Southern Nuclear Operating Company; Vogtle Electric Generating Plant, Units 1 and 2; Exemption, 22928-22929 [E5-2109]

Download as PDF 22928 Federal Register / Vol. 70, No. 84 / Tuesday, May 3, 2005 / Notices NUCLEAR REGULATORY COMMISSION [Docket Nos. 50–424 and 50–425] Southern Nuclear Operating Company; Vogtle Electric Generating Plant, Units 1 and 2; Exemption 1.0 Background The Southern Nuclear Operating Company (SNC or the licensee) is the holder of Facility Operating License Nos. NPF–68 and NPF–81 that authorizes operation of Vogtle Electric Generating Plant (VEGP), Units 1 and 2. The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the Nuclear Regulatory Commission (NRC, the Commission) now or hereafter in effect. The facility consists of two pressurized-water reactors located in Burke County, Georgia. 2.0 Request/Action Section IV.F.2.b and c of Appendix E, to Title 10 of the Code of Federal Regulations (10 CFR) Part 50 requires the licensee at each site to conduct an exercise of its onsite emergency plans and offsite emergency plans biennially with full participation by each offsite authority having a role under the plan. During such biennial full participation exercises, the NRC evaluates onsite and the Federal Emergency Management Agency (FEMA) evaluates offsite emergency preparedness activities, including interaction with it’s various State and local emergency management agencies. SNC’s previously scheduled full-participation exercise at VEGP was successfully conducted during the week of June 12, 2002. The licensee had scheduled a fullparticipation exercise for September 2004, however, FEMA requested that the exercise be postponed to enable the Georgia Emergency Management Agency to respond to multiple hurricanes. FEMA subsequently consulted with the States of Georgia and South Carolina, and in a letter to the Georgia Emergency Management Agency dated November 23, 2004, FEMA approved rescheduling the fullparticipation exercise to February 2005. Under the current regulations, the licensee would have had until December 31, 2004, to complete it’s next full-participation exercise. By letter dated December 10, 2004, the licensee requested an exemption from Section IV.F.2.e of Appendix E to 10 CFR part 50 regarding the requirement to conduct a biennial fullparticipation exercise. The NRC staff VerDate jul<14>2003 15:43 May 02, 2005 Jkt 205001 determined that the requirements of Section IV.F.2.e are not applicable to the circumstances of the licensee’s request and, accordingly, no exemption from those requirements is being granted. However, the NRC staff has determined that the requirements of Appendix E to 10 CFR part 50, Sections IV.F.2.b and 2.c are applicable to the circumstances of the licensee’s request and that an exemption from those requirements is appropriate. 3.0 Discussion The Commission, pursuant to 10 CFR 50.12(a)(1), may grant exemptions from the requirements of 10 CFR part 50 that are authorized by law, will not present an undue risk to public health and safety, and are consistent with the common defense and security. The Commission, however, pursuant to 10 CFR 50.12(a)(2), will not consider granting an exemption unless special circumstances are present. Under 10 CFR 50.12(a)(2)(ii), special circumstances are present when application of the regulation in the particular circumstances would not serve the underlying purpose of the rule or is not necessary to achieve the underlying purpose of the rule. Under 10 CFR 50.12(a)(2)(v), special circumstances are present whenever the exemption would provide only temporary relief from the applicable regulation and the licensee or applicant has made good faith efforts to comply with the regulation. The underlying purpose for conducting a biennial full-participation exercise is to ensure that emergency organization personnel are familiar with their duties and to test the adequacy of emergency plans. In order to accommodate scheduling of a full participation exercise, the NRC has allowed licensees to schedule the exercises at any time during the calendar biennium. Conducting the VEGP full-participation exercise in calendar year 2005 as proposed places the exercise past the previously scheduled biennial calender year of 2004. Since the last full-participation exercise conducted at VEGP, Units 1 and 2 on June 12, 2002, VEGP conducted two annual Full Scale Plume Phase exercises on November 5, 2003, and June 30, 2004, and an off-hour/ unannounced exercise on November 8, 2004. Six other emergency plan drills have also been conducted since June 2002. The NRC staff considers that the intent of this requirement is met by having conducted these series of exercises and drills. The NRC staff considers that these measures are PO 00000 Frm 00088 Fmt 4703 Sfmt 4703 adequate to maintain an acceptable level of emergency preparedness during this period, satisfying the underlying purpose of the rule. Therefore, the special circumstances of 10 CFR 50.12(a)(2)(ii) are satisfied. The licensee also stated in its letter dated December 10, 2004, that only temporary relief from the regulation is requested for the exemption, since VEGP will resume its normal biennial exercise cycle in 2006. The NRC staff also found that the licensee made a good faith effort to comply with the regulation by originally scheduling the full participation exercise within the calendar biennium, in accordance with the regulation. The exemption is being sought by the licensee in response to a request by FEMA to reschedule the exercise. As documented in FEMA letter dated November 23, 2004, the Georgia Emergency Management Agency was unable to support the original schedule for the exercise due to a series of severe weather events that impacted its available resources. FEMA, in consultation with the States of Georgia and South Carolina, proposed a rescheduled date for the exercise that is beyond that allowed by the regulations. The NRC staff, having considered the schedule and resource issues associated with those agencies that participate in and evaluate the offsite portion of fullparticipation exercises, concludes that the licensee made a good faith effort to meet the requirements of the regulation. The NRC staff, therefore, concludes that the exemption request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and should be granted. 4.0 Conclusion Accordingly, the Commission has determined that, pursuant to 10 CFR 50.12(a), the exemption is authorized by law, will not present an undue risk to the public health and safety, and is consistent with the common defense and security. Also, special circumstances are present. Therefore, the Commission hereby grants SNC an exemption from the requirements of 10 CFR part 50, Appendix E, Section IV.F.2.b and c for VEGP, Units 1 and 2. Pursuant to 10 CFR 51.32, the Commission has determined that the granting of this exemption will not have a significant effect on the quality of the human environment (70 FR 19108). This exemption is effective upon issuance. Dated at Rockville, Maryland, this 13th day of April 2005. E:\FR\FM\03MYN1.SGM 03MYN1 22929 Federal Register / Vol. 70, No. 84 / Tuesday, May 3, 2005 / Notices For the Nuclear Regulatory Commission. Ledyard B. Marsh, Director, Division of Licensing Project Management, Office of Nuclear Reactor Regulation. [FR Doc. E5–2109 Filed 5–2–05; 8:45 am] BILLING CODE 7590–01–P NUCLEAR REGULATORY COMMISSION Request to Amend a License for the Export of Radioactive Waste Pursuant to 10 CFR 110.70(b)(4) ‘‘Public notice of receipt of an Regulatory Commission, Washington DC 20555; the Secretary, U.S. Nuclear Regulatory Commission, Washington, DC 20555; and the Executive Secretary, U.S. Department of State, Washington, DC 20520. In its review of the application for a license to export radioactive waste as defined in 10 CFR part 110 and noticed herein, the Commission does not evaluate the health, safety or environmental effects in the recipient nation of the material to be exported. The information concerning the application follows. application,’’ please take notice that the Nuclear Regulatory Commission has received the following request for an export license. Copies of the request can be accessed through the Public Electronic Reading Room (PERR) link https://www.nrc.gov/reading-rm/ adams.html at the NRC Homepage. A request for a hearing or petition for leave to intervene may be filed within 30 days after publication of this notice in the Federal Register. Any request for hearing or petition for leave to intervene shall be served by the requestor or petitioner upon the applicant, the Office of the General Counsel, U.S. Nuclear NRC APPLICATION TO AMEND LICENSE FOR THE EXPORT OF RADIOACTIVE WASTE Description of material Name of applicant and date of application* Material type Total quantity (qty) Westinghouse Electric Company LLC. Class A Radioactive Waste—(contaminated scrap metals). February 3, 2005 ............... ........................................... End use Increase the total qty of scrap metal from 149,320.0 kgs to 562,320.0 kgs and increase the total qty of low enriched uranium contaminanats to 9.0 kgs U–235 contained in 215 kgs uranium. ........................................... For decontamination and recovery for commercial use. Country of destination Canada Extend expiration date from 12/31/10 to 12/31/ 15. February 7, 2005 XW003/ 03 11005171. * Date received, application number and docket number For the Nuclear Regulatory Commission. Dated this 26th day of April 2005 at Rockville, Maryland. Margaret M. Doane, Deputy Director, Office of International Programs. [FR Doc. E5–2106 Filed 5–2–05; 8:45 am] BILLING CODE 7590–01–P Week of May 9, 2005—Tentative Week of May 30, 2005—Tentative Wednesday, May 11, 2005 Wednesday, June 1, 2005 10:30 a.m. All Employees Meeting (Public Meeting). 1:30 p.m. All Employees Meeting (Public Meeting). 9:30 a.m. Discussion of Security Issues (Closed—Ex. 1). Week of May 16, 2005—Tentative NUCLEAR REGULATORY COMMISSION There are no meetings scheduled for the week of May 16, 2005. Sunshine Act; Meetings Week of May 23, 2005—Tentative AGENCY HOLDING THE MEETING: Nuclear 1:30 p.m. Discussion of Security Issues (Closed—Ex. 1). Regulatory Commission. Weeks of May 2, 9, 16, 23, 30, June 6, 2005. DATE: Wednesday, May 25, 2005 Commissioners’ Conference Room, 11555 Rockville Pike, Rockville, Maryland. PLACE: STATUS: Public and closed. MATTERS TO BE CONSIDERED: Week of May 2, 2005 There are no meetings scheduled for the week of May 2, 2005. VerDate jul<14>2003 16:54 May 02, 2005 Jkt 205001 Monday, May 23, 2005 9:30 a.m. Briefing on Results of the Agency Action Review Meeting (Public Meeting) (Contact: Lois James, 301–415– 1112). This meeting will be webcast live at the Web address—https://www.nrc.gov. 1:30 p.m. Briefing on Threat Environment Assessment (Closed—Ex. 1). PO 00000 Frm 00089 Fmt 4703 Sfmt 4703 Thursday, June 2, 2005 9:30 a.m. Briefing on Office of International Programs (OIP) Programs, Performance, and Plans (Public Meeting) (Contact: Margie Doane, 301– 415–2344). This meeting will be webcast live at the Web address—https://www.nrc.gov. 1:30 p.m. Discussion of Management Issues (Closed—Ex. 2 & 9). Week of June 6, 2005—Tentative There are no meetings scheduled for the week of June 6, 2005. * The schedule for Commission meetings is subject to change on short notice. To verify the status of meetings call (recording)—(301) 415–1292. Contact person for more information: Dave Gamberoni, (301) 415–1651. * * * * * The NRC Commission Meeting Schedule can be found on the Internet E:\FR\FM\03MYN1.SGM 03MYN1

Agencies

[Federal Register Volume 70, Number 84 (Tuesday, May 3, 2005)]
[Notices]
[Pages 22928-22929]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-2109]



[[Page 22928]]

-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-424 and 50-425]


Southern Nuclear Operating Company; Vogtle Electric Generating 
Plant, Units 1 and 2; Exemption

1.0 Background

    The Southern Nuclear Operating Company (SNC or the licensee) is the 
holder of Facility Operating License Nos. NPF-68 and NPF-81 that 
authorizes operation of Vogtle Electric Generating Plant (VEGP), Units 
1 and 2. The license provides, among other things, that the facility is 
subject to all rules, regulations, and orders of the Nuclear Regulatory 
Commission (NRC, the Commission) now or hereafter in effect.
    The facility consists of two pressurized-water reactors located in 
Burke County, Georgia.

2.0 Request/Action

    Section IV.F.2.b and c of Appendix E, to Title 10 of the Code of 
Federal Regulations (10 CFR) Part 50 requires the licensee at each site 
to conduct an exercise of its onsite emergency plans and offsite 
emergency plans biennially with full participation by each offsite 
authority having a role under the plan. During such biennial full 
participation exercises, the NRC evaluates onsite and the Federal 
Emergency Management Agency (FEMA) evaluates offsite emergency 
preparedness activities, including interaction with it's various State 
and local emergency management agencies. SNC's previously scheduled 
full-participation exercise at VEGP was successfully conducted during 
the week of June 12, 2002.
    The licensee had scheduled a full-participation exercise for 
September 2004, however, FEMA requested that the exercise be postponed 
to enable the Georgia Emergency Management Agency to respond to 
multiple hurricanes. FEMA subsequently consulted with the States of 
Georgia and South Carolina, and in a letter to the Georgia Emergency 
Management Agency dated November 23, 2004, FEMA approved rescheduling 
the full-participation exercise to February 2005. Under the current 
regulations, the licensee would have had until December 31, 2004, to 
complete it's next full-participation exercise.
    By letter dated December 10, 2004, the licensee requested an 
exemption from Section IV.F.2.e of Appendix E to 10 CFR part 50 
regarding the requirement to conduct a biennial full-participation 
exercise. The NRC staff determined that the requirements of Section 
IV.F.2.e are not applicable to the circumstances of the licensee's 
request and, accordingly, no exemption from those requirements is being 
granted. However, the NRC staff has determined that the requirements of 
Appendix E to 10 CFR part 50, Sections IV.F.2.b and 2.c are applicable 
to the circumstances of the licensee's request and that an exemption 
from those requirements is appropriate.

3.0 Discussion

    The Commission, pursuant to 10 CFR 50.12(a)(1), may grant 
exemptions from the requirements of 10 CFR part 50 that are authorized 
by law, will not present an undue risk to public health and safety, and 
are consistent with the common defense and security. The Commission, 
however, pursuant to 10 CFR 50.12(a)(2), will not consider granting an 
exemption unless special circumstances are present. Under 10 CFR 
50.12(a)(2)(ii), special circumstances are present when application of 
the regulation in the particular circumstances would not serve the 
underlying purpose of the rule or is not necessary to achieve the 
underlying purpose of the rule. Under 10 CFR 50.12(a)(2)(v), special 
circumstances are present whenever the exemption would provide only 
temporary relief from the applicable regulation and the licensee or 
applicant has made good faith efforts to comply with the regulation.
    The underlying purpose for conducting a biennial full-participation 
exercise is to ensure that emergency organization personnel are 
familiar with their duties and to test the adequacy of emergency plans. 
In order to accommodate scheduling of a full participation exercise, 
the NRC has allowed licensees to schedule the exercises at any time 
during the calendar biennium. Conducting the VEGP full-participation 
exercise in calendar year 2005 as proposed places the exercise past the 
previously scheduled biennial calender year of 2004.
    Since the last full-participation exercise conducted at VEGP, Units 
1 and 2 on June 12, 2002, VEGP conducted two annual Full Scale Plume 
Phase exercises on November 5, 2003, and June 30, 2004, and an off-
hour/unannounced exercise on November 8, 2004. Six other emergency plan 
drills have also been conducted since June 2002. The NRC staff 
considers that the intent of this requirement is met by having 
conducted these series of exercises and drills. The NRC staff considers 
that these measures are adequate to maintain an acceptable level of 
emergency preparedness during this period, satisfying the underlying 
purpose of the rule. Therefore, the special circumstances of 10 CFR 
50.12(a)(2)(ii) are satisfied.
    The licensee also stated in its letter dated December 10, 2004, 
that only temporary relief from the regulation is requested for the 
exemption, since VEGP will resume its normal biennial exercise cycle in 
2006. The NRC staff also found that the licensee made a good faith 
effort to comply with the regulation by originally scheduling the full 
participation exercise within the calendar biennium, in accordance with 
the regulation. The exemption is being sought by the licensee in 
response to a request by FEMA to reschedule the exercise. As documented 
in FEMA letter dated November 23, 2004, the Georgia Emergency 
Management Agency was unable to support the original schedule for the 
exercise due to a series of severe weather events that impacted its 
available resources. FEMA, in consultation with the States of Georgia 
and South Carolina, proposed a rescheduled date for the exercise that 
is beyond that allowed by the regulations.
    The NRC staff, having considered the schedule and resource issues 
associated with those agencies that participate in and evaluate the 
offsite portion of full-participation exercises, concludes that the 
licensee made a good faith effort to meet the requirements of the 
regulation. The NRC staff, therefore, concludes that the exemption 
request meets the special circumstances of 10 CFR 50.12(a)(2)(v) and 
should be granted.

4.0 Conclusion

    Accordingly, the Commission has determined that, pursuant to 10 CFR 
50.12(a), the exemption is authorized by law, will not present an undue 
risk to the public health and safety, and is consistent with the common 
defense and security. Also, special circumstances are present. 
Therefore, the Commission hereby grants SNC an exemption from the 
requirements of 10 CFR part 50, Appendix E, Section IV.F.2.b and c for 
VEGP, Units 1 and 2.
    Pursuant to 10 CFR 51.32, the Commission has determined that the 
granting of this exemption will not have a significant effect on the 
quality of the human environment (70 FR 19108).
    This exemption is effective upon issuance.

    Dated at Rockville, Maryland, this 13th day of April 2005.


[[Page 22929]]


    For the Nuclear Regulatory Commission.
Ledyard B. Marsh,
Director, Division of Licensing Project Management, Office of Nuclear 
Reactor Regulation.
[FR Doc. E5-2109 Filed 5-2-05; 8:45 am]
BILLING CODE 7590-01-P
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.