17246
Federal Register / Vol. 70, No. 64 / Tuesday, April 5, 2005 / Notices
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would use the Keno
Dam and reservoir licensed to
PacifiCorp for Project No. 2082 and
would consist of: (1) A proposed
powerhouse containing a generating
unit having an installed capacity of 3.8
megawatts; (2) a proposed 0.5-mile-long
12.5 kilovolt transmission line; and (3)
appurtenant facilities. The project
would have an annual generation of
13.7 Gigawatt-hours, which would be
sold to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h.
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
VerDate jul<14>2003
19:48 Apr 04, 2005
Jkt 205001
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
PO 00000
Frm 00019
Fmt 4703
Sfmt 4703
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
t. Agency Comments—Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–1508 Filed 4–4–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
March 29, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
permit.
b. Project No.: 12568–000.
c. Date filed: December 22, 2004.
d. Applicant: Black Brook
Environmental. Inc.
e. Name of Project: Bagley Creek
Project.
f. Location: On Bagley Creek, in
Whatcom County, Washington. The
existing diversion structure is owned by
the U.S. Forest Service. The project
would also use lands within the Mount
Baker-Snoqualmie National Forest.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)—825(r).
h. Applicant Contact: Mr. Jason M.
Hines, P. O. Box 1691, Bellingham, WA
98225, (360) 603–4053.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Deadline for filing comments,
protests, and motions to intervene: 60
days from the issuance date of this
notice.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
E:\FR\FM\05APN1.SGM
05APN1
Federal Register / Vol. 70, No. 64 / Tuesday, April 5, 2005 / Notices
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would consist of: (1)
An existing 67-foot-long, 15-foot-high
diversion structure, (2) an existing
impoundment having a surface area of
6.5 acres and storage capacity of 20 acrefeet and normal water surface elevation
of 4,195 feet mean sea level, (3) a
proposed 7,500-foot-long, 16-inchdiameter steel penstock, (4) a proposed
powerhouse containing a generating
unit having an installed capacity of 800
kilowatts, (5) a proposed 7,000-footlong, 4.16 kilovolt transmission line,
and (6) appurtenant facilities. The
project would have an annual
generation of 5.1 gigawatt-hours that
would be sold to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, call toll-free
1–866–208–3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY,
call (202) 502–8659. A copy is also
available for inspection and
reproduction at the address in item h
above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit—
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application—Any qualified
development applicant desiring to file a
competing development application
must submit to the Commission, on or
before a specified comment date for the
particular application, either a
VerDate jul<14>2003
19:48 Apr 04, 2005
Jkt 205001
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with18 CFR
4.30(b) and 4.36.
p. Notice of Intent—A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies under
Permit—A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; See 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title—
COMMENTS’’, ‘‘RECOMMENDATIONS
FOR TERMS AND CONDITIONS’’,
‘‘PROTEST’’, OR ‘‘MOTION TO
INTERVENE’’, as applicable, and the
Project Number of the particular
PO 00000
Frm 00020
Fmt 4703
Sfmt 4703
17247
application to which the filing refers.
Any of the above-named documents
must be filed by providing the original
and the number of copies provided by
the Commission’s regulations to: The
Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE.,
Washington, DC 20426. A copy of any
motion to intervene must also be served
upon each representative of the
Applicant specified in the particular
application.
t. Agency Comments—Federal, state,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–1509 Filed 4–4–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Project No. 7321–018]
Erie Boulevard Hydropower, L.P. ;
Notice of Application Ready for
Environmental Analysis and Soliciting
Comments, Recommendations, Terms
and Conditions, and Prescriptions
March 28, 2005.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
license.
b. Project No.: P–7321–018.
c. Date filed: November 26, 2004.
d. Applicant: Erie Boulevard
Hydropower, L.P.
e. Name of Project: Macomb Project.
f. Location: On the Salmon River in
Franklin County, near Malone, New
York. This project does not occupy
federal lands.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Jerry L. Sabattis,
Erie Boulevard Hydropower, L.P., 225
Greenfield Parkway, Suite 201,
Liverpool, NY 13088, (315) 413–2787.
i. FERC Contact: John Smith, (202)
502–8972 or john.smith@ferc.gov.
j. Deadline for filing comments,
recommendations, terms and
conditions, and prescriptions is 60 days
E:\FR\FM\05APN1.SGM
05APN1
Agencies
[Federal Register Volume 70, Number 64 (Tuesday, April 5, 2005)]
[Notices]
[Pages 17246-17247]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-1509]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepted for Filing and Soliciting Motions
To Intervene, Protests, and Comments
March 29, 2005.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12568-000.
c. Date filed: December 22, 2004.
d. Applicant: Black Brook Environmental. Inc.
e. Name of Project: Bagley Creek Project.
f. Location: On Bagley Creek, in Whatcom County, Washington. The
existing diversion structure is owned by the U.S. Forest Service. The
project would also use lands within the Mount Baker-Snoqualmie National
Forest.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)--825(r).
h. Applicant Contact: Mr. Jason M. Hines, P. O. Box 1691,
Bellingham, WA 98225, (360) 603-4053.
i. FERC Contact: Robert Bell, (202) 502-6062.
j. Deadline for filing comments, protests, and motions to
intervene: 60 days from the issuance date of this notice.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an
[[Page 17247]]
issue that may affect the responsibilities of a particular resource
agency, they must also serve a copy of the document on that resource
agency.
k. Description of Project: The proposed project would consist of:
(1) An existing 67-foot-long, 15-foot-high diversion structure, (2) an
existing impoundment having a surface area of 6.5 acres and storage
capacity of 20 acre-feet and normal water surface elevation of 4,195
feet mean sea level, (3) a proposed 7,500-foot-long, 16-inch-diameter
steel penstock, (4) a proposed powerhouse containing a generating unit
having an installed capacity of 800 kilowatts, (5) a proposed 7,000-
foot-long, 4.16 kilovolt transmission line, and (6) appurtenant
facilities. The project would have an annual generation of 5.1
gigawatt-hours that would be sold to a local utility.
l. Locations of Applications: A copy of the application is
available for inspection and reproduction at the Commission in the
Public Reference Room, located at 888 First Street NE., Room 2A,
Washington DC 20426, or by calling (202) 502-8371. This filing may also
be viewed on the Commission's Web site at https://www.ferc.gov using the
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, call toll-free 1-866-208-3676 or e-mail
FERCOnlineSupport@ferc.gov. For TTY, call (202) 502-8659. A copy is
also available for inspection and reproduction at the address in item h
above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit--Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR
4.30(b) and 4.36.
o. Competing Development Application--Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with18 CFR 4.30(b) and 4.36.
p. Notice of Intent--A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies under Permit--A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions to Intervene--Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; See 18 CFR 385.2001 (a)(1)(iii) and
the instructions on the Commission's web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents--Any filings must
bear in all capital letters the title--COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', OR ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. Any of the above-named documents must be filed
by providing the original and the number of copies provided by the
Commission's regulations to: The Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426. A copy of any
motion to intervene must also be served upon each representative of the
Applicant specified in the particular application.
t. Agency Comments--Federal, state, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file comments within the time specified for filing
comments, it will be presumed to have no comments. One copy of an
agency's comments must also be sent to the Applicant's representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5-1509 Filed 4-4-05; 8:45 am]