption, since
VEGP will resume its normal biennial
exercise cycle in 2006. The NRC staff
also found that the licensee made a good
faith effort to comply with the
regulation by originally scheduling the
full participation exercise within the
calendar biennium, in accordance with
the regulation. The exemption is being
sought by the licensee in response to a
request by FEMA to reschedule the
exercise. As documented in FEMA letter
dated November 23, 2004, the Georgia
Emergency Management Agency was
unable to support the original schedule
for the exercise due to a series of severe
weather events that impacted its
available resources. FEMA, in
consultation with the States of Georgia
and South Carolina, proposed a
rescheduled date for the exercise that is
beyond that allowed by the regulations.
The NRC staff, having considered the
schedule and resource issues associated
with those agencies that participate in
and evaluate the offsite portion of fullparticipation exercises, concludes that
the licensee made a good faith effort to
meet the requirements of the regulation.
The NRC staff, therefore, concludes that
the exemption request meets the special
circumstances of 10 CFR 50.12(a)(2)(v)
and should be granted.
4.0
Conclusion
Accordingly, the Commission has
determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by
law, will not present an undue risk to
the public health and safety, and is
consistent with the common defense
and security. Also, special
circumstances are present. Therefore,
the Commission hereby grants SNC an
exemption from the requirements of 10
CFR part 50, Appendix E, Section
IV.F.2.b and c for VEGP, Units 1 and 2.
Pursuant to 10 CFR 51.32, the
Commission has determined that the
granting of this exemption will not have
a significant effect on the quality of the
human environment (70 FR 19108).
This exemption is effective upon
issuance.
Dated at Rockville, Maryland, this 13th day
of April 2005.
E:\FR\FM\03MYN1.SGM
03MYN1
22929
Federal Register / Vol. 70, No. 84 / Tuesday, May 3, 2005 / Notices
For the Nuclear Regulatory Commission.
Ledyard B. Marsh,
Director, Division of Licensing Project
Management, Office of Nuclear Reactor
Regulation.
[FR Doc. E5–2109 Filed 5–2–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Request to Amend a License for the
Export of Radioactive Waste
Pursuant to 10 CFR 110.70(b)(4)
‘‘Public notice of receipt of an
Regulatory Commission, Washington DC
20555; the Secretary, U.S. Nuclear
Regulatory Commission, Washington,
DC 20555; and the Executive Secretary,
U.S. Department of State, Washington,
DC 20520.
In its review of the application for a
license to export radioactive waste as
defined in 10 CFR part 110 and noticed
herein, the Commission does not
evaluate the health, safety or
environmental effects in the recipient
nation of the material to be exported.
The information concerning the
application follows.
application,’’ please take notice that the
Nuclear Regulatory Commission has
received the following request for an
export license. Copies of the request can
be accessed through the Public
Electronic Reading Room (PERR) link
https://www.nrc.gov/reading-rm/
adams.html at the NRC Homepage.
A request for a hearing or petition for
leave to intervene may be filed within
30 days after publication of this notice
in the Federal Register. Any request for
hearing or petition for leave to intervene
shall be served by the requestor or
petitioner upon the applicant, the Office
of the General Counsel, U.S. Nuclear
NRC APPLICATION TO AMEND LICENSE FOR THE EXPORT OF RADIOACTIVE WASTE
Description of material
Name of applicant and
date of application*
Material type
Total quantity (qty)
Westinghouse Electric
Company LLC.
Class A Radioactive
Waste—(contaminated
scrap metals).
February 3, 2005 ...............
...........................................
End use
Increase the total qty of
scrap metal from
149,320.0 kgs to
562,320.0 kgs and increase the total qty of
low enriched uranium
contaminanats to 9.0
kgs U–235 contained in
215 kgs uranium.
...........................................
For decontamination and
recovery for commercial
use.
Country of destination
Canada
Extend expiration date
from 12/31/10 to 12/31/
15.
February 7, 2005 XW003/
03 11005171.
* Date received, application number and docket number
For the Nuclear Regulatory Commission.
Dated this 26th day of April 2005 at
Rockville, Maryland.
Margaret M. Doane,
Deputy Director, Office of International
Programs.
[FR Doc. E5–2106 Filed 5–2–05; 8:45 am]
BILLING CODE 7590–01–P
Week of May 9, 2005—Tentative
Week of May 30, 2005—Tentative
Wednesday, May 11, 2005
Wednesday, June 1, 2005
10:30 a.m. All Employees Meeting
(Public Meeting).
1:30 p.m. All Employees Meeting
(Public Meeting).
9:30 a.m. Discussion of Security
Issues (Closed—Ex. 1).
Week of May 16, 2005—Tentative
NUCLEAR REGULATORY
COMMISSION
There are no meetings scheduled for
the week of May 16, 2005.
Sunshine Act; Meetings
Week of May 23, 2005—Tentative
AGENCY HOLDING THE MEETING:
Nuclear
1:30 p.m. Discussion of Security
Issues (Closed—Ex. 1).
Regulatory Commission.
Weeks of May 2, 9, 16, 23, 30,
June 6, 2005.
DATE:
Wednesday, May 25, 2005
Commissioners’ Conference
Room, 11555 Rockville Pike, Rockville,
Maryland.
PLACE:
STATUS:
Public and closed.
MATTERS TO BE CONSIDERED:
Week of May 2, 2005
There are no meetings scheduled for
the week of May 2, 2005.
VerDate jul<14>2003
16:54 May 02, 2005
Jkt 205001
Monday, May 23, 2005
9:30 a.m. Briefing on Results of the
Agency Action Review Meeting (Public
Meeting) (Contact: Lois James, 301–415–
1112).
This meeting will be webcast live at
the Web address—https://www.nrc.gov.
1:30 p.m. Briefing on Threat
Environment Assessment (Closed—Ex.
1).
PO 00000
Frm 00089
Fmt 4703
Sfmt 4703
Thursday, June 2, 2005
9:30 a.m. Briefing on Office of
International Programs (OIP) Programs,
Performance, and Plans (Public
Meeting) (Contact: Margie Doane, 301–
415–2344).
This meeting will be webcast live at
the Web address—https://www.nrc.gov.
1:30 p.m. Discussion of Management
Issues (Closed—Ex. 2 & 9).
Week of June 6, 2005—Tentative
There are no meetings scheduled for
the week of June 6, 2005.
* The schedule for Commission
meetings is subject to change on short
notice. To verify the status of meetings
call (recording)—(301) 415–1292.
Contact person for more information:
Dave Gamberoni, (301) 415–1651.
*
*
*
*
*
The NRC Commission Meeting
Schedule can be found on the Internet
E:\FR\FM\03MYN1.SGM
03MYN1
Agencies
[Federal Register Volume 70, Number 84 (Tuesday, May 3, 2005)]
[Notices]
[Pages 22928-22929]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-2109]
[[Page 22928]]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-424 and 50-425]
Southern Nuclear Operating Company; Vogtle Electric Generating
Plant, Units 1 and 2; Exemption
1.0 Background
The Southern Nuclear Operating Company (SNC or the licensee) is the
holder of Facility Operating License Nos. NPF-68 and NPF-81 that
authorizes operation of Vogtle Electric Generating Plant (VEGP), Units
1 and 2. The license provides, among other things, that the facility is
subject to all rules, regulations, and orders of the Nuclear Regulatory
Commission (NRC, the Commission) now or hereafter in effect.
The facility consists of two pressurized-water reactors located in
Burke County, Georgia.
2.0 Request/Action
Section IV.F.2.b and c of Appendix E, to Title 10 of the Code of
Federal Regulations (10 CFR) Part 50 requires the licensee at each site
to conduct an exercise of its onsite emergency plans and offsite
emergency plans biennially with full participation by each offsite
authority having a role under the plan. During such biennial full
participation exercises, the NRC evaluates onsite and the Federal
Emergency Management Agency (FEMA) evaluates offsite emergency
preparedness activities, including interaction with it's various State
and local emergency management agencies. SNC's previously scheduled
full-participation exercise at VEGP was successfully conducted during
the week of June 12, 2002.
The licensee had scheduled a full-participation exercise for
September 2004, however, FEMA requested that the exercise be postponed
to enable the Georgia Emergency Management Agency to respond to
multiple hurricanes. FEMA subsequently consulted with the States of
Georgia and South Carolina, and in a letter to the Georgia Emergency
Management Agency dated November 23, 2004, FEMA approved rescheduling
the full-participation exercise to February 2005. Under the current
regulations, the licensee would have had until December 31, 2004, to
complete it's next full-participation exercise.
By letter dated December 10, 2004, the licensee requested an
exemption from Section IV.F.2.e of Appendix E to 10 CFR part 50
regarding the requirement to conduct a biennial full-participation
exercise. The NRC staff determined that the requirements of Section
IV.F.2.e are not applicable to the circumstances of the licensee's
request and, accordingly, no exemption from those requirements is being
granted. However, the NRC staff has determined that the requirements of
Appendix E to 10 CFR part 50, Sections IV.F.2.b and 2.c are applicable
to the circumstances of the licensee's request and that an exemption
from those requirements is appropriate.
3.0 Discussion
The Commission, pursuant to 10 CFR 50.12(a)(1), may grant
exemptions from the requirements of 10 CFR part 50 that are authorized
by law, will not present an undue risk to public health and safety, and
are consistent with the common defense and security. The Commission,
however, pursuant to 10 CFR 50.12(a)(2), will not consider granting an
exemption unless special circumstances are present. Under 10 CFR
50.12(a)(2)(ii), special circumstances are present when application of
the regulation in the particular circumstances would not serve the
underlying purpose of the rule or is not necessary to achieve the
underlying purpose of the rule. Under 10 CFR 50.12(a)(2)(v), special
circumstances are present whenever the exemption would provide only
temporary relief from the applicable regulation and the licensee or
applicant has made good faith efforts to comply with the regulation.
The underlying purpose for conducting a biennial full-participation
exercise is to ensure that emergency organization personnel are
familiar with their duties and to test the adequacy of emergency plans.
In order to accommodate scheduling of a full participation exercise,
the NRC has allowed licensees to schedule the exercises at any time
during the calendar biennium. Conducting the VEGP full-participation
exercise in calendar year 2005 as proposed places the exercise past the
previously scheduled biennial calender year of 2004.
Since the last full-participation exercise conducted at VEGP, Units
1 and 2 on June 12, 2002, VEGP conducted two annual Full Scale Plume
Phase exercises on November 5, 2003, and June 30, 2004, and an off-
hour/unannounced exercise on November 8, 2004. Six other emergency plan
drills have also been conducted since June 2002. The NRC staff
considers that the intent of this requirement is met by having
conducted these series of exercises and drills. The NRC staff considers
that these measures are adequate to maintain an acceptable level of
emergency preparedness during this period, satisfying the underlying
purpose of the rule. Therefore, the special circumstances of 10 CFR
50.12(a)(2)(ii) are satisfied.
The licensee also stated in its letter dated December 10, 2004,
that only temporary relief from the regulation is requested for the
exemption, since VEGP will resume its normal biennial exercise cycle in
2006. The NRC staff also found that the licensee made a good faith
effort to comply with the regulation by originally scheduling the full
participation exercise within the calendar biennium, in accordance with
the regulation. The exemption is being sought by the licensee in
response to a request by FEMA to reschedule the exercise. As documented
in FEMA letter dated November 23, 2004, the Georgia Emergency
Management Agency was unable to support the original schedule for the
exercise due to a series of severe weather events that impacted its
available resources. FEMA, in consultation with the States of Georgia
and South Carolina, proposed a rescheduled date for the exercise that
is beyond that allowed by the regulations.
The NRC staff, having considered the schedule and resource issues
associated with those agencies that participate in and evaluate the
offsite portion of full-participation exercises, concludes that the
licensee made a good faith effort to meet the requirements of the
regulation. The NRC staff, therefore, concludes that the exemption
request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and
should be granted.
4.0 Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
50.12(a), the exemption is authorized by law, will not present an undue
risk to the public health and safety, and is consistent with the common
defense and security. Also, special circumstances are present.
Therefore, the Commission hereby grants SNC an exemption from the
requirements of 10 CFR part 50, Appendix E, Section IV.F.2.b and c for
VEGP, Units 1 and 2.
Pursuant to 10 CFR 51.32, the Commission has determined that the
granting of this exemption will not have a significant effect on the
quality of the human environment (70 FR 19108).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 13th day of April 2005.
[[Page 22929]]
For the Nuclear Regulatory Commission.
Ledyard B. Marsh,
Director, Division of Licensing Project Management, Office of Nuclear
Reactor Regulation.
[FR Doc. E5-2109 Filed 5-2-05; 8:45 am]
BILLING CODE 7590-01-P