Contractors' Safety for Ammunition and Explosives, 16038-16077 [05-5429]
Download as PDF
16038
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
DEPARTMENT OF DEFENSE
Office of the Secretary
32 CFR Part 184
RIN 0790–AH76
[DoD 4145.26–M]
Contractors’ Safety for Ammunition
and Explosives
Office of the Secretary of
Defense.
ACTION: Proposed rule for comment.
AGENCY:
The Department of Defense
(DoD) is codifying its revised explosives
safety standards for ammunition and
explosives (A&E) work performed under
DoD contracts. This proposed rule is
necessary to minimize the potential for
mishaps that could interrupt DoD
operations, delay project completion
dates, adversely impact DoD production
base or capability, damage or destroy
DoD-owned material/equipment, cause
injury to DoD personnel, or endanger
the general public. The benefits of this
proposed rule in terms of the protection
of the public and ensuring contract
performance are expected to balance its
potential cost or administrative impacts.
Only provisions related to conventional
AE operations have been included in
this proposed rule. No attempt was
made to encompass general industrial
safety, occupational health concerns,
chemical warfare agents, radiation, or
over-the-road transportation
requirements, because these are either
the responsibility of other regulatory
agencies (for example DOT, DOL/OSHA,
or NRC) or may be addressed elsewhere
in the contract by the procuring activity.
Budgetary effects of this proposed rule
are minimal since existing DoD Federal
Acquisition Regulation Supplement
coverage already requires compliance
with safety requirements in AE
solicitations and contracts. Finally,
because this proposed rule is needed to
minimize the potential for AE mishaps
that could adversely impact DoD and
the public, timely publication in the
Federal Register is important.
DATES: Comments are to be received not
later than May 31, 2005.
FOR FURTHER INFORMATION CONTACT: Dr.
Jerry M. Ward, Director, Engineer
Technical Programs Division, DDESB,
telephone (703) 325–2525, fax: (703)
325–6227; e-mail:
Jerry.Ward@DDESB.OSD.mil.
SUMMARY:
Pursuant
to the authority vested in the Secretary
of Defense in accordance with 10 U.S.C.
172, DoD Directive 6055.9 established
SUPPLEMENTARY INFORMATION:
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
the Department of Defense Explosives
Safety Board as a joint activity of the
Department of Defense subject to the
direction, authority and control of the
Secretary of Defense. The majority of the
standards impacting upon the public
were adopted prior to the enactment of
the Administrative Procedure Act. This
proposed rule is intended to ensure
public awareness of the extent of the
explosives safety standards as well as
offer the public an opportunity to
comment on the standards. The
information addresses the HCSDS
sometimes furnished with solicitations
or contracts to provide an insight into
potentially hazardous characteristics of
the materials involved in the production
of the item addressed in the solicitation.
Contractors retain the ultimate
responsibility for assuring the safety of
their personnel and establishment.
Information provided by the HCSDS is
derived from other sources. Verification
of such data as shipping and storage
hazard division and storage
compatibility group information must
be done through the DoD Joint Hazard
Classification System (JHCS) or Title 49,
Code of Federal Regulations.
These classifications pertain to AE
packaged for transportation or storage.
Such hazard classification information
may not be valid when applied to the
hazards associated with manufacturing
or loading processes. For such
processes, the materials and processes
must be analyzed on a case-by-case
basis. Sources of information to support
this analysis are available from service
research and development organizations
through contract channels and other
sources.
promulgated, shall be exempt from the
requirements under 5 U.S.C. 601–612.
This proposed rule does not have a
significant economic impact on small
entities as defined in the Act.
Executive Order 12866
This proposed rule does not:
(1) Have an annual effect of the
economy of $100 million or more or
adversely affect in a material way the
economy, a sector of the economy,
productivity, competition, jobs, the
environment, public health or safety, or
state, local, or tribal governments.
(2) Create a serious inconsistency or
otherwise interfere with an action taken
or planned by another agency.
(3) Materially alter the budgetary
impact of entitlement, grants, user fees,
or loan programs or the rights and
obligations of recipients thereof; or
(4) Raise novel legal or policy issues
arising out of legal mandates, the
President’s priorities, or the principles
set forth in this Executive Order.
List of Subjects in 32 CFR Part 184
Regulatory Flexibility Act of 1980 (5
U.S.C. 605(b))
Regulatory Flexibility Act. It has been
certified that this proposed rule, if
PO 00000
Frm 00002
Fmt 4701
Sfmt 4702
Unfunded Mandates Act of 1995 (Sec.
202, Pub. L. 104–4)
This proposed regulatory action does
not contain a Federal mandate that will
result in the expenditure by State, local,
and tribal governments, in aggregate, or
by the private sector of $100 million or
more in any one year.
Paperwork Reduction Act of 1995 (44
U.S.C. Chapter 35)
Paperwork Reduction Act. The
proposed rule imposes no obligatory
information requirements beyond
internal Department of Defense needs.
Federalism (Executive Order 13132)
This proposed regulatory action does
not have federalism implications, as set
forth in Executive Order 13132. It will
not have substantial direct effects on the
States, on the relationship between the
national government and the States, or
on the distribution of power and
responsibilities among the various
levels of government.
Section 202, Public Law 104–4,
‘‘Unfunded Mandates Reform Act’’
It has been determined that this rule
does not involve a Federal mandate that
may result in the expenditure by State,
local and tribal governments, in the
aggregate, or by the private sector, of
$100 million or more and that such
rulemaking will not significantly or
uniquely affect small governments.
Ammunition and explosives, DoD
contractors.
Accordingly, 32 CFR part 184 is
proposed to be added to read as follows:
PART 184—DOD CONTRACTORS’
SAFETY MANUAL
Sec.
184.1 Introduction.
184.2 Mishap investigation and reporting.
184.3 General safety requirements.
184.4 Quantity-distance and siting.
184.5 Hazard classification, storage
principles, and compatibility groups.
184.6 Electrical safety requirements for AE
facilities.
184.7 Manufacturing and processing
propellants.
184.8 Safety requirements for
manufacturing and processing
pyrotechnics.
184.9 Storage of ammunition and
explosives.
184.10 Fire protection.
184.11 Risk identification and management.
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
184.12 AE building design and layout.
184.13 Safety requirements for specific AE
and AE operations.
184.14 Test and testing requirements.
184.15 Collection and destruction
requirements for AE.
184.16 Construction and siting criteria.
Appendix A to 32 CFR Part 184—Glossary
Authority: 10 U.S.C. 172.
§ 184.1
Introduction.
(a) Purpose. This part provides safety
requirements, guidance and information
to minimize potential mishaps which
could interrupt Department of Defense
(DoD) operations, delay production,
damage DoD property, cause injury to
DoD personnel, or endanger the public
during contract work or services
involving ammunition and explosives
(AE). The part contains the minimum
contractual safety requirements to
support the objectives of DoD. These
requirements are not a complete safety
program and this part does not relieve
a contractor from complying with
Federal, State and local laws and
regulations.
(b) Applicability. These safety
requirements apply to contractors
performing AE work or AE services on
DoD contracts, subcontracts, purchase
orders, or other procurement methods.
The requirements also apply to non-DoD
contractor operations to the extent
necessary to protect DoD work or
services.
(c) Mandatory and advisory
requirements. The part uses the term
‘‘shall’’, or an affirmative statement, to
indicate mandatory requirements. The
terms ‘‘should’’ and ‘‘may’’ are advisory.
When advisory provisions are not met,
adverse consequences might develop
and become proximate causes of AE
mishaps.
(d) Compliance with mandatory
requirements. (1) The Department of
Defense requires compliance with
mandatory provisions of this part and
applicable portions of DoD 6055.9–
STD.1 Siting criteria for AE are provided
in quantity distance (Q–D) standards
contained in Chapter 9 of DoD 6055.9–
STD. In order to provide consistent and
current information to all DoD AE
contractors, Q–D requirements of DoD
6055.9–STD are incorporated by
reference in paragraph C317.
(2) Waivers. Procuring contracting
officers (PCO) may grant contractspecific waivers to mandatory
provisions of this part. Rationale for
waiver of DoD pre-award safety surveys
must be documented and provided to
the cognizant ACO for transmittal to the
1 Copies may be obtained via Internet at https://
www.dtic.mil/whs/directives.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
cognizant DoD Component explosives
safety office for their records. Military or
commercial ammunition and explosives
shall not be procured unless their use is
authorized by the cognizant DoD
Component explosives safety approval
authority. Methods of addressing noncompliance with mandatory
requirements and requests for waivers
are different during the pre- and postaward phases of a contract.
(3) In the pre-award phase, the PCO
will request a DoD pre-award safety
survey to help determine contractor
capability. During pre-award surveys,
noncompliance with mandatory safety
requirements normally results in a
recommendation of ‘‘no award.’’ Any
noncompliance should be resolved
during the pre-award survey.
Contractors may choose to correct the
deficiencies immediately, may offer a
letter of intent to correct the deficiencies
(which will become binding upon
award of contract), or may request that
the PCO accept specifically identified
existing conditions of facilities
(contract-specific waiver).
(4) In the post-award phase, the
contractor has 30 days from the date of
notification by the administrative
contracting officer (ACO) to correct the
noncompliance and inform the ACO of
the corrective actions taken. The
contracting officer may direct a different
time period for the correction of any
noncompliance. If the contractor refuses
or fails to correct any noncompliance
within the time period specified by the
ACO, the Government has the right to
direct the contractor to cease
performance on all or part of affected
contracts. When the contractor cannot
comply with the mandatory safety
requirements of the contract, the
contractor will develop and submit a
request for a waiver through the ACO to
the PCO for the final determination. The
request will contain complete
information concerning the
requirements violated, actions planned
to minimize the hazard, and a proposed
date for correction of the deficiency.
(e) Pre-award safety survey. DoD
safety personnel conduct pre-award
surveys to evaluate each prospective
contractor’s ability to comply with
contract safety requirements. The preaward safety survey is also an
opportunity for the contractor to request
clarification of any safety requirement
or other AE issue that may affect the
contractor’s ability to comply. During
pre-award surveys, the contractor shall
provide the following:
(1) Site plans conforming to
paragraphs (h)(5)(i) through (h)(5)(iv) of
this section for proposed facilities to be
used in contract performance.
PO 00000
Frm 00003
Fmt 4701
Sfmt 4702
16039
(2) Evidence of implementation of a
safety program containing at least
mandatory requirements described in
§ 184.3.
(3) General description of proposed
contract facilities, including size,
building layouts, construction details,
and fire resistive capabilities.
(4) Fire prevention program and
available firefighting resources
including local agreements or other
documentation demonstrating
coordination.
(5) Copies of required licenses and
permits or demonstration of the ability
to obtain approvals necessary to support
the proposed contract.
(6) A safety history including mishap
experience, safety survey or audit
reports by insurance carriers or Federal,
State, and local authorities, and any
variances, exemptions or waivers of
safety or fire protection requirements
issued by Federal, state or local
authorities.
(7) Details of proposed operations and
equipment to include process flow
narrative/diagram, proposed facility or
equipment changes, hazard analysis,
and proposed procedures for all phases
of AE operations.
(8) Subcontractor information. (i)
Identification of all subcontractors
proposed for the AE work.
(ii) Methods used to evaluate
capability of subcontractor to comply
with the requirements of this part.
(iii) Methods used to manage
subcontractor compliance.
(f) Preoperational safety survey. The
DoD reserves the right to conduct a
preoperational survey after contract
award of new items with limited
contractor experience, after major new
construction or major modifications, or
after an AE mishap. When these
situations occur, the contractor shall
notify the ACO, sufficiently in advance,
to provide the Department of Defense
the opportunity to schedule and
perform a preoperational survey.
(g) Post-award contractor
responsibilities. The contractor shall:
(1) Comply with the requirements of
this part and any other safety
requirements contained within the
contract.
(2) Develop and implement a
demonstrable safety program, including
operational procedures, intended to
prevent AE-related mishaps.
(3) Designate qualified individuals to
administer and implement this safety
program.
(4) Prepare, and keep available for
review, all hazard analyses used to
justify alternative methods of hazards
control that differ from those
recommended in this part.
E:\FR\FM\29MRP2.SGM
29MRP2
16040
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(5) Provide access to facilities and
safety program documentation to
Government safety representatives.
(6) Report and investigate AE mishaps
in accordance with § 184.2.
(7) Provide identification and location
of subcontractors to the ACO for
notification or approval in accordance
with terms of the contract.
(8) Establish and implement
management controls to ensure AE
subcontractors comply with paragraphs
(g)(1) through (g)(7) of this section.
(h) Site and construction plans. (1)
Contractors must prepare site and
construction plans for support of the
pre-award process, and for any change
in layout or construction potentially
affecting Q–D incident to the contract.
Contractors shall also maintain a current
site map depicting Q–D relationships for
all AE locations within the facilities.
(2) When the place of performance of
the contract is at a DoD-owned facility,
site and construction plans shall be
prepared and processed (content and
staffing) in accordance with the
requirements of DoD 6055.9–STD, as
well as, appropriate military service
regulations contained within the
contract.
(3) For contractor-owned, contractoroperated (COCO) facilities, the
contractor shall submit, through the
ACO to the PCO, site and construction
plans for all new construction or major
modification of facilities for AE
activities and for the facilities that may
be exposed to AE hazards if improperly
located. The contractor shall provide
sufficient copies for the review process.
The contractor shall not begin
construction or modification of
proposed facilities until receiving site
and construction plan approval from the
PCO through the ACO.
(4) Minor new construction, changes,
and modifications of existing AE
facilities involving Hazard Class/
Division (HC/D) additions and deletions
or that add or remove small portable
operating buildings and magazines may
not require formal site plan submission.
Minor applies to all changes that
involve only 1.4 HC/D materials. Minor
also applies to changes of other HC/D
materials that do not increase the
existing maximum credible event (MCE)
for an AE facility or do not extend any
quantity distance arcs beyond existing
fragment, inhabited building, and public
traffic route distance arcs for other
nearby potential explosion sites (PES).
When the contractor thinks a
modification/change is minor, he shall
notify the ACO and request a
determination. The ACO shall make the
final determination as to whether a
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
formal site plan submission is
necessary.
(5) Site plans shall comply with the
following:
(i) Plans shall include maps and
drawings which are legible, accurate,
and of a scale which permits easy
determination of essential details. For
general layout of buildings, this is
normally a scale of 1 inch to 400 feet (or
metric equivalent) or less. Site plans
may require other-scaled drawings,
which provide details of construction,
structure relationships within the
project area, barricades, or other unique
details. Plans may also include pictures
to illustrate details and videotapes of
MCE testing data.
(ii) Maps and drawings shall identify
distances between all PESs, all exposed
sites (ESs) within the facility, the
facility boundary, any additional
property under contractor control, ESs
on adjacent property when applicable,
public railways and highways, power
transmission lines and other utilities.
(iii) Plans shall identify and briefly
describe all PESs and all ESs within any
applicable fragmentation distance and/
or inhabitable building distance of a
PES. Site plans for major new
construction or modification shall also
identify and briefly describe all PESs
whose inhabitable building distance are
includes the proposed new or modified
site.
(iv) Plans shall include the maximum
net explosive weight(s) (NEW) and the
HC/Ds of all PESs and, when applicable,
shall include MCE information and
maximum NEW for each room or bay.
Plans shall also include engineering or
test data when substituting construction
or shielding for distance to protect from
fragmentation or overpressure.
(v) Plans shall include a topographical
map in sufficient detail to permit
evaluation, when the contractor uses
natural terrain for barricading to reduce
fragment distance.
(6) Construction plans for proposed
facilities shall contain the information
required in paragraphs (h)(5)(i) through
(h)(5)(v) of this section and construction
details of dividing walls, venting
surfaces, firewalls, roofs, operational
shields, barricades, exits, ventilation
systems and equipment, AE waste
disposal systems, lightning protection
systems, grounding systems, processing
equipment auxiliary support structures,
and, general materials of construction,
as applicable.
§ 184.2 Mishap investigation and
reporting.
(a) General. This section contains
requirements for investigating and
reporting mishaps involving AE.
PO 00000
Frm 00004
Fmt 4701
Sfmt 4702
(b) Reporting criteria. The contractor
shall investigate and report to the ACO
and cognizant Defense Contract
Management Agency (DCMA) contract
safety specialist all mishaps involving
ammunition or explosives that result in
one or more of the following:
(1) One or more fatalities.
(2) One or more lost-work day cases
with days away from work as defined by
29 U.S.C. 651–678.
(3) Five or more non-fatal injuries
(with or without lost workdays).
(4) Damage to government property
exceeding $20,000.
(5) Delay in delivery schedule
exceeding 24 hours. (This requirement
does not constitute a waiver or
amendment of any delivery schedule
required by the contract.).
(6) Contractually required
notifications of mishaps other than in
paragraphs (b)(1) through (b)(5) of this
section; or
(7) Any mishap that may degrade
operational or production capability, or
is likely to arouse media interest.
(c) Mishap investigation requirements.
Paragraph (e) of this section contains the
elements of information which a basic
investigation shall produce. Based upon
the seriousness of the mishap and
impact on munitions or munitions
systems involved, the ACO or PCO may
require an additional, more
comprehensive investigation. The PCO
retains the right to participate in
contractor investigations, or to perform
an independent DoD investigation. In
the event the PCO directs DoD
participation, or an independent DoD
investigation, the contractor shall
preserve the mishap scene, taking only
those actions necessary to protect life
and health, preclude further damage, or
prevent access by unauthorized persons
in order to preserve investigative
evidence. The contractor shall obtain
the PCO’s permission to disturb the
evidence, with the exception of
paragraph (b)(2) of this section. Nothing
in the reporting requirements contained
in this part relieve the contractor of
making other notifications required by
Federal, State, or local requirements.
(d) Telephone report. The contractor
shall report any mishap described in
paragraph (b) of this section by
telephone to the ACO and cognizant
DCMA contract safety specialist as soon
as practicable, but not later than three
hours after the mishap.
(e) Written report. (1) The contractor
shall submit a written report to the ACO
and cognizant DCMA contract safety
specialist by the end of the second
business day after mishap occurrence.
(i) Contractor’s name and location.
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(ii) Date, local time, and plant facility/
location of the mishap.
(iii) Type of mishap (explosion, fire,
loss, other).
(iv) Contract, subcontract, or purchase
order.
(v) Item nomenclature, hazard
classification, lot number.
(vi) Mishap narrative.
(vii) Number of injuries, fatalities,
degree of injuries. (viii) Description of
property damage and cost.
(ix) Quantity of energetic material
involved (pounds, units, rounds).
(x) Probable cause(s).
(xi) Corrective action taken or
planned.
(xii) Effect on production.
(xiii) Name, title or position, and
phone number of person submitting the
report.
(xiv) Remarks.
(2) The contractor shall provide to the
ACO supplemental information to the
initial report within 30 days of mishap
occurrence.
(f) Special technical mishap
investigations and reports. When
warranted by the circumstances of a
mishap, the PCO may require a special
technical investigation conducted by
DoD personnel. The PCO may also
direct the contractor to conduct a
special technical investigation. In either
case, the investigation report shall
provide details such as fragmentation
maps, photographs, more detailed
description of events of the mishap,
effects on adjacent operations, structural
and equipment damage, Q–D drawings,
detailed description of occurrence and
related events, findings and
conclusions. If the contractor performs
the special technical mishap
investigation, the contractor shall
forward the report through the ACO to
the PCO within 60 days of the direction
by the PCO to perform the investigation.
Upon determination by the PCO that a
DoD investigation is required, the PCO
will immediately advise the contractor.
§ 184.3
General safety requirements.
(a) General. This section provides
general safety requirements for all AE
operations addressed in this part. When
these practices exceed or differ from
local or national codes or requirements,
the more restrictive shall apply.
(b) Personnel and material limits. (1)
Control of all locations or operations
presenting real or potential hazards to
personnel, property, or the environment
is essential for safety and efficiency.
Control measures include minimizing
the number of personnel exposed,
minimizing the duration of the
exposure, and minimizing the amount
of hazardous material consistent with
safe and efficient operations.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(2) All buildings, cubicles, cells,
rooms, and locations containing AE
shall have AE and personnel limits
prominently posted. Include
supervisors, production workers, and
transient personnel when determining
personnel limits. Posted personnel
limits are not required in storage
magazines, magazine areas, or transfer
points.
(3) All buildings, cubicles, cells,
rooms or locations containing AE shall
have prominently posted limits for the
quantities of AE permitted. The posted
limits shall not exceed the quantity
stipulated in the site plan, and shall
accurately reflect current process
requirements. Post AE limits in storage
magazines when the limit differs from
that for other magazines in the block, or
when circumstances prevent the limit
from being readily apparent. It is not
required to express AE limits in units of
weight or in the number of items.
Express limits in terms of trays, boxes,
racks, or other units more easily
observed and controlled.
(c) Standard operating procedures
(SOP). (1) Clearly written procedures are
essential to avoid operator errors and
ensure process control. Therefore,
before commencing manufacturing
operations involving AE, qualified
personnel shall develop, review, and
approve written procedures.
(2) Preparation. The contractor shall
prepare and implement written
procedures which provide clear
instructions for safely conducting AE
activities. The use of controlled tests is
an acceptable method for developing
and validating SOPs. SOPs shall include
the following:
(i) The specific hazards associated
with the process.
(ii) Indicators for identifying
abnormal process conditions.
(iii) Emergency procedures for
abnormal process conditions or other
conditions which could affect the safety
of the process.
(iv) Personal protective clothing and
equipment required by process
personnel.
(v) Personnel and AE limits.
(vi) Specific tools permitted for use by
the process operator.
(vii) The chronological sequence of
job steps the operator is to follow in
performing the work.
(viii) Procedures for disposing of any
scrap and waste AE.
(3) Dissemination. Personnel involved
with AE processes, and personnel who
maintain AE equipment, shall have
written operating procedures readily
accessible.
(4) Training. Personnel shall receive
appropriate training before performing
PO 00000
Frm 00005
Fmt 4701
Sfmt 4702
16041
work involving exposure to AE. The
training shall include emphasis on the
specific safety and health hazards,
emergency operations including
shutdown, and safe work practices
applicable to the employee’s job tasks.
The contractor shall ascertain that each
employee involved in an AE process has
received and understood the training.
The contractor shall prepare a record
that contains the identity of the
employee, the date of training, and the
means used to verify that the employee
understood the training.
(5) Emergency procedures. The
contractor shall instruct employees on
procedures to follow in the event of
electrical storms, utility or mechanical
failures, equipment failures, process
abnormalities, and other emergencies
occurring during the manufacturing,
handling, or processing of AE.
(6) Revalidation. Qualified personnel
shall review SOPs on a regular basis.
The managing authority shall change
and validate SOPs as often as necessary
to reflect improved methods, equipment
substitutions, facility modifications, or
process revisions.
(d) Storage in operating buildings. (1)
The contractor may store limited
quantities of hazardous materials, other
than AE materials, which are essential
for current operations in an operating
building.
(2) The contractor shall store AE
materials that exceed minimum quantity
necessary for sustained operations in a
service magazine located no closer than
the intraline distance (ILD) (based on
the quantity in the magazine) from the
operating building or area. If ILD
distance is not available for a separate
service magazine, the contractor may
designate storage locations within the
operating building. Designated storage
locations shall preclude immediate
propagation from the operational
location to the storage location. The
quantity of AE material in the internal
storage location shall not exceed that
needed for one half of a work shift. The
contractor should consider personnel
exposure, structural containment
afforded, and the venting ability of the
proposed storage location when
determining where to locate a
designated storage location. When
storage containers completely contain
all fragments, debris, and overpressure,
AE material may be stored without
regard to Q–D requirements.
(3) At the end of the workday,
personnel should remove all AE
material from processing equipment and
store it in an appropriate magazine or
designated storage location. If
operationally required, personnel may
store in-process AE materials in the
E:\FR\FM\29MRP2.SGM
29MRP2
16042
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
building during non-operating hours
provided the physical characteristics
and stability of the AE materials are not
degraded, and the AE material would
not compromise the safety of the
process equipment or personnel when
the process is restarted.
(4) The contractor may use a separate
enclosed room or bay in an operating
building specifically adapted for the
interim storage of production items
awaiting the results of testing before
final pack-out. The room or bay must
afford the equivalent of service
magazine distance protection to other
parts of the building, and ILD to other
buildings. Such a room or bay is limited
to its defined and designed function and
items, but is not subject to the four-hour
supply limitation for the building or the
ultimate pack-out operation.
(e) Housekeeping in hazardous areas.
(1) The contractor shall keep
structures containing AE clean and
orderly.
(2) Explosives and explosive dusts
shall not accumulate on structural
members, radiators, heating coils, steam,
gas, air or water supply pipes, or
electrical fixtures.
(3) Written procedures shall include
instructions for the removal of spilled
material.
(4) Floor cleaning methods shall not
create an ignition hazard or alter the
conductive ability of floors in AE areas,
nor should they result in an
environmental contamination potential.
(5) Cleaning methods for AE
processing equipment shall not result in
any foreign material or AE remaining in
the equipment.
(f) Precautions for maintenance and
repairs to equipment and buildings. (1)
The contractor shall examine and test
all new or repaired AE processing
equipment prior to placing the
equipment in service in order to ensure
that it is safe to operate.
(2) Before proceeding with
maintenance or repairs to AE processing
equipment, contractor personnel shall
decontaminate the equipment to the
degree necessary to perform the work
safely. The contractor shall protect
maintenance personnel from the effects
of a reaction resulting from AE material
in or on other parts of the equipment.
Contractor personnel shall tag AE
processing equipment before proceeding
with repairs. The tag shall identify the
decontaminated parts of the equipment,
and those parts that contain AE.
(3) The contractor shall have SOPs for
maintenance personnel performing
work on AE equipment or performing
building maintenance, repair, or
modification activities in AE areas. The
SOPs shall include a provision for
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
inspecting equipment after maintenance
work to ensure no tools or foreign
materials remain in AE equipment. The
SOPs shall identify the specific tools
required to perform work on equipment
which may contain explosive residues
or areas which could have an explosive
atmosphere.
(4) Before performing any building
repair, modification or maintenance
activity, the contractor shall ensure the
removal of all AE materials from areas
that may pose a hazard. The contractor
shall also ensure the decontamination of
all places where AE material could
accumulate, such as, equipment,
crevices, vents, ducts, wall cavities,
pipes and fittings.
(g) Operational shields. (1) The
purpose of operational shields is to
prevent propagation of AE material from
one AE operation or location to another,
protect facilities and equipment, and
provide personnel protection. Shields
used for these purposes require an
evaluation to determine their suitability
for their intended purpose. All AE
operations and processes require a
hazard assessment prior to work
performance to determine the type of
hazard involved, the level of risk
associated with the AE material or item,
and the corresponding level of
protection required.
(2) The primary hazards that
accompany explosions and deflagrations
are blast overpressure, fragmentation
(primary and secondary) and thermal
effects. The hazard assessment shall
consider these hazards and the quantity
of AE materials, initiation sensitivity,
heat output, rate of burning, potential
ignition and initiation sources,
protection capabilities of shields,
various types of protective clothing, fire
protection systems, and the acute and
chronic health hazards of vapors and
combustion products on exposed
personnel.
(3) When the hazard assessment
indicates an unacceptable probability of
explosion or deflagration, conduct
operations or processes remotely. When
an analysis of the hazard assessment
indicates the hazards associated with an
explosion or deflagration are
controllable by using operational
shields, the contractor shall design,
install, and use shields which
effectively protect personnel from the
hazards. Shields complying with MIL–
STD–398 are acceptable protection.
(4) The contractor shall test
operational shields under conditions
that simulate the operational
environment. AE materials or items
used in the test shall correspond to
those that may be involved in a
maximum credible event (MCE), plus 25
PO 00000
Frm 00006
Fmt 4701
Sfmt 4702
percent. The contractor shall maintain
records of the test that demonstrate the
shields will function as planned.
Analysis rather than testing of shields
may be acceptable on a case-by-case
basis.
(5) When the doors of AE processing
equipment function as operational
shields, interlocking devices are
required to prevent the operator from
opening the door while the equipment
is in operation.
(h) Protective clothing. (1) All AE
operations require a hazard assessment
to determine the need for protective
clothing and personal protective
equipment. The assessment shall
include an evaluation of all hazards and
factors contained in paragraph (g)(2) of
this section.
(2) The contractor shall provide a
changing area for employees who must
remove their street clothes to wear
protective clothing, such as explosive
plant clothing, anti-contamination
clothing, impervious clothing, and so
forth. To avoid exposing personnel not
involved in AE operations to
unnecessary risks, employees shall not
wear or remove protective clothing from
the premises. Employees shall not wear
any static producing clothing in areas
where static electricity is a hazard.
(3) Explosives plant clothing,
generally referred to as powder
uniforms, shall have nonmetallic
fasteners and be easily removable.
(4) When sending explosivescontaminated clothing to an off-plant
laundry facility, the contractor is
responsible for informing the laundry of
the hazards associated with the
contaminants and any special
laundering or disposal requirements.
(i) Material handling equipment. (1)
The contractor shall not refuel gasoline,
diesel or liquefied petroleum gas (LPG)
powered equipment inside buildings
containing AE. Refueling shall take
place at least 100 feet from structures or
sites containing AE. Doors and windows
through which vapors may enter the
building shall not be open during
refueling. Position refueling vehicles at
least 100 feet from structures or sites
containing AE during refueling.
(2) Gasoline-, diesel- or LPG-powered
equipment shall not be stored in
buildings, loading docks, or piers
containing AE. The contractor shall
store gasoline-, diesel-, and LPGpowered equipment at the appropriate
fire protection distance from buildings
containing AE.
(3) Gasoline, diesel, and LPG powered
equipment shall have spark arrestors.
The contractor shall perform and
document inspections of the exhaust
and electrical systems of the equipment
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
as necessary to ensure that the systems
are functioning within the
manufacture’s specifications. The
contractor shall maintain
documentation of the inspections for a
period of one year.
(j) Parking of privately owned
vehicles. (1) Control of parking of
privately owned vehicles within an AE
establishment minimizes fire and
explosion hazards and prevents
congestion in an emergency.
(2) Parking lots serving multiple PESs
shall not be closer than the ILD from
each PES. Parking lots serving a single
PES shall not be closer than 100 feet to
the associated facility to protect it from
vehicle fires, and shall be at least public
traffic route distance from unassociated
PESs. Parking lots for administration
areas shall be located at public traffic
route distance from all PESs.
(3) Vehicles shall not obstruct access
to buildings by emergency equipment or
personnel.
(k) Ignition sources in hazardous
areas. The contractor shall not permit
any nonessential ignition sources in
operating buildings.
(l) Operational explosives containers.
(1) Containers shall be compatible with
the material they contain.
(2) Containers used for intraplant
transportation or storage of process
explosives and energetic materials shall
not leak. Because of their fragility and
potential for fragmentation, glass
containers are not acceptable.
(m) Intraplant rail transportation. (1)
The contractor shall develop written
procedures to ensure safe and efficient
rail movement of AE. The SOPs shall
include information covering the
inspection of the engine, car mover, and
cars, normal and emergency operating
procedures for the engine and car
mover, AE loading and unloading
procedures, and emergency procedures
including fire fighting.
(2) Railcars positioned for loading
shall have their brakes engaged to
prevent movement. Contractor
personnel shall inspect each railcar
before loading to ensure it is suitable to
carry the specific AE cargo. Contractor
personnel shall check the cargo to
ensure it is stable and secure, and close
the railcar doors before car movement.
If using an engine to move railcars, the
contractor shall ensure that personnel
have connected the air brakes of the
railcars in sequence to the engine. If
moving a railcar with a car mover the
contractor shall station an individual at
the hand brake of the railcar.
(3) A single parked railcar shall have
the hand brakes set and the wheels
chocked. When more than one railcar is
parked, personnel shall set hand brakes
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
on enough railcars to ensure the cars
will not move. Personnel shall set hand
brakes on the downgrade end of a group
of parked railcars. Do not rely on the
automatic air brakes to hold parked
railcars.
(4) Contractor personnel shall avoid
rough handling of railcars. Personnel
shall not disconnect railcars containing
AE from each other or a locomotive
while in motion. Personnel shall couple
railcars gently in order to avoid
damaging the AE cargo or shipping
containers. Disconnected railcars shall
not strike railcars containing AE.
(5) The contractor shall maintain all
rolling stock used for intraplant
transportation of AE in a safe and good
working condition.
(6) Portable transmitters and railroad
locomotives equipped with two-way
radios shall not transmit when passing
AE operating buildings where electroexplosive devices are in use. The
contractor shall determine minimum
safe distances based on radio frequency
and power output of the transmitter.
(n) Intraplant motor vehicle
transportation of AE. (1) The contractor
shall develop written procedures for the
safe transportation of AE in motor
vehicles. The SOP shall include
procedures for vehicle inspection,
vehicle operation, loading and
unloading AE materials, and emergency
procedures, including fire fighting.
(2) The operator responsible for
transporting AE material shall perform a
daily inspection of the vehicle before
transporting materials. The operator
shall verify that the fire extinguisher is
charged and in working order, there are
no fuels or other fluid leaks, and that
brakes, tires, steering, and other
equipment are in good operating
condition. Before transporting AE, the
operator shall inspect the cargo
compartment to ensure it does not
contain any residual AE material or any
object which could present a hazard to
the cargo.
(3) When loading or unloading AE,
the operator shall shutoff the vehicle’s
engine, unless the engine is required to
provide power to equipment for loading
or unloading. The operator shall engage
the emergency brake and use wheel
chocks when the vehicle could move
during loading or unloading. The
operator shall stabilize and ensure the
load is secure to prevent damage to
containers or their contents. The
operator shall not transport AE material
in the passenger compartment of the
vehicle.
(4) The vehicle operator shall
understand and follow established
procedures involving a vehicle fire,
PO 00000
Frm 00007
Fmt 4701
Sfmt 4702
16043
breakdown, accident, damaged or
leaking containers, and spilled material.
(5) Transportation containers shall not
allow the contents to leak or spill in
transit.
(6) Non-sparking material shall cover
the cargo compartment when
transporting AE in containers capable of
exposing their contents if damaged.
(7) Motor vehicles transporting AE
within the establishment boundaries but
outside the AE area shall bear at least
two placards. Placards based on the fire
division symbols discussed in § 184.10,
‘‘Fire Protection,’’ are acceptable. Motor
vehicles or equipment with internal
combustion engines, used near
explosives scrap, waste, or items
contaminated with explosives shall
have exhaust system spark arresters and
carburetor flame arresters (authorized
air cleaners).
(8) The contractor shall maintain
vehicles and material handling
equipment used to load and transport
AE in a safe operating condition.
(9) Batteries and wiring shall be
located to prevent contact with
containers of AE material.
(o) Inspection of AE mixing
equipment. (1) The contractor shall
establish a preventative maintenance
program which includes the inspection
of all AE mixing equipment on a
periodic basis. The SOP for the
inspection shall include criteria for
inspecting the blades to bowl
clearances, alignment of the blades and
bowl, and detection of any distortion of
the blades or bowl. The inspection
procedures shall also include
instructions for checking critical drive
system components for wear, damage or
misalignment. The procedures shall
include criteria for determining that
associated equipment used to control
the mixer is functioning as designed.
The contractor shall maintain a record
of all inspections. After performing
maintenance of the equipment, the
contractor shall run the equipment
under load to ensure it is safe to operate.
(2) The SOPs for operating mixing
equipment shall include instructions for
inspecting specific equipment
components before each use.
(p) Facility requirements. (1)
Buildings. The design, construction
techniques, process layout, and siting of
AE buildings are important
considerations in explosives safety and
directly influence quantity distance (Q–
D) requirements and the degree of
exposure to personnel, equipment, and
facilities. Construction features which
limit the amount of explosives involved,
attenuate the resulting blast
overpressure or thermal radiation, and
reduce the quantity and range of
E:\FR\FM\29MRP2.SGM
29MRP2
16044
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
hazardous fragments and debris will
help to minimize the effects of an
explosion. Incorporating Q–D criteria,
when locating an exposed site (ES) in
relation to a potential explosive site
(PES), will reduce the amount of
damage and injuries in the event of an
incident.
(2) Building exteriors. The contractor
should design and erect AE buildings
with the ability to allow for the venting
of an internal explosion without
collapsing. The use of lightweight
materials in exterior wall and roof
sections designed to vent the effects of
an explosion will help reduce the
number of large fragments. Exceptions
from using lightweight materials
include earth-covered magazines,
containment type structures, firewalls,
substantial dividing walls, special roof
loadings, and walls and roofs used for
external overpressure protection. Noncombustible exterior wall and roof
coverings of operating buildings help
prevent the spread of fire from one area
of a building to another and from
building to building.
(3) Interior walls, roofs, and ceilings.
(i) Non-combustible material is
preferred for the interior surfaces of
buildings. The contractor should treat or
cover exposed combustion supporting
building materials with fire retardant
material.
(ii) Where hazardous locations exist,
interior surfaces shall be smooth, free
from cracks, crevices and openings
which may create a hazardous
condition. This is important to prevent
the accumulation or migration of
explosive dust and vapors which could
result in an incident. The National Fire
Protection Association (NFPA),
Standard 70 2 provides criteria for
determining if a location is hazardous.
(iii) The contractor should use hard
gloss, easily cleanable, paint on painted
surfaces.
(iv) Periodically clean any surface
where explosive dust could accumulate.
Establish cleaning schedules on
information obtained from the job
hazard analysis.
(v) Do not use suspended ceilings in
hazardous locations.
(4) Floors and work surfaces. (i)
Locations where exposed explosives or
hazardous concentrations of flammable
vapor or gas are present require nonsparking floors and work surfaces.
(ii) § 184.12 provides requirements for
conductive non-sparking floors and
work surfaces.
(iii) Floors and work surfaces require
periodic cleaning to prevent the
2 Obtain NFPA publications from the National
Fire Protection Association at https://www.nfpa.org/
catalog/home/index.asp.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
accumulation of energetic materials. In
addition, all conductive and nonsparking floors and work surfaces
require preventative maintenance to
ensure their functional integrity.
(5) Substantial dividing walls. The
contractor shall design and construct
substantial dividing walls to prevent
simultaneous detonation of explosives
on opposite sides of the wall. The
design and construction shall meet the
criteria contained in Army TM 5–1300,
Navy NAVFAC P–397, or Air Force AFR
88–22 (different designations for the
same publication).
(6) Exits and doors. (i) All AE
buildings require adequate exits and
doors. NFPA Standard No. 101, ‘‘Life
Safety Code,’’ provides information
concerning exits and doors.
(ii) NFPA Standard No. 80, ‘‘Standard
for Fire Doors, Fire Windows,’’ provides
information on the selection and
installation of fire doors and windows.
(iii) No AE hazards shall occupy
space between an operator and an exit.
(7) Safety chutes. Multi-storied
locations where rapid egress is vital and
not otherwise possible require safety
chutes.
(8) Passageways. (i) Weatherprotected passageways and ramps for
travel between buildings or magazines
should include features to help prevent
fire from spreading from one building to
another. Fireproof construction
materials, fire stops, fire doors, and fire
suppression systems aid in preventing
the spread of fire.
(ii) The incorporation of weak
sections, openings, or abrupt change in
direction of passageways will aid in the
prevention of funneling the explosion
forces from one building to another.
(9) Roads and walkways. (i) Only
roads servicing a single magazine or AE
processing building, including its
service facilities, may dead end at the
magazine or building.
(ii) Hard surfaced roads and walkways
at the entrances to or between adjacent
operating buildings containing AE will
help reduce the amount of foreign
material tracked into the building by
personnel.
(iii) Avoid a road system which
requires personnel to pass through an
AE area when traveling from one area to
another.
(10) Windows and skylights. (i)
Inhabited building distances do not
protect against glass breakage and the
hazards of flying glass. Buildings
separated by inhabited building
distance should not have windows or
other glass surfaces exposed to PESs.
(ii) Minimize personnel hazards from
glass breakage by means such as
building orientation and/or keeping the
PO 00000
Frm 00008
Fmt 4701
Sfmt 4702
number of exposed glass panels and
panel size to a minimum. When
window panels are necessary and risk
assessment determines a glass hazard
will be present, blast resistant windows
must be used. The framing and/or sash
of such panels must be of sufficient
strength to retain the panel in the
structure.
(11) Hardware. (i) AE operations and
hazardous locations require an
evaluation to determine the safest type
of hardware and fasteners to use in
order to reduce the risk of an accidental
ignition. Consider using non-sparking
hardware and fasteners if they will meet
the design parameters of the intended
application. Depending on the potential
hazard, a locking device or some other
installation technique shall retain the
hardware and fasteners securely in
place. This will prevent the hardware
and fasteners from becoming loose,
entering process equipment and creating
a spark or pinch point.
(ii) The contractor should avoid
installing hardware, pipes, ducts, and
other items on blowout panels in order
to prevent the materials from becoming
secondary fragments. If it is necessary to
install items on blowout panels, select
items made of materials which will not
yield heavy fragments in an explosion.
(12) Ventilation systems. (i) Welldesigned ventilation systems reduce
personnel exposures to airborne
contaminants and prevent the
accumulation of flammable or explosive
concentrations of gases, vapors or dusts.
A local ventilation system, which
removes the gases, vapors, or dusts at
the source, is more effective than a
general ventilation system.
(ii) A ventilation system is required in
areas of buildings generating potentially
explosive dusts, gases or vapors.
Testing, inspection, and maintenance of
ventilation systems used for
contaminant control require
documentation.
(iii) Exhaust fans through which
combustible dust or flammable vapor
pass shall have nonferrous blades or a
casing lined with nonferrous material.
The electrical wiring and equipment of
the system should comply with
provisions of NFPA Standard No. 70,
‘‘National Electrical Code’’. Bonding
and grounding of the entire system is
required.
(iv) A slight negative pressure is
required in rooms where AE operations
generate explosive dust.
(v) NFPA Standard No. 91, ‘‘Standard
for Exhaust Systems for Air Conveying
of Vapors, Gases, Mists, and
Noncombustible Particulate Solids,’’
provides standards for exhaust systems.
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(13) Steam for processing and heating.
(i) Steam used to heat buildings
containing explosives shall not exceed
228 °F (108.9 °C) or have a pressure
greater than 5 psi (34.48 kPa).
(ii) Process steam shall not exceed
249.5 °F (120.8 °C), or exceed 15 psi
(103.43 kPa). Steam pressure greater
than 15 psi (103.43 kPa) requires
procuring contracting officer (PCO)
approval.
(iii) The surface temperature of steam
and hot water pipes in contact with
combustible materials shall not exceed
160 °F (71 °C). Pipes with an ambient
temperature greater than 160 °F (71 °C)
shall not contact combustible materials.
An insulating pipe covering capable of
reducing the surface temperature of the
covering to 160 °F (71 °C) or less is
acceptable.
(iv) In AE handling or storage
locations where resistance to ground is
high, ground steam and hot water lines
where they enter the building.
(v) When using a reducing valve,
consider installing a relief valve on the
low-pressure piping. The throttling
action of reducing valves requires a
positive means to prevent the
production of superheated steam.
(14) Tunnels. Tunnels between
buildings that contain AE shall
incorporate features that resist the shock
16045
wave of an explosion. This is important
in order to minimize the possibility of
an explosion in one building from
affecting the operations in the other
building. For further information on
tunnels go to DoD 6055.9–STD.3
(q) Quantity-distance (Q–D)
requirements. (1) Minimum Q–D
requirements are contained in DoD
6055.9–STD, DoD Ammunition and
Explosives Safety Standards.
(2) For AE work involving an MCE of
0.25 kg (0.55 lbs) or less of HD 1.1
materials, the use of the separation
distances listed in Table 1 to § 184.3 are
acceptable for meeting minimum Q–D
requirements.
TABLE 1 TO § 184.3.—MINIMUM Q–D REQUIREMENTS FOR SMALL QUANTITIES OF HAZARD DIVISION 1.1 MATERIAL
Net explosive weight
Inhabited building and fragment distance
Public traffic route and
fragment distance
Less than 0.003 kg (0.0066 lb) .......................................
0.003 kg–0.01 kg (0.0066 lb–0.022 lb) ...........................
0.01 kg–0.25 kg (0.022 lb–0.55 lb) .................................
0 .........................................
5 m (16.5 ft) .......................
15 m (49.5 ft) .....................
0 .........................................
3 m (9.9 ft) .........................
9 m (29.7 ft) .......................
§ 184.4
Quantity-distance and siting.
Refer to DoD 6055.9, Chapter 9 for
guidance.
§ 184.5 Hazard classification, storage
principles, and compatibility groups.
Please refer to DoD 6055.9, Chapter 3
for guidance.
§ 184.6. Electrical safety requirements for
AE facilities.
(a) General. Initiation systems often
use the controlled input of electrical
energy to initiate explosive mixtures
and compounds, which start an
explosive train. The uncontrolled
release of electrical energy in explosive
atmospheres or near explosives and
explosive-loaded articles can result in
unintended initiation and serious
mishaps. Electrical energy manifests
itself in many forms (e.g., standard
electrical installations, lightning,
electrostatic discharge, electrical testing)
and with various intensities which
require special precautions. This
chapter contains minimum electrical
safety requirements for existing, new, or
modified explosives facilities and
equipment.
(b) Electrical installations. (1)
National Fire Protection Association
(NFPA) Standard No. 70 and this
section are minimum requirements for
areas containing explosives. NFPA
Standard No. 70 does not specifically
address explosives, but it does establish
standards for the design and installation
of electrical equipment and wiring in
atmospheres containing combustible
3 See
dusts and flammable vapors and gasses
which, in general, are comparably
hazardous. NFPA Standard No. 70
(Article 500) defines ‘‘hazardous
locations’’ according to the hazard
presented by electrical equipment
installed in environments where
flammable gases or vapors, combustible
dusts or flyings may exist. The presence
of AE may or may not result in rating
a particular location as a ‘‘hazardous
location.’’ The following exceptions
shall be used by DoD contractors when
applying the NFPA Standard No. 70
definitions of Class I, Division 1, and
Class II, Division 1 hazardous locations:
(i) Classify areas containing explosive
dusts or explosive substances which
may produce dust capable of suspension
in the atmosphere as Class II, Division
1 hazardous locations.
(ii) Classify areas where explosive
sublimation or condensation may occur
as both Class I Division 1 and Class II
Division 1 hazardous locations.
(iii) Exceptions are extraordinarily
hazardous explosive substances, such as
nitroglycerin (NG), which require
special consideration, including
physical isolation from electric motors,
devices, lighting fixtures and the like.
(2) Multiple classifications. In some
potential explosion sites (PES) (e.g.,
powder blending with solvents),
hazards resulting from both dusts and
flammable vapors may exist. In these
cases, it is necessary for that area to
have a dual, or multiple, classification.
Use only electrical equipment listed by
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00009
Fmt 4701
Sfmt 4702
0.
2 m (6.6 ft).
5 m (16.5 ft).
Underwriters Laboratories (UL) or other
recognized testing laboratory as suitable
for use in all classes of hazardous
locations.
(3) Change of classification. The
specific processes performed in
operating buildings and magazines
dictate the requirements for electrical
equipment installation. If functions
performed in the facility change,
responsible personnel shall inspect,
approve, or reclassify the hazardous
locations.
(4) Alternate power source. Facilities
shall have an alternate power source for
special processes and operations
requiring a continuous supply of power,
whenever the loss of power will result
in a more hazardous condition.
(5) Portable engine-driven generators.
The exposed, non-current-carrying,
metallic frame and parts shall be
electrically grounded. In addition,
observe the following requirements
when supplying power to magazines or
explosives operating facilities.
(i) Place generating units at least 50 ft
(15.2 m) from magazines or hazardous
(classified) locations.
(ii) Keep the ground area between and
around the generator and the NFPA
Standard No. 70 hazardous (classified)
location clear of debris and other
combustible materials.
(iii) The exhaust from the generator
shall not impinge on grass or any other
combustible material.
(iv) Position the power cord
connecting the generator to the load to
footnote 1 to § 184.1(d)(1).
VerDate jul<14>2003
Intraline and fragment distance
E:\FR\FM\29MRP2.SGM
29MRP2
16046
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
prevent trucks or personnel from
running over or otherwise damaging the
cord.
(v) Do not use cable-to-cable splices
within a magazine, explosive operating
facility, or other NFPA Standard No. 70
hazardous (classified) location. Use only
three-wire, three-prong, approved
service type plugs and connectors.
(vi) Refer to § 184.3(i)(1) for refueling
procedures.
(6) Electric supply systems. Electrical
and explosives hazards may mutually
exist when PES are in close proximity
to electric supply lines. To protect these
hazards from each other, the following
separation requirements shall apply:
(i) Separate overhead service lines
from a PES of combustible construction
or a PES in the open by the distance
between the poles or towers supporting
the lines, unless an effective means is
provided to ensure that energized lines
cannot contact the facility or its
appurtenances if they are severed. Four
acceptable alternatives are cable trays
and messenger lines, a ground-fault
circuit-interrupter which causes a
disconnecting means to open all
ungrounded conductors of the faulted
circuit, weighted triangle line separators
or similar weights which ensure broken
lines fall straight down away from PES,
and constructed physical barriers.
(ii) Separate electric distribution lines
carrying less than 69 kV, the tower or
poles supporting those lines, and
unmanned electrical substations from
PES by public traffic route distance
(PTRD).
(iii) Separate electric transmission
lines carrying 69 kV or more and the
tower or poles supporting them from
PES by:
(A) Inhabited building distance (IBD)
if the line in question is part of a grid
system serving a large area off the
establishment.
(B) PTRD if loss of the line does not
create serious social or economic
hardships. (Note: Base PTRD and IBD on
airblast overpressure only. Fragment
distances shall not apply.)
(C) Distances in accordance with
paragraph (b)(6)(1) of this section when
the line(s) in question can be
interrupted without loss of power (i.e.,
other lines or networks exist for
rerouting power).
(iv) Avoid locating permanent electric
installations in NFPA Standard No. 70
Class I or Class II hazardous locations.
When practical operating reasons
prevent locating permanent electrical
installations outside of hazardous
locations, or require the use of portable
electrical equipment (e.g., lighting
equipment) in hazardous locations,
contractors shall only install or use
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
electrical equipment approved for the
National Electric Code (NEC) defined
‘‘hazardous location’’ and listed by
Underwriters Laboratories (UL) or other
nationally recognized testing agencies.
(c) Primary electric supply. The
primary electric supply to an entire
explosives area should be arranged to
allow cutting off the supply by remote
switches located at one or more central
points away from the area.
(d) Ventilation. Equip exhaust fans,
through which combustible dust or
flammable vapor pass, with nonferrous
blades, or line the casing with
nonferrous material. Motors shall meet
the proper NEC class for the hazard
(NFPA Standard No. 70). Clean and
service exhaust systems on a regular
schedule. Bond and ground the entire
system.
(e) Lightning protection. When
lightning protection systems are
installed, the installation, inspection,
and maintenance shall comply with the
NFPA Standard No. 780, at a minimum.
Typically, six month visual tests and 24month electrical tests of installed
systems are acceptable.
(f) Static electricity and grounding. (1)
Two unlike materials (at least one of
which is non-conductive) produce static
electricity due to contact and
separation. Contact creates a
redistribution of charge across the area
of contact and establishes an attractive
force. Separation of the materials
overcomes these attractive forces and
sets up an electrostatic field between the
two surfaces. If no conducting path is
available to allow the charges to
equalize on the surfaces, the voltage
difference between the surfaces can
easily reach several thousand volts as
they separate.
(2) The potential hazard of static
electricity arises when an accumulated
electrical charge subsequently
discharges as a spark in the presence of
hazardous atmospheres, flammable
vapors, dusts, exposed sensitive
explosives, or electro-explosive device
(EED). Electrostatic discharge (ESD)
does not present a substantial hazard
during the handling of most bulk
explosive substances if the explosives
are in approved containers. It also does
not present a hazard near explosives
totally contained and unexposed within
loaded articles. It is not possible to
prevent the generation of static
electricity entirely. Elimination of
potential ESD hazards requires proper
grounding to dissipate static charges
before they accumulate to dangerous
levels. The NFPA, UL and the U.S.
Department of Commerce publish
detailed discussions of the hazards of
static electricity and ways of reducing it.
PO 00000
Frm 00010
Fmt 4701
Sfmt 4702
Where static spark discharge may be
hazardous, NFPA Standard No. 77, shall
apply, except as otherwise specified.
(3) Static ground system. A static
ground system consists of one or more
electrodes in contact with the earth and
a conductor (i.e., metal wire) bonded to
the electrode and routed throughout the
protected facility. The static ground
system may use building structural steel
(unless structural steel is used as
lightning protection down conductor),
metallic water pipes, ground cones,
buried copper plates, and rods driven
into the earth as electrodes. The ground
system shall not use gas, steam, or air
lines, dry pipe sprinkler systems, or air
terminals and down conductors of
lightning protection systems as earth
electrodes. A static ground system
provides a conductive path to earth
from conductive floors, conductive
work surfaces, and AE equipment and
allows any generated static charges to
dissipate.
(4) Testing equipment grounds.
Trained personnel shall test ground
systems after installation, after repairs,
and at locally determined intervals and
shall keep all records. Remove all
exposed explosive or hazardous
materials from the room or area before
testing. The resistance of the electrode
to earth shall not exceed 25 ohms. The
electrical resistance from any point on
the conductor to the electrode shall not
exceed 1 ohm. The ground system
design shall provide for interconnecting
all ground electrodes of structures
equipped with a lightning protection
system.
(5) Grounding of equipment.
Contractor maintenance personnel shall
bond all AE equipment (e.g., mixers,
grinding mills, screening and sifting
devices, assembly and disassembly
machines, conveyors, elevators, steel
work tables, presses, hoppers) to the
ground system wherever ESD presents
an ignition hazard. The resistance of the
AE equipment to the grounding system
shall not exceed 1 ohm. Trained
personnel shall test this resistance
initially at installation and at least
semiannually thereafter, and shall keep
all records. Exclude the resistance of
conductive belting when testing for
resistance of belt-driven machinery to
the ground system. Bonding straps shall
bridge contact points where oil, paint,
or rust could disrupt electrical
continuity. Permanent equipment in
contact with conductive floors or
tabletops does not meet the bonding
requirement to the ground system.
Maintain compatibility of metallic
bonding and grounding cables, straps, or
clamps with the explosives involved in
the process.
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(6) Belts. Use conductive belting
wherever ESD is an ignition hazard. The
resistance of conductive conveyor belts
shall not exceed one million ohms as
measured between two electrodes
placed on the belt and as measured
between an electrode placed on the
conductive conveyor belt and an
electrode attached to the ground system.
Do not use static combs to drain off
static charges generated from belts or
pulleys used in hazardous locations.
(g) Conductive floors, tabletops, and
footwear. Contractors shall use
conductive tabletops and, shall use
conductive floors and conductive shoes
for grounding personnel at operations
involving exposed explosives with
electrostatic sensitivity of 0.1 J or less
(e.g., primer, initiator, detonator, igniter,
tracer, and incendiary mixtures).
Bonding wires or straps shall connect
the tabletops and floors to the static
ground system. Materials sensitive to
initiation by ESD sparks include lead
styphnate, lead azide, mercury
fulminate, tetrazene,
diazodinitrophenol, potassium chloratelead styphanate mixtures, igniter
compositions, grade B magnesium
powder, and exposed layers of black
powder dust. Dust from solid
propellants can be ignited from spark
energy, making conductive floors and
shoes necessary where such dust is
present. Air and dust mixtures of
ammonium picrate, tetryl, tetrytol, and
solid propellants are also sensitive to
initiation by ESD. Testing indicates
mixtures of air with vapors from many
flammable liquids (e.g., ethyl ether,
ethyl alcohol, ethyl acetate, acetone, and
gasoline) may ignite by ESD from the
human body. Therefore, contractors
shall equip areas where personnel might
contact these kinds of explosives or
with conductive floors and tabletops,
except when hazard analysis indicates
adequate housekeeping, dust collection,
ventilation, or solvent recovery methods
eliminate the ignition hazard.
(1) Unless hazard analyses indicate
otherwise, conductive tabletops, floors,
and shoes shall also protect operations
involving the following:
(i) Unpackaged detonators and
primers and electro-explosive devices.
(ii) Electrically initiated items, such
as rockets, with exposed circuit and
(iii) Hazardous materials capable of
initiation by ESD from the human body.
(2) When a hazard remains localized,
the contractor may use conductive mats
or runners instead of conductive floors
throughout an entire building or room.
These mats and runners shall meet all
the specifications and test requirements
that apply to conductive floors. When
justified by hazard analysis, contractors
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
may use conductive wrist straps in
place of conductive floors and shoes for
grounding personnel at small scale and
isolated operations. When using wrist
straps, operators shall test wrist straps
before each use (whenever removed and
re-worn) and record test results. The
resistance of the wrist strap while the
operator is wearing the strap shall fall
within a range of 25,000 ohms
(minimum) and 1,200,000 ohms
(maximum) when measured from
opposite hand to ground. Use test
equipment capable of testing 1,200,000
ohms + 10%. (Note: Operators with dry
skin may use special contact creams to
decrease the resistance to the required
value.)
(3) Conductive floor and tabletop
specifications. Conductive floors and
tabletops, made of, or covered with nonsparking materials such as lead,
conductive rubber, or conductive
compositions, shall meet the following
requirements:
(i) Provide a continuous electrical
path to the static ground system and the
electrical resistance shall not to exceed
the limits specified in paragraph (g)(5)(i)
of this section.
(ii) Provide a reasonably smooth
surface which is free from cracks. and
(iii) Maintain compatibility of
conductive floor and tabletop materials
with the energetic materials present.
(4) Conductive footwear. Operators
shall wear conductive shoes in areas
requiring conductive mats, floors, or
runners. Personnel visiting such areas
shall wear conductive shoes, ankle
straps, or similar devices, one on each
leg. Prominent markings should identify
conductive shoes to help supervisors
ensure personnel compliance. Personnel
required to work on electrical
equipment in areas where conductive
floors are installed shall not wear
conductive shoes and shall not begin
work until operators remove all AE.
(5) Testing conductive footwear,
floors, and tabletops. (i) Test criteria.
The maximum resistance of a body, plus
the resistance of the conductive shoes,
plus the resistance of the floor to the
ground system shall not exceed 1
million ohms total. That is, if 500,000
ohms is the maximum resistance
allowed from the floor to the ground
system, then 500,000 ohms is the
maximum combined resistance allowed
for the person’s body plus the resistance
of the conductive shoes (i.e., 500,000 +
500,000 does not exceed 1 million). The
contractor can set the maximum
resistance limits for the floor to the
ground system and for the combined
resistance of a person’s body plus the
shoes, as long as the total resistance
does not exceed 1 million ohms.
PO 00000
Frm 00011
Fmt 4701
Sfmt 4702
16047
(ii) To protect against electrocution,
the minimum resistance of the floor to
the ground system and the minimum
resistance of the tabletop to the ground
system shall exceed 11,000 ohms in
areas with 110 volts service and 22,000
ohms in areas with 220 volts service. A
ground fault interrupt (GFI) circuit also
meets this requirement.
(iii) Tabletop test criteria. The
maximum resistance of conductive
tabletops to the ground system shall not
exceed 1 million ohms.
(iv) Conductive footwear. All
personnel shall test conductive footwear
daily before use to ensure that the
combined resistance of the person’s
body and the conductive shoes do not
exceed the limit specified in paragraph
(g)(5)(i) of this section. Supervisors shall
keep documentation of all test results,
including calibration of test equipment.
The test voltage of the shoe tester shall
not exceed 500 volts. The short circuit
current across the shoe tester electrodes
(plates) should be limited between 0.5
ma and 2.0 ma. The design of the test
instrument shall include built-in
safeguards to prevent the test subject
from experiencing electric shock.
Personnel shall not test shoes in rooms
or areas with exposed explosives or
flammable gas mixtures. Personnel shall
not wear static generating stockings
such as silk, wool, and synthetics; and
shall not use foot powders, which have
a drying action which can increase
resistance. Dirt and grit increase
resistance of conductive shoes.
Personnel should avoid wearing
conductive shoes outdoors and shall
keep shoes clean.
(v) Trained personnel shall test
conductive floors and tabletops upon
installation and at least annually
thereafter using test equipment
specifically designed for this purpose
and shall keep records of all test results
for at least five years. Testing shall
proceed only when the room or area is
free from exposed explosives and
flammable gas mixtures. The test
procedure shall measure the resistance
of the floor between an electrode
attached to the ground system and an
electrode placed at any point on the
floor or tabletop and also as measured
between two electrodes placed 3 ft (1 m)
apart at any points on the floor or
tabletop. Each electrode shall weigh 5 lb
(2.3 kg) and shall have a dry, flat,
circular contact area diameter of 2.5 in
(64 mm). The contact area shall have a
surface of aluminum or tin foil which is
0.0005 in to 0.001 in (0.013 mm to 0.025
mm) thick and is backed by a layer of
rubber 0.25 in (6.4 mm) thick. The
surface hardness shall measure between
40 and 60 Shore A when measured by
E:\FR\FM\29MRP2.SGM
29MRP2
16048
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
a Shore Type A Durometer (see
American Society for Testing and
Materials (ASTM) D–2240–68, Institute
of Electrical and Electronics Engineers
(IEEE) Standard 14 and NFPA Standard
No. 99. Make both electrode-to-electrode
and electrode-to-ground system
measurements at five or more locations
in each room with at least two of the
points in heavily trafficked areas. If the
resistance measurement changes
appreciably with time, record the
resistance at the 5-second interval. To
prevent biased measurements, locate the
electrodes for both the electrode-toelectrode and electrode-to-ground
measurements a minimum of 3 ft (1 m)
away from an earth ground or other
grounded items such as a door frame,
ordnance handling equipment, or any
grounded item resting on a conductive
floor. (Note: The size of the floor or
tabletop may make it impractical to
conduct five surface resistance
(electrode-to-electrode) or resistance-toground measurements and still remain 3
ft (1 m) away from all grounded items.
In such cases, take enough
measurements to ensure adequate
testing of all parts of the conductive
surface and document the justification
for a reduced number of electrode-toelectrode or electrode-to-ground
measurements in the grounding system
test plan.) Only trained personnel shall
operate and maintain test instruments.
(h) Handling low-energy initiators.
Supplement typical precautions, such as
shielding and safety glasses, with the
following measures, as appropriate,
when manufacturing, processing, using,
or testing low-energy initiators initiated
by 0.1 J of energy or less.
(1) Electrically bond and ground all
metal parts of equipment.
(2) Ensure personnel wear clothing
which prevents generation of static
electricity. Test conductive shoes with a
resistance meter before entering an area
where low-energy initiators are being
processed.
(3) When low-energy initiators are
being handled, ground personnel
directly by wrist straps. The acceptable
resistance reading, taken once daily
when the operator is wearing the strap,
shall be between 250,000 and one
million ohms when measured from
opposite hand to ground. Special
contact creams may be used to decrease
the resistance to the required value.
(4) Periodically coat glass, acrylic, or
polycarbonate materials required for
transparent shielding with an anti-static
material to prevent buildup of static
electricity, when static sensitivity is
indicated to be a hazard.
(5) The sounding of a static electricity
alarm, installed with the setting best
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
able to provide ample warning, signals
a work stoppage until the problem has
been located and corrective action
taken.
(6) Check relative humidity and
temperature before starting operations
and throughout the workday where such
conditions are used to mitigate or
prevent safety problems (i.e.,
hydroscopicity or static control).
(7) Do not paint metal surfaces
subjected to rubbing or friction. If a
lubricant is necessary, use a
composition which allows the metal’s
surface resistance to remain at or below
25 ohms.
(8) Work on or with low-energy
initiators only in areas equipped with
conductive floors and table tops.
Exceptions may be made when the
initiators are in their original packaging,
or are part of a finished metallic end
item affording them complete protection
from electromagnetic or electrostatic
energy.
(9) Do not work in the vicinity of
actual or potential electromagnetic or
electrostatic fields (e.g., radio
transmission, electrical storms,
transformer stations, high voltage
transmission lines, improperly
grounded electric circuitry, rotating
equipment, belts, etc.). Establish
adequate lightning protection and
grounding and adequate resistances for
fixed sources of energy for locations
with low-energy initiator operations.
Shield these areas to afford protection
against local mobile radio transmission.
(10) Locate electrical equipment out
of the range of an operator working with
a low-energy initiator. With soldering
irons, it may be advisable to ground and
limit energy to levels below initiating
thresholds.
(11) When not part of an end item or
end item subassembly, transport
initiators only when packed according
to the latest packing specifications for
low-energy initiators.
(i) Electrical test equipment. Use the
lowest possible power source for all
electrical and electronics test
equipment. When possible, use batteries
in lieu of 110 Vac power sources.
During testing, do not use power
sources capable of initiating the AE.
When test specifications require using
electrical energy at or above the
initiating threshold level of explosive
devices, use test chambers or provide
shielding capable of containing all
hazards and apply energy remotely.
Provide safeguards against the
possibility of human error.
(j) Humidification and ionization. (1)
Humidification which maintains
relative humidity above 60 percent
effectively prevents static electricity
PO 00000
Frm 00012
Fmt 4701
Sfmt 4702
accumulations and subsequent
discharges. This technique involves preoperational checks and regular
monitoring of the humidity levels
throughout the day. Do not use
humidification with metallic powders
unless hazard analysis indicates the
powders are not susceptible to
spontaneous ignition in air with 60
percent relative humidity.
(2) Ionization is electrical
neutralization and serves as an effective
method of removing static charges from
certain processes and operations.
Methods of application can be found in
NFPA Standard 77.
(3) Contractors may use ionization or
humidification to augment their ESD
control program but, may not use them
in lieu of conductive floors and
footwear (where required).
§ 184.7 Manufacturing and processing
propellants.
(a) General. (1) These requirements
apply to propellant manufacturing and
augment other requirements contained
in this part.
(2) The safety precautions for
fabrication of propellants, propellant
loaded items, gun ammunition, and
rocket motors follow the generally
accepted principles used for many types
of explosives and energetic materials.
Solid propellants can be divided into
general categories such as single,
double, and triple base, castable
composite, and modified double base
composite. (e.g., castable composite
propellant modified with explosive
plasticizer such as nitroglycerin). Liquid
propellants include a wide range of
liquid fuels, liquid oxidizers and fueloxidizer monopropellants.
(3) Although processing safety
considerations for finished propellant
AE and loaded rocket motors are
similar, each propellant type has its
own characteristics for processing of
raw materials, intermediate
compositions, and final processing.
Hazards data for intermediate and
finished propellant can help to define
the requirements that ensure safety in
processing. Hazards data includes
initiation thresholds to such stimuli as
impact, friction, heat, and electrostatic
discharge for specific processes and
handling situations. In evaluating and
properly applying the guidelines of this
chapter, consider the response of the
materials in terms of energy input
sensitivity and magnitude of energy
release. Follow the general requirements
for manufacturing and processing of
pyrotechnics given in Chapter 8 for
safety precautions for ignition system
fabrication. (Note: An exception to this
requirement is processing of a
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
propellant grain igniter the same as
motor propellant until the grain is
mated with the initiator assembly.)
(4) In addition to generally accepted
safety precautions for handling of
explosives and other energetic
materials, the following paragraphs
provide general guidance pertinent to
the manufacturing of propellants,
propellant loaded items, gun
ammunition and rocket motors.
(b) Properties of propellants.
Knowledge of the properties and types
of propellants is critical to the
establishment of proper hazard controls.
Propellants present a wide range of
hazard characteristics even within the
various types due to variations in grain
size of ingredients and energy content of
additives, both solid and liquid. As
described below, test data is essential
for determining the chemical, physical,
physiological and explosive properties
and hazards of raw materials,
intermediate compositions, processing
aids, and liquid or solid propellant, both
uncured and cured.
(1) Single base propellants. Single
base propellants have the principal
explosive ingredient of nitrocellulose.
Remaining ingredients include
stabilizers as well as other additives.
The mixture is shaped into tubes,
perforated tubes, flakes, etc. by
extrusion and cutting.
(2) Double base propellants. Double
base propellants contain nitrocellulose
and nitroglycerine (or other liquid
nitrate ester) as the two main
ingredients. Remaining ingredients
include stabilizers as well as other
additives. This propellant can be
extruded/cut or cast into its final shape.
(3) Triple base propellants. Triple
base propellants contain three main
components: nitrocellulose,
nitroglycerine (or other liquid nitric
acid ester), and nitroguanidine. This
propellant can be extruded, cut or cast
into its final shape.
(4) Composite propellants. Composite
propellants consist of finely divided
oxidizers dispersed in fuel matrix with
the binder normally being made of
plastic material. Nitrates and
perchlorates are commonly used as
oxidizers. Common binders include:
hydroxyl terminated polybutadiene,
carboxyl terminated polybutadiene,
polybutadiene-acrylonitrile,
polyurethane, polybutadieneacrylic
acid, and polysulfides. This propellant
is typically cast into its final shape.
(5) Composite modified double base
propellants. Composite modified double
base propellants contain a dispersed
phase of finely ground oxidizer and
usually powdered fuel additive. This
propellant is typically cast into its final
shape.
(6) Liquid propellants. Liquid
propellants include a wide range of
liquid fuels, liquid oxidizers and fueloxidizer monopropellants. (Note: Refer
to the DOD 6055.9–STD, 9.6 for more
information and requirements
associated with specific liquid
propellants.
(c) In-process hazards. (1) During
scale up from research and development
of new propellants to an existing
manufacturing process, determine the
chemical, physical, physiological,
explosive properties, and hazards of raw
materials, intermediate compositions,
processing aids, and liquid or solid
propellant, both uncured and cured.
(2) Unless available from other
sources, conduct testing to determine
thermal stability, chemical
compatibility of ingredients, exothermic
reactions, and sensitivity to ignition or
detonation from friction, impact, and
electrostatic discharge. Additionally,
deflagration-to-detonation and card gap
test data can be valuable. Applicable
tests are described in TB 700–2,
Explosives Hazard Classification
Procedures.
(3) Minimum testing may satisfy the
classification requirements for several
in-process operations. For example:
(i) If reliable data exist that indicate
that the propellant mixing operations
16049
are H/D 1.1, no testing would be needed
to adopt this classification.
(ii) If testing shows that uncured
propellant will detonate, the casting and
curing operations are HD 1.1 hazards.
(iii) If detonation tests show that the
cured propellant will detonate, all
operations with cured or curing
propellant are HD 1.1 hazards.
(4) Make safety information for all
materials used in the formulation
available as required. Train personnel
on the hazards involved in propellant
process situations.
(d) Q–D requirements. Operate new
manufacturing and support facilities for
processing of propellants and propellant
loaded items to conform to the latest QD
requirements for the HD of the
propellant in its in-process condition.
(e) Separation of operations and
buildings. (1) Perform propellant and
rocket motor manufacturing and
processing in special areas (i.e.,
operating lines) whose boundaries are
separated from all other areas outside
the line in accordance with applicable
QD criteria. Table 1 to § 184.7 provides
remote control and personnel protection
requirements for certain propellant
processing operations.
(2) Generally treat sequential
operations on rocket motors as one
process operation in one building.
(3) When the hazard classification of
a propellant has not been established,
classify the propellant during site and
construction planning as the most
hazardous class/division that might
possibly apply during manufacturing
and processing.
(4) Locate safety shelters, lunchrooms,
convenience buildings, and private
vehicle parking for personnel working
in an operating building in accordance
with applicable QD criteria.
TABLE 1 TO § 184.7.—CONTROL AND PERSONNEL PROTECTION REQUIREMENTS FOR CERTAIN PROPELLANT PROCESSING
OPERATIONS
Personnel protected 1
Operation
Remote control
Blending and screening of ammonium perchlorate .......................................................
Blending, screening of nitramines and Mandatory perchlorates other than ammonium
Grinding, and mechanized drying of perchlorates and nitramines ...............................
Grinding, blending, screening, and mechanized drying of ammonium nitrates ............
Rotating blade propellant mixing ...................................................................................
Power-driven cutting, machining, sawing, planing, drilling, or other unconfined operations in which rocket motors or propellant of Hazard Division 1.1 and 1.3 are involved.2
Mandrel break away removal from cured propellant .....................................................
Pressing, extruding, pelletizing or blending ...................................................................
Casting Propellants ........................................................................................................
Mandatory ..........................
Mandatory 2 ........................
Mandatory ..........................
Advisory ..............................
Mandatory ..........................
Mandatory 3 ........................
Mandatory.
Mandatory.2
Mandatory.
Advisory.
Mandatory.4
Mandatory.3
Mandatory 3 ........................
Mandatory ..........................
Mandatory 3 ........................
Mandatory.3
Mandatory.
Mandatory.3
1 Operating
VerDate jul<14>2003
personnel shall be at K24 or in a control room that will limit overpressure to less than 2.3 psi.
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00013
Fmt 4701
Sfmt 4702
E:\FR\FM\29MRP2.SGM
29MRP2
16050
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
2 Attended
screening of wet material may take place if shown acceptable by hazard analysis.
operation permitted if shown to be acceptable by hazard analysis.
attended operation may take place when a hazard analysis shows the MCE to only be fire hazard.
3 Attended
4 The
(f) Equipment and facilities. (1)
Except as provided for in other
applicable documentation, follow the
mandatory requirements of this part for
the design, layout, and operation of
facilities and equipment for propellant
operations. Where there is no guidance,
govern operations by the results of
hazard tests and analyses (see § 184.12)
performed and documented to address
specific operations. As some propellants
can be sensitive to initiation by static
electricity, consider bonding and
grounding of equipment, tooling, and
rocket motor conductive components
along with other means of static
elimination and control. Use conductive
work surfaces and floors or floor mats
for assembly of igniters and igniter
subassemblies.
(2) Use non-sparking and non-rusting
materials, which are chemically
compatible with the propellant material,
for equipment, tooling, and machinery
that will come in contact with
propellant or propellant ingredients.
(3) Certain propellant operations
involve significant energy input that
enhances the possibility of ignition.
Examples are rolling mills, machining
and drilling operations. In these
situations, conduct complete hazard
analysis and evaluation prior to starting
the operation.
(4) Special requirements of this part
apply to heat-conditioning equipment.
(5) Exposed radiant surfaces in the
form of S-shaped smooth pipe or fintype radiators are easy to clean. Other
types of radiators are acceptable, but are
less desirable because of cleaning
difficulties.
(6) When mechanical ventilating
equipment is used in operations
involving potential concentrations of
solvent vapors, dusts, and nitroester
vapors, do not locate the electric motor
and motor controls directly in the
potentially contaminated air stream.
Provide the ventilation system with a
suitable means of collecting condensate.
(7) Design air conditioning and cure
oven air-circulating equipment of the
closed system type to prevent
contaminated air from contacting the air
motor and controls. Monitor
recirculated air to ensure concentration
of vapors and dusts do not reach
flammable (or explosive), or personnel
threshold limits. Use dustproof and
vaporproof electric motors and controls.
Preferably use air mover blades that are
nonmetallic.
(8) Rigidly fix and stabilize the
equipment during mixing to preclude
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
contact between fixed and movable
parts. Design mix bowl lift mechanisms
(i.e., elevators) to assure adequate bladeto-blade and blade-to-bowl clearances
during the complete operation cycle.
(9) Provide positive controls to
physically block or stop bowl or mixer
head movement in case of drive
mechanism malfunction. Assure
maintenance of blade-to-blade and
blade-to-bowl clearance at all times.
(10) Use rigid and strong mix blades
and shaft to ensure minimum flex from
viscosity of the mix and speed of the
shaft.
(11) Use electrical components of all
mixers that meet the appropriate
electrical classification or remotely
locate them or shroud and purge them
with inert gas. Design purged systems to
provide automatic warning upon loss of
gas pressure.
(12) Equip mixer blade shafts with
seals or packing glands that prevent
migration of liquids or solvent vapors
into bearings. Avoid submerged
bearings and packing glands. However,
if used periodically test them for
contamination and clean them.
(13) Establish a program to detect
significant changes in blade/shaft
position relative to mixer head. Check
clearances between mix blades and
mixer bowls at regular intervals based
on operating time and experience to
make sure the clearance is adequate.
Maintain a record of such checks, mixer
blade adjustments, and any damage to
the mixer blades and bowls.
(14) Electrically bond and ground mix
bowl, blades, and drive unit.
(15) Inspect blades and other moving
parts of new mixers and replacement
parts for old mixers. Inspect (i.e.,
magnaflux or X-ray) for cracks, crevices,
and other flaws.
(16) Interlock electric service to
propellant mixers with fire protection
system controls so that the mixer cannot
start when the fire protection system is
inoperative.
(17) Regularly check and maintain all
process equipment that applies energy
to in-process propellant for wear and
misalignment. Keep a record of these
checks and any maintenance performed
for the process equipment.
(18) Control equipment performing
sequential operations on propellants
(e.g., extrusion and cutting) to prevent
interference.
(g) In-process quantities and storage.
(1) Allow only the quantity of
propellant and loaded subassemblies
PO 00000
Frm 00014
Fmt 4701
Sfmt 4702
needed to ensure a safe and efficient
workflow, when conducting operations
in an operating building. Short-term
storage of larger quantities in an
operating building is permissible when
it is not in use for other operations.
(2) Completed assemblies with or
without installed ignition system may
be stored in operating buildings
provided there are no other operations
in progress and quantity/distance
complies with requirements.
(3) Production igniters may be stored
in designated areas within an assembly
or disassembly facility.
(4) Indoor storage is preferable for all
types of explosives and is mandatory for
bulk HE, solid propellants, and
pyrotechnics. Give priority of existing
indoor storage to AE requiring the most
protection from the weather (based on
the method of packing). Protect
propellant and propellant materials
from overheating by exposure to direct
sunlight when in transit or on
temporary hold.
(5) Consider the propulsive
characteristics and the ignition
probability of AE (e.g., propellant
loaded devices, rocket motors, assist
take-off units and missiles) during all
logistical phases in order to obtain as
much safety as possible under the
circumstances. Because of the great
number of types and sizes of propellant
loaded devices and conditions of
assembly encountered, only general
safety guidance is provided in this part.
Thus, the contractor should make every
effort to prevent ignition of any units
being manufactured, assembled,
disassembled, handled, stored,
transported or deployed. Use approved
flight restraining devices (tie-downs) to
the maximum extent possible. When
doubt exists as to whether a given AE
or configuration (state of assembly) is
propulsive or nonpropulsive, treat the
AE as propulsive until pertinent
technical information can be obtained.
(h) Ingredients processing. (1)
Weighing, measuring, and handling raw
materials. (i) Electrically ground scales
for weighing raw materials, where
needed, to properly protect the
operation. This grounding is especially
important where flammable or
combustible materials are involved.
(ii) Provide separate weight or
measurement rooms, cubicles, or areas
(dependent upon the quantity and
sensitivity of the materials handled)
provided. Separate oxidizer and
metallic powder weighing from each
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
other and from other materials by
physical barriers rather than distance.
(iii) It is important that containers,
equipment, hand tools, scale pans, etc.,
used for weighing processes do not mix
with those weighing or measuring
oxidizers and fuels, particularly where
distance rather than physical barriers
separates these areas. Use positive
measures to ensure the complete
separation of such equipment and tools.
(iv) Do not change the designated use
of space and equipment without a
thorough cleaning and inspection to
make sure that all traces of the previous
material have been removed, if any
possibility exists that materials are
incompatible.
(2) Oxidizer Processing. Solid
propellant oxidizing agents are
perchlorates, nitrates, nitroesters, and
nitramines used in solid rocket motor
propellants.
(i) Avoid contaminating an oxidizer
agent with any metal or chemical (fuel)
which may result in a more sensitive
composition.
(ii) Use closed systems as much as
possible for dust, humidity, and tramp
material control.
(iii) Use fire-retardant materials to
make flexible connections (socks) in
pipes or duct systems that convey
oxidizer materials and dust socks in
collectors or hoppers. Only use
connection materials that are chemically
compatible with the oxidizers.
(iv) Make the pipes and duct systems
electrically continuous. Avoid threaded
joints and fittings in contact with
oxidizer. Preferably use quick clamp
neuter end pipe joints.
(v) Use static electricity control
measures to dissipate static charges to
an acceptable level if transporting
oxidizer by fluidization.
(3) Oxidizer drying. (i) Establish the
safe temperature for drying each
material and do not exceed that
temperature at any point in the drying
apparatus or drying room.
(ii) Use thermostatic controls to
prevent exceeding the maximum safe
temperature in the drying process.
Install and use redundant temperature
controls.
(iii) Do not use electrical heating
elements that may contact the oxidizer
or oxidizer dust.
(iv) Hold dust to a minimum in the
drying process. Use a dust collection
system if dusting can create a potential
hazard.
(v) Exercise care to prevent drying of
incompatible materials simultaneously
in the same drying process. Do not dry
oxidizers in an oven, drying room, etc.,
used for processing flammable or other
incompatible materials until after
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
cleaning and inspection shows it is free
of any residual contamination.
(4) Screening oxidizers. (i) Construct
screening equipment so it cannot
subject oxidizer material to pinching,
friction, or impact as a result of metalto-metal contact. Keep rooms in which
screening units are operated thoroughly
clean to eliminate hazardous
accumulations of dust.
(ii) Electrically ground oxidizer
screens and bond them to the receiving
vessel.
(5) Blending oxidizers. (i) If blending
of oxidizers generates gases, design and
install a suitable means of gas pressure
relief into the blender.
(ii) Electrically bond the blender
throughout.
(iii) Construct blending equipment so
it cannot subject oxidizer material to
pinching, friction, or impact between
metal-to-metal surfaces.
(iv) When blending ammonium
perchlorate using powered mechanical
equipment, protect operating personnel.
Use remote controls for mechanical
blending.
(v) When using powered mechanical
methods for blending HD 1.1 substances
(such as RDX or HMX), use remote
controls and personnel protection (See
Note 1 to Table 1 to § 184.7).
(6) Grinding oxidizers. (i) When using
impact type mills, provide sufficient
clearance between stationary and
moving parts to prevent metal-to-metal
contact. Check clearances as often as
needed to ensure they are adequate. Air
purge mill bearings to prevent
contamination. Do not use impact type
grinders for HD 1.1 substances.
(ii) Pass oxidizer feed materials
through a screen mesh with openings no
greater than the clearance between
hammer and plate. Use the smallest
screen mesh size for ammonium nitrate
that allows free flow of the prills. Use
magnetic separators if screening is not
possible.
(iii) Use only compatible lubricants in
grinding equipment.
(iv) Install and use heat sensing
devices for the bearing housing of
grinding and conditioning equipment.
(v) Determine the optimum cleaning
cycle and method for grinding
equipment and include them in SOP.
(vi) Provide grinding operations with
wet dust collection systems, where
appropriate.
(vii) Thoroughly ground and bond
pneumatic grinding operations to
provide for electrostatic charge
dissipation.
(7) Preparation of fuel compositions.
(i) Determine the sensitivity
characteristics of fuel compositions
prior to production mixing operations.
PO 00000
Frm 00015
Fmt 4701
Sfmt 4702
16051
(ii) Establish compatibility of
materials. Develop procedures that
preclude the formation of highly
sensitive compositions or hazardous
conditions during processing, such as,
dry AP and powdered metal mixtures.
(iii) Preferably bond equipment,
piping, and vessels used in fuel
preparation to form a continuous
electrical path with each other and to
building ground. When pouring metallic
powder or flammable liquids from one
container to another, bond the
containers together prior to the transfer.
(iv) Minimize the formation and
accumulation of dust in all preparation
operations.
(v) Use fume hoods, dust socks,
closed systems, and dust/fume vacuum
exhaust hoses, as appropriate, to
prevent vapors and dust getting into the
operating areas.
(8) Transfer operations. (i) Transfer
finely divided powdered ingredients by
methods that control flow rate and
minimize electrostatic charge
generation.
(ii) Before transferring flammable
solvents, electrically bond the transfer
and receiving vessels to eliminate
electrostatic potential differences.
(i) Mixing. (1) Secure hardware and
associated equipment to prevent loose
items falling into mixers.
(2) Pass liquids and powders to be
added to the mix vessels through a
screen or orifice with an opening(s) less
than the smallest clearance in the mixer.
You may directly add smaller amounts
of material, provided a positive means
exists to ensure the material does not
contain any foreign material.
(3) Use other means such as x-rays to
examine materials that you cannot
screen or that are opaque or not easily
inspected.
(4) When consistent with the process
system and requirements, cover the
mixer bowl after completing charging or
mixing to prevent the accidental
introduction of foreign objects into the
mixer and to prevent sunlight impinging
directly on the materials in the bowl.
(5) Use only non-sparking devices for
hand scrapping the sides and blades of
mixers. Set up controls to prevent
accidental introduction of these and
other devices into the mixer.
(6) Account for all loose tools and
equipment before starting or continuing
mixing operations.
(7) Do not allow loose objects such as
jewelry, pens and coins in the mixer
operating area where accidental
introduction into the mixers might
occur. Pocketless coveralls should be
used.
E:\FR\FM\29MRP2.SGM
29MRP2
16052
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(8) Provide direct and unobstructed
routes for personnel egress from mixer
buildings or bays.
(9) Do not attempt to fight propellant
fires.
(10) Preferably equip propellant
mixers, inside and outside of the mixing
vessel, with a high-speed deluge system.
(j) Casting and curing. (1) Personnel
may attend cast operations if you first
conduct a thorough safety review of the
operation is conducted.
(2) Multiple or single production line
type casting is permitted. However,
when the survivability of the production
facility is critical or the risk to the
program is significant, the PCO may
require the contractor to provide
protection that prevents propagation of
an incident from the casting operation
to adjacent bells or pits.
(3) Use only smooth cast piping
surfaces in contact with propellant. Use
tooling free of cracks, pits crevices, and
weld slag for propellant casting and
curing operations. Avoid threaded joints
as much as possible, especially at
unions requiring disassembly for
process operation or cleaning.
(4) Do not design or use cast tooling
and mandrels that permit metal-to-metal
friction or impact sites.
(5) Design and use propellant flow
valves that prevent propellant pinching
or compression between two metal
surfaces.
(6) Design and use pressurized casting
vessels capable of withstanding at least
twice the maximum allowable working
pressure.
(7) Secure lids to pressurized casting
vessels so that they will withstand the
rated pressures of the vessels.
(8) Do not exceed the working line
pressure of casting vessels. Install a
relief valve downstream of the regulator
on pressure lines.
(9) Equip each vessel with a blowout
disk (burst diaphragm) designed to blow
out at less than 120% of the vessel’s
maximum allowable working pressure.
Allow for the release of the potential
rapid rise of pressure in the vessel
should the propellant ignite.
(10) When curing or casting
propellant under pressure, provide
emergency pressure relief.
(11) Pressurize and depressurize
propellant cure operations remotely.
(12) Physically and electrically
disconnect casting vessels from lifting
devices during cast operations.
(k) Extrusion processes. (1) Design
solventless extrusion presses and
compression molding equipment to
remove air from the propellant before
compaction and extrusion begin. Assure
that procedures provide for checking
operation of the vacuum system and for
cleaning it of propellant residue and
condensed vapors such as those
generated from nitroglycerin
volatilization.
(2) Check ramheads for alignment
with the press bore to preclude metalto-metal contact. Include flashing
removal in the process procedures.
(3) Provide interlocks to preclude
press operation during loading or other
attended operations.
(l) Propellant loaded AE. (1) When
performing operations on cured
propellant contained in pressure vessels
or rocket motor cases and there may be
a risk of ignition due to energy inputs
(e.g., electrical check of pyrotechnic
devices). In such cases, secure the unit
in a fixture capable of withstanding 2.5
times the rated thrust of the assembly.
(2) Use remote control to apply
mechanical force to ‘‘breakaway’’ the
mandrel or other tooling embedded in
propellant. However, see Table 1 to
§ 184.7 for exceptions.
(3) Avoid moving loaded rocket
motors with cores in place. If loaded
motors containing cores must be moved,
however, support the core and motor
case by or suspended from a common
source or in some manner locked or tied
together to prevent independent
movement of either.
(4) When determining the safest
method to use, evaluate and consider
the hazard characteristics of individual
propellants you will cut, machine, or
contour.
(5) Design propellant machining
equipment:
(i) To prevent contact of cutting tools
or blades with motor cases and other
metal objects.
(ii) To minimize generation of heat.
(iii) To facilitate removal of dust and
chips, and to afford personnel
protection. If there is a possibility that
a metal or other foreign object may be
in the propellant, x-ray the motor or
grain prior to machining.
(6) Frequently remove propellant
dust, chips and shavings from the work
area during machining and contouring.
(7) Preferably position rocket motors
in final assembly process to permit
ready access to all sides of the motor.
Keep aisles and exit doors clear and
unobstructed. Install quick release
hardware on all exit doors.
(8) Keep the number of items in the
final assembly building at the minimum
consistent with a safe and efficient
operation.
(9) Grounding of propellant loaded
assemblies in storage is optional, based
on a case-by-case review.
(10) If the process requires removing
an igniter-shorting clip, keep the igniter
shorted until immediately before
insertion. Minimize the time that the
igniter remains unshorted.
(11) Provide means for controlled
dissipation of static electrical charges
during igniter insertion.
(12) Conduct operations that involve
electrical continuity checking/testing of
ignition systems installed in rocket
motors according to thoroughly
reviewed and approved procedures.
Conduct these checks by remote control
with the motor mounted in a test stand
designed to withstand 2.5 times the
thrust of the motor.
(m) Disassembly. (1) As much as
possible, avoid metal-to-metal
movement and trapping of explosive
substance in process equipment or
tooling that require disassembly in a
process operation.
(2) Use clean, external clamp fittings
on pipe assemblies for propellant
transfer.
(3) Before starting non-routine
disassembly of equipment or tooling
(such as that necessary for equipment
repair or for securing the process),
evaluate potential hazards of trapped
material or process residuals.
TABLE 1–1 TO § 184.7.—CONTROL AND PERSONNEL PROTECTION REQUIREMENTS FOR CERTAIN PROPELLANT
PROCESSING OPERATIONS
Operation
Remote controls
Blending and screening of ammonium perchlorate .......................................................
Blending, screening of nitramines and perchlorates other than ammonium ................
Grinding, and mechanized drying of perchlorates and nitramines ...............................
Grinding, blending, screening, and mechanized drying of ammonium nitrates ............
Rotating blade propellant mixing ...................................................................................
Mandatory ..........................
Mandatory 2 ........................
Mandatory ..........................
Advisory ..............................
Mandatory ..........................
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00016
Fmt 4701
Sfmt 4702
E:\FR\FM\29MRP2.SGM
29MRP2
Personnel protected 1
Mandatory.
Mandatory.2
Mandatory.
Advisory.
Mandatory.4
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
16053
TABLE 1–1 TO § 184.7.—CONTROL AND PERSONNEL PROTECTION REQUIREMENTS FOR CERTAIN PROPELLANT
PROCESSING OPERATIONS—Continued
Personnel protected 1
Operation
Remote controls
Power-driven cutting, machining, sawing, planing, drilling, or other unconfined operations in which rocket motors or propellant of Hazard Division 1.1 and 1.3 are involved 2.
Mandrel break away removal from cured propellant .....................................................
Pressing, extruding, pelletizing or blending ...................................................................
Casting propellants. .......................................................................................................
Mandatory 3 ........................
Mandatory.3
Mandatory 3 ........................
Mandatory ..........................
Mandatory 3 ........................
Mandatory.3
Mandatory.
Mandatory.3
1 Operating
personnel shall be at K24 or in a control room that will limit overpressure to less than 2.3 psi.
screening of wet material may take place if shown acceptable by hazard analysis.
3 Attended operation permitted if shown to be acceptable by hazard analysis.
4 The attended operation may take place when a hazard analysis shows the maximum credible event (MCE) to only be fire hazard. For guidance on ENERGETIC (PROPELLANT) LIQUIDS, please refer to DoD 6055.9, Section 9.5.
2 Attended
§ 184.8 Safety requirements for
manufacturing and processing
pyrotechnics.
(a) General. (1) Pyrotechnics, as well
as propellants and explosives, are
chemical mixtures which release large
amounts of energy. The amount of
energy released, the speed of reaction,
and the form of the output energy are
the characteristics that distinguish
between pyrotechnics and other forms
of high-energy (HE) mixtures, and
between types of pyrotechnics. The
safety precautions for manufacturing
and processing pyrotechnics parallel
those of many types of explosives and
propellants. However, incident
mitigation techniques must recognize
the unique characteristics of the
particular mixtures, and not rely on
techniques appropriate to other types of
explosive substances (e.g., HE). Rates of
reaction of pyrotechnic mixtures vary
greatly, from mixtures with very low
rates of reaction to rates equivalent to
high explosives. Energy output also
varies from very low to very great.
Process variables, such as ingredient
particle size, can affect reaction rate and
output to the extent that a change in
process variables can negate protective
measures. Complicating safety in
pyrotechnics operations is the variety of
highly flammable solvents often used as
processing aides.
(2) Pyrotechnics are mixtures of fuels
and oxidizers, typically held together by
binders. Pyrotechnics display many
different characteristics, because they
are formulated for different purposes.
General categories of pyrotechnics are:
initiators (igniters); illuminants; smokes.
gas generators; sound generators; heat
producers; and timing compositions.
Each has its own characteristics and
attendant processing requirements.
(b) Properties of pyrotechnic materials
and mixtures. Knowledge of the various
pyrotechnic properties is critical to the
establishment of proper hazard controls.
(1) Oxidizers. Oxidizers are oxygen
rich substances which decompose to
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
liberate oxygen gas, or substances which
act as oxidizers with active metal fuels.
Typical inorganic oxidizers are nitrates,
chlorates, perchlorates, oxides,
chromates, and dichromates. Fluorine
and chlorine, as in hexachloroethane
and Teflon (brand of fluorine containing
compound) are examples of organic
compounds used as oxidizers. All
oxidizers, if not well controlled, tend to
increase the risk of undesired reactions,
particularly in the presence of organic
materials (including wood). Potassium
chlorate compositions are particularly
susceptible to accidental ignition.
Impurities in process materials, or
introduced by poor process control (e.g.,
oils, lubricants) can readily increase the
sensitivity of mixtures or result in
ignition. Some oxidizers with trace
impurities, or by themselves (i.e.,
ammonium perchlorate (AP)), can
detonate when subjected to severe
stimuli such as an adjacent explosion or
thermal energy. Safety requires absolute
control of oxidizers to prevent
contamination, uncontrolled moisture
absorption (many are hydroscopic), fires
or explosions from accidental mixing
with fuels.
(2) Fuels. Fuels react with the
oxidizers to produce heat and an
oxidized product. It is the proper
pairing of the fuel with an appropriate
oxidizer that determines the reaction
characteristics, and the use for the
mixtures. Metals, such as magnesium or
aluminum, create high heat or light
output. Fuels include an almost
unlimited variety of organic (sugars and
red gum) and a more limited variety of
inorganic materials (e.g., sulfur boron,
phosphorus, and sulfides). Although
generally more stable than oxidizers,
fuels also have unique characteristics
that contribute to risk. These include
the liberation of hydrogen from
magnesium and aluminum powders
which become wetted. Again, storage
and handling of fuels requires tight
process controls which respect the
characteristics of the specific materials
PO 00000
Frm 00017
Fmt 4701
Sfmt 4702
and prevent contamination which may
result in a reaction.
(3) Binders. Homogeneity of the
mixtures governs the effectiveness of
pyrotechnic compositions. Some
pyrotechnics (e.g., black powder) are
self-bound by the manufacturing
process to maintain the charcoal, sulfur,
and potassium nitrate in the correct,
proportionate, intimate mixture needed.
Other mixtures, because of differences
in particle size or weight of ingredients,
require the use of a binder to retain the
homogeneous blend. Other binders
include lacquers, epoxies, and a variety
of polymers activated by heat or
solvents. Some solvents are similar in
composition to fuels, and the binder
may also be a fuel or burn rate modifier.
Some binders are flammable, others
require the use of a highly flammable
solvent, and thus the ignition
characteristics of these materials are
important risk factors.
(4) Types of pyrotechnic
compositions. Pyrotechnic compositions
are usually grouped by the function of
the end item. There is no universal
single grouping, but typical major
groupings are: heat and delay
compositions (e.g., ignition, delay, heat,
and propellant), color and light
compositions, smoke (e.g., obscuring
and signal smokes, noise). The range of
sensitivity to initiation and the rate/
amount of output energy varies greatly
both within and between groups.
(i) Heat and delay compositions.
Pyrotechnic fuzes, electric matches, first
fires, primers, igniters, delay
compositions are all members of this
group. The end products must function
with very little stimulus, and thus the
mixtures, as well as individual
ingredients, are sensitive to initiation.
First fire, igniter and primer mixtures
are generally the most sensitive to
initiation stimuli (i.e., heat, friction,
impact, static electricity). (Note: Primer
mixes containing initiating explosives
such as lead azide or lead styphnate are
properly classed as explosives.) These
E:\FR\FM\29MRP2.SGM
29MRP2
16054
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
mixtures often use black powder or
potassium chlorate/metal combinations
or potassium chlorate/phosphorous
mixtures. This group also contains
mixtures with high heat outputs for
such purposes as document destroyers
and welding. These high heat producers
are generally metallic fuels and metallic
oxidizers, as in the iron oxide/
aluminum powder formulations for
Thermite. Black powder, when used to
launch or expel items is a propellant
and is included in this group.
(ii) Color or light producing
compositions. There are a wide variety
of mixes and compositions which
produce light, color, or both. Illuminant
candles, photoflash, decoy flares all are
part of this very broad category. Many
of the compositions, notably the
photoflash and decoy flare
compositions, are characterized by very
rapid reactions, and extreme
temperature outputs. Both have resulted
in fatal accidents. Metallic fuels are
characteristic of the high light (visible,
IR) output mixtures. Output
temperatures exceeding 2000 °F (1093
°C) characterize many of the items in
this category. Accidental initiation of
large mix batches of some compositions
may have a significant pressurization
effect in addition to the heat, with
resultant structural damage.
(iii) Smoke and noise producing
compositions. Obscurants, colored
markers, weapons simulators and
weapons effects simulators comprise
this category. Smoke compositions are
characteristically slow burning in
finished form, but must burn at a
temperature high enough to vaporize the
dye compound (usually organic).
Chlorates are often the oxidizer in
colored smoke mixes. ‘‘Flash-bang
compositions’’ used in weapons
simulators and weapons effects
simulators are actually explosives in
most instances, and will detonate with
adequate stimulus in unconfined bulk
form. ‘‘Flash-bang’’ compositions,
particularly in display or commercial
fireworks, but also in military items,
were the cause of many injuryproducing accidents. Similarly,
‘‘whistle’’ compositions are very
sensitive to ignition and can detonate.
(c) Process requirements. Pyrotechnic
operations, because of the sensitive
nature of the ingredients and
compositions, the dangerous effects of
contamination, including cross
contamination of oxidizers and fuels,
and the amount of open or exposed
ingredients and mixtures, require
stringent housekeeping and cleanliness.
Materials control and cleanliness are
mandatory not only to reduce the
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
likelihood of accidental initiations, but
also to minimize the effects of a mishap.
(1) Do not allow ingredient or
composition dusts to accumulate,
whether on the exterior work surfaces or
the interior of process equipment and
ventilation systems. (Note: Accident
investigations frequently identify dust
buildups as the source of initiation
when items are dropped on, or scraped
across them.) Dust accumulations also
provide a propagation path, which can
follow from initiation to a significant
source of material, causing an accident.
(2) Similarly, where flammable
solvents are part of the process, positive
vapor control is mandatory to prevent
initiation of a solvent vapor cloud,
which may be injurious in itself, or may
be the propagation path which ignites a
mixture. Just as dusts in ventilation
systems may provide a propagation path
for an event, solvent vapors in
ventilation systems, hallways, conduits,
or pipes may also provide a propagation
path.
(3) As many pyrotechnic ingredients,
mixtures or the solvents used in their
production are highly susceptible to
initiation by static electricity, static
control systems (i.e., conductive floors/
mats, shoes, wrist straps, grounding of
equipment, etc.) are mandatory where
hazard analysis indicates a need for
static control.
(4) For all pyrotechnic operations, a
documented hazard analysis and risk
assessment is mandatory to validate the
layout of operations, selection of
materials and equipment, and process
control parameters. See § 184.11.
(5) Weighing raw materials. Positive
means of separation of fuels and
oxidizers is mandatory. The scale of the
operation will dictate whether separate
rooms, cubicles, areas, or other means
for separation are required. It is
important that equipment (e.g.,
containers, hand tools, scale pans, etc.)
used for weighing fuels or oxidizers are
not interchanged or shared among
incompatible operations, unless
thoroughly cleaned between fuel and
oxidizer use, particularly where
distance rather than physical barriers
separates these areas. A hazard analysis
shall determine appropriate personnel
protective equipment for personnel
weighing or handling exposed oxidizers
or fuels.
(6) Drying materials. Drying materials
may result in the generation of
flammable vapors or dust which have
the potential to create an explosive
atmosphere. The dust settling out of the
atmosphere may increase in sensitivity.
Operational hazard analysis must
address these possibilities and the
possibility of initiation by over-
PO 00000
Frm 00018
Fmt 4701
Sfmt 4702
temperature or extended heating. Use
the minimum temperature necessary for
drying component and pyrotechnic
materials. Dust and residue control is
very important in drying operations, as
elevated temperatures frequently results
in increased sensitivity of materials. The
requirements for drying apparatus are
described in § 184.8.
(7) Mixing and blending. Mixing,
blending, and cleanup of pyrotechnic
compositions from equipment apparatus
require attention because of the high
potential for mishaps during these
operations. As compositions vary, no
single type of mixer or blender can be
the exclusively approved equipment for
pyrotechnic mixing and blending
operations.
(i) Select the mixing equipment and
methods appropriate for each
composition. Hazard analysis or test
shall determine the type of mixer or
blender and batch size. Devices using a
tumbling action eliminate many of the
problems associated with rotating blade
mixers, plows and scrapers. Rotating
blade type mixers create points where
frictional heat may develop or where
accidentally introduced foreign material
can create hot spots through friction or
crushing of the composition. Equip
enclosed mixers and blenders with
pressure relief, to preclude a transition
from burning to detonation. Minimize
personnel exposure when charging and
emptying mixers and blenders. Unless
hazard analysis indicates otherwise,
charge, operate and empty mixers and
blenders remotely. Use appropriate
interlocks, clutch brakes, and similar
devices to preclude personnel exposure
during mixer or blender operation, and
to preclude the movement of mixer or
blender parts during periods when
operators are present.
(ii) Mixing and blending operations
often present a high risk of explosion.
Facility construction and procedural
controls, guided by hazard analysis or
test, must reflect this risk. Prevention of
propagation, protection of production
capability and personnel require
separation and isolation of these
operations. At least one wall or
equivalent panel area in each bay shall
be frangible to provide pressure relief in
case of an incident. Preclude personnel
exposure to pressure relief areas.
(iii) Flammable solvents used in
mixing operations present a potential
fire or explosion vapor hazard. When
flammable solvents are used, install
ventilation equipment, interlocked to
the mixers. Design interlocks to
preclude mixer operation without
ventilation. Ventilation systems must
operate in the presence of solvent
vapors. Vapor sensors provide warning
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
of flammable vapor levels approaching
the lower explosive limit. Design
ventilation systems to prevent
propagation of an incident from one bay
to others served by the same system.
(iv) Prohibit direct viewing of blender
or mixer operations. Use remote means
such as television or mirrors, or
interpose transparent shields.
(v) Prohibit part mixing, blending or
scraping of pyrotechnic composition.
(vi) The following are the minimum
criteria for rotating-blade mixing
operations:
(A) Assure the stability of mixers, and
platforms, to prevent distortion during
operation and resultant contact between
the bowl and blade.
(B) Provide positive controls to
physically block or stop bowl or blender
head movement in case of malfunction
to assure maintenance of clearances
between mixer bowl and blades.
(C) Mixer blades and shaft shall be
rigid and structurally strong to ensure
minimum flex from weight of the mix
and speed of the shaft.
(D) All mixer electrical components
shall meet the appropriate NFPA
Standard No. 70 electrical classification.
(E) The mixer blade shaft shall
include adequate and compatible seals
or packing glands to prevent migration
of mix or solvent vapor into bearings.
Submerged bearings and packing glands
should be avoided. If used, periodically
test packing glands and bearings for
contamination and clean them as
necessary.
(F) Establish a maintenance program
to monitor wear in the mixer blade shaft
and bearings to avoid excess play.
Maintain a record of such checks, mixer
blade adjustments, and any damage to
the mixer blades and bowls. Perform
operational checks of blade/plow and
bowl clearances prior to the
introduction of materials.
(G) Procedures must exclude dry
mixing. Starting the mix with dry
pockets of materials has been the cause
of several serious accidents. Unless
adequate amounts of solvent are added
in an appropriate sequence with dry
ingredients, pockets of dry mix may
remain after solvent addition.
(H) Interlock power to mixers with
fire protection system controls so that
the mixer cannot start when the fire
protection system is inoperative.
(I) Maintain grounding during
charging or discharging of mixes.
(J) Maintain torque limits or amperage
overload protection.
(K) Maintain appropriate solvent traps
for vacuum mixing.
(8) Pressing, extruding, and pelleting.
(i) Few pressing, extruding, or pelleting
operations are sufficiently safe to
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
operate without personnel and facility
protective features. Omit protective
features only when documented hazard
analysis supports direct personnel
involvement. Use substantial dividing
walls, barricades, operational shields or
intraline distance (ILD) to protect
personnel from pressing, extruding or
pelleting operations. (Note: ILD alone
does not provide adequate personnel
protection. For personnel protection by
separation alone, use public traffic route
distance (PTRD).) When it is necessary
to repair, adjust, or otherwise clear a
jam on a press or extruder, remove the
pyrotechnic material from the hopper
and the bay or press room before making
such repairs or adjustments. Only those
adjustments of ram speed or conveyor
speed routinely controlled by the
operator may proceed with material in
the bay. Under no circumstances shall
repair or adjustment require the use of
tools with pyrotechnic material in the
bay.
(ii) Limit the quantity of composition
at the pressing location behind the
barricade to that required for the
components undergoing the pressing
operation. Separate all other quantities
in the bay to prevent propagation from
an event in the press. The quantity of
composition in the remainder of the
building at any one time shall not
exceed the minimum required for a safe,
efficient operation.
(iii) Each individual press, extruder,
or loading device shall be located in a
separate building, room, or cubicle, and
be designed to limit an incident to that
area and protect operators. Tests or a
hazard analysis may be used to
demonstrate that multiple operations in
a bay or cubicle do not jeopardize
personnel or the facility. Due to the
difficulty in positively excluding
propagation to feed hoppers or similar
feeds to the equipment, designs for
pressure relief in case of an incident
must include the quantities in such
hoppers when present.
(9) Assembly operations. Cleanliness
and isolation are important safety
requirements for assembly operations.
Keep individual assembly operations
separate from other assembly, mixing,
blending, and consolidation operations.
Use separate cubicles, bays, or buildings
as dictated by hazard analysis. To
reduce the possibility of accidental
initiation, keep pyrotechnic
compositions (including fuels and
oxidizers) in closed or covered
containers at all times, except during
physical processing (i.e., requiring
access to the material). This is
especially important when materials are
accumulating or in transit between
operations. Limit quantities of
PO 00000
Frm 00019
Fmt 4701
Sfmt 4702
16055
pyrotechnics, including those in
components to the smallest quantity
necessary for safe and efficient
operations.
(10) Granulation, grinding and
screening. Operations which reduce
particle size are particularly hazardous
due to the energy imparted to a material
with an increasing surface area,
including dusts. The materials are often
in their most sensitive form during these
operations.
(i) Remove foreign materials using
mechanical or magnetic screening from
compositions reduced in particle size
both before and after the size reduction
operation.
(ii) Provide positive personnel
protection for the operation of ball
mills, hammer mills, granulators, or
screeners. It is highly desirable to fill
and discharge grinding, granulating, and
screening equipment remotely. Hazard
analysis may dictate that the cleaning of
such devices also requires operator
protection.
(iii) Bond and ground working
surfaces, containers, and hand tools.
(11) Transportation. Transport
pyrotechnic compositions in closed
containers only. Fabricate individual
containers and the transport vehicle
(e.g., handcart, hand truck, etc.) of the
lightest materials compatible with the
composition and having the requisite
strength. This minimizes fragment
generation if an incident occurs. ‘‘Dead
man’’ brakes are often desirable on
transport vehicles. Transport vehicles
require protection from the weather
when loading or unloading. Provide
racks or other support, suited to the size
and shape of composition containers, to
stabilize them in transport.
(12) Rebowling. These operations
transfer materials, typically sensitive
and in small quantities, from one
container to another, to recover remains
of small quantities of materials, or to
subdivide large masses for processing.
Rebowling of dry pyrotechnics
compositions with characteristics
similar to initiating explosives require
operational shields to protect operators.
(13) Machining of pyrotechnic
material. (i) Conduct machining of
pyrotechnic materials remotely.
(ii) Drilling and facing operations
must be done to minimize friction and
heat build-up. Hazard analysis should
address factors including feed rate, type
of composition and tooling.
(iii) Perform hand trimming and
cutting of pyrotechnic candles only
when supported by results of a hazard
analysis specific to that composition
and candle configuration.
(iv) Sawing operations require
particular care to prevent work from
E:\FR\FM\29MRP2.SGM
29MRP2
16056
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
plunging into the saw blade, and to
ensure chip removal from saw teeth
before subsequent cutting passes.
Plunging can occur when thin sections
are force fed into coarse pitch saw
blades. To prevent this, the work feed
rate shall be controlled. Chip
accumulation in the saw teeth is a
function of the material being sawed,
rate of feed, blade speed, tooth design,
and flushing arrangement.
(d) Spill control. Spills of pyrotechnic
composition and energetic ingredients
pose potential hazards. Notify the
responsible supervisor before any action
to clean or contain the spills. SOP for
pyrotechnic operations shall cover spill
cleanup, either as part of the various
operations detailed or as a separate
procedure. The procedures shall specify
which actions are to be taken by whom
and in what order. The procedures shall
also address recovery of the spilled
material and decontamination of the
area.
(e) Management of pyrotechnic scrap
and rejects. (1) At regular intervals,
remove all pyrotechnic reject materials
and scraps from all operating areas.
Segregate such materials by type and
compatibility, and keep it separate from
common wastes. Use positive
identification systems for containers of
these materials. Place filled containers
at designated collection points.
(2) To prevent undesired reactions,
use special care to preclude the mixing
of water with powdered or finely
granulated metals. Plastic liners for
waste containers facilitate cleaning.
Liners should be conductive when
contents are subject to initiation by
static electrical discharge.
(f) Cleaning of pyrotechnic processing
equipment. (1) Since pyrotechnic
materials are sensitive to friction,
impact, or static discharge, cleaning
equipment contaminated with
pyrotechnic materials poses hazards.
Because personnel are near the
equipment being cleaned, risks may
exceed those of processing. Therefore,
cleaning shall receive the same planning
and SOP coverage as production.
(2) Cleaning procedures must satisfy
environmental and safety concerns. The
use of flammable solvent solutions for
flushing may require remote control.
Minimize the quantity of solvents used.
Control possible run-off from cleaning
operations to preclude the spread of
contamination.
(3) Select personal protective
equipment based on hazard analysis and
test data. Protective equipment must
withstand the maximum credible event
(MCE) when personnel perform cleaning
in the vicinity of equipment and
contamination.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(g) Personal protective equipment. (1)
Engineering controls remain the primary
and preferred means of providing
personnel protection. Unattended
operations, remote controls, substitution
of less hazardous materials, and reduced
quantities are all more effective than
personal protective equipment or
apparel. Personal protective equipment
shall not be relied upon as the primary
means of operator protection.
Operational shields and high-speed
deluge systems may offer supplemental
protection. Operators must use only the
protective equipment and apparel
prescribed by the SOP, and that apparel
or equipment must be that prescribed by
hazard analysis.
(2) The minimum protective apparel
for personnel exposed to open
containers of pyrotechnic or energetic
raw materials shall consist of the
following:
(i) Cotton socks.
(ii) Conductive-soled safety shoes.
(iii) Flame-retardant coveralls, and
(iv) Hair coverings.
(3) All employees exposed to
hazardous quantities of pyrotechnic
compositions shall wear:
(i) Aluminized, thermally protective
suit with hood and faceplate.
(ii) Aluminized, thermally protective
trousers. and
(iii) Aluminized, thermally protective
gloves or equivalent.
(Note: The definition of hazardous
quantities will depend on the
composition’s energy output and
sensitivity (as determined by hazard
analysis or tests) and the nature of the
operation.)
(4) Required levels of protective
apparel shall be specified in appropriate
SOP steps.
(5) When the protective clothing
described in paragraphs (g)(2) and (g)(3)
of this section is required, the design
and wearing shall ensure no exposure of
any area of the body. Use appropriate
seals or joints to preclude flame
intrusion where apparel items overlap
or join. Give particular attention to
possible gaps in coverage provided by
the hood in order to prevent flame or
hot gas impingement on the face, head,
or neck. Protection of the employee’s
throat and lungs may require use of a
self-contained breathing apparatus or
supplied-air respirator from the effects
of a fireball.
(h) Reworking pyrotechnic
components. (1) Perform all repair,
reassembly, or similar operations on
loaded pyrotechnic compositions in a
separate bay used only for that purpose.
(2) Reworking and reusing
pyrotechnic material is desirable from
both an economic and environmental
PO 00000
Frm 00020
Fmt 4701
Sfmt 4702
basis. However, all rework and reuse
concepts require careful analysis to
assure safety. Manage all unused
materials in accordance with local, State
and Federal requirement.
(i) Fire protection. When compatible
with process materials, use deluge
systems for the protection of mixing and
blending operations, screening,
granulation, drying, and pressing or
extrusion operations. Select the
response time of the deluge system to
minimize the damage to process
equipment and facilities. Hazard
analysis of the operation may dictate
other applications.
§ 184.9 Storage of ammunition and
explosives.
(a) General. A properly sited storage
area is mandatory for AE. Earth-covered
magazines (ECM) offer the greatest
protection for the stored AE, and
provide some mitigation of fragments
and over pressures from internal
explosions. Such magazines are
preferred for the storage of all AE.
(b) Magazine operational regulations.
(1) Do not store unpackaged AE and
ammunition components, packing
materials, conveyors, skids, empty
boxes, or other such items in magazines
containing AE. Limited dunnage lumber
may be stored in the magazines, if it
does not block exits or aisles.
(2) All AE containers shall be marked
with a DoD hazard classification/
division, storage compatibility group
and item nomenclature.
(3) While crews are working inside
magazines, keep doors unlocked to
permit rapid egress.
(4) Do not store flammable liquids in
magazines containing AE, except as the
chemical filler of ammunition, or as a
prepackaged storable liquid propellant.
(c) Stacking. (1) Store AE in original
shipping containers or equivalent.
When stacking, group and identify AE
according to lots, if practicable.
(2) Use dunnage to provide
ventilation to all parts of the stack.
(3) Maintain aisles between each stack
to allow inspection, inventory, and
removal for shipment or surveillance
tests. Block storage configuration is
permitted, provided ventilation of
stacks exists. Maintain unobstructed
aisles to permit rapid egress.
(4) Avoid more than one light
(partially filled) box or pallet per lot in
storage. Stack light units to be readily
visible and immediately accessible.
Conspicuously mark incomplete boxes
to identify contents and quantities.
(d) Unpackaged AE items and
damaged containers. (1) When
necessary, store unpackaged AE items in
separate magazines.
E:\FR\FM\29MRP2.SGM
29MRP2
16057
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(2) Do not store damaged containers of
AE in a magazine with serviceable
containers of AE. Repair such containers
or transfer the contents to new or
serviceable containers. Close and
securely fasten covers on containers of
AE allowed in magazines. Close
containers that have been opened before
storing them again. Keep stored
containers free from loose dust and grit.
(3) Do not permit loose powder,
grains, powder dust, or particles of
explosive substances from broken AE or
explosive substance containers in
magazines. In addition, clean up any
spilled explosive substance as soon as
possible and suspend all other work in
the magazine until accomplished. (Note:
Manage explosive residue as a waste in
accordance with § 184.15.)
(e) Maintenance and repairs to
magazines. Perform and document a
hazard analysis, and implement the
recommendations resulting to support
the plans for maintenance and repairs of
magazines containing AE.
(f) Open storage (outdoors). Do not
store AE outdoors.
(g) Storage of bulk initiating
explosives. Bulk initiating explosives
must neither be stored dry nor exposed
to the direct rays of the sun. Containers
of ample size to hold the double bag of
explosives are used for normal storage.
Types of AE range from highly sensitive,
bulk explosive substances (e.g.,
pyrotechnics, propellants and
explosives) to less sensitive, metal-cased
AE (e.g., bombs, torpedoes and artillery
projectiles). For appropriate guidance,
refer to DoD 6055.9–STD or industry
standards for specific storage
requirements applicable to the various
types of AE.
(h) Hazards of long-term storage. (1)
AE may deteriorate in storage. The
method of packaging, extremes of
temperature and humidity during
storage, the length of time the AE is
stored, the nature of the deterioration,
and the explosive substance
compositions used are factors in the rate
and criticality of the deterioration. Any
deterioration that decreases the stability
of the AE increases the risk of autoignition or a handling mishap due to
friction, impact or electrostatic
discharge. The longer that AE remains
in storage, the greater the likelihood that
stocks of AE for issue or use will
deteriorate. Older unstable AE material
should be tracked, identified and
prioritized in the contractor inventory
management programs.
(2) Dispose of unstable AE stock
material in accordance with the
procedures and requirements of
§ 184.15, Collection and Destruction
Requirements for AE. Disposition of
unserviceable AE will be under local
procedures based on the latest available
technical data. Unstable AE includes
substances with totally depleted
stabilizer, misfired ordnance, explosive
devices rendered safe by explosive
ordnance disposal and any similar
items. Unstable AE material is
incompatible with all other AE material
in storage. When available store
different types of unstable AE material
in separate magazines.
(3) Treat AE with unknown stability
as unstable. Examples of AE to treat as
unstable include non-stock material,
dropped or damaged material, material
in substandard packaging, unidentified
material and material not receipt
inspected.
§ 184.10
Fire protection.
(a) General. This section provides:
(1) General requirements for
developing and implementing AE fire
protection and prevention programs,
and
(2) Standard fire fighting hazard
identification measures to ensure a
minimum practicable risk in fighting
fires involving AE.
(b) Fire plan. (1) A written fire plan
shall be prepared which itemizes the
emergency functions of each department
or outside agency and indicates
responsible individuals and alternates.
(2) When the contractor has an
internal fire department or brigade,
plant officials have the responsibility for
firefighting procedures, training of
firefighting personnel, the use and
maintenance of firefighting equipment
and vehicles, the provision of water
supply and alarm systems and first aid
measures required in firefighting.
(3) Firefighting agreements. Voluntary
and mutual agreements with local
municipalities or industrial centers
shall include AE firefighting guidelines
(see paragraph (i) of this section).
Contractor officials are responsible for
informing the firefighters of AE hazards.
(c) Smoking. Smoking may take place
only in safe, specifically designated and
posted ‘‘smoking locations.’’ Personnel
shall not wear clothing contaminated
with explosives or other dangerous
material in smoking locations.
(d) Hot work permits. A written
permit shall be required for the
temporary use of heat-producing
equipment or devices when explosives
or highly flammable materials are
involved.
(e) Portable fire extinguishers. Hand
extinguishers within buildings can
extinguish fires before major damage is
done. Portable equipment may prove
similarly valuable outside aboveground
magazines (AGM) and other buildings
with AE. Portable fire extinguishers will
be maintained in accordance with NFPA
Standard No. 10.
(f) Fire hazard identification system.
(1) The contractor shall establish a fire
hazard identification system. This
system shall assess the relative dangers,
up to the most hazardous material
stored. The system must include
placards on AE buildings.
(2) One such system is the DoD Fire
Identification System, which consists of
six fire divisions (1–6) which
correspond to Hazard Division (HD) 1.1
through HD 1.6. Fire Division 1
indicates the greatest hazard. The
hazard decreases with ascending fire
division numbers from 1 to 4. Fire
Divisions 5 and 6 refer to explosion
hazards from less sensitive substances
and extremely insensitive articles.
(3) Fire division symbols.
(i) The six fire divisions are indicated
by four distinctive symbols (see Table 1
to § 184.10 and Figure 1 to § 184.10) in
order to be visually recognized by the
firefighting personnel from a distance.
The number is shown on each symbol
indicating the type of AE present.
Reflecting or luminous symbols should
be used. For application on doors or
lockers inside buildings, half-sized
symbols may be used.
(ii) The symbols are orange and each
number identifying the fire division is
black.
TABLE 1 TO § 184.10—FIRE DIVISION MARKINGS
Fire
division
1
2
3
4
5
..............................
..............................
..............................
..............................
..............................
VerDate jul<14>2003
Hazard involved
Shape
Mass detonation ..........................................................................................................................
Explosion with fragment hazard ..................................................................................................
Mass fire ......................................................................................................................................
Moderate fire ...............................................................................................................................
Mass Explosion (blasting agents) ...............................................................................................
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00021
Fmt 4701
Sfmt 4702
E:\FR\FM\29MRP2.SGM
29MRP2
Octagon.
Cross.
Inverted triangle.
Diamond.
Octagon.
16058
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
TABLE 1 TO § 184.10—FIRE DIVISION MARKINGS—Continued
Fire
division
Hazard involved
6 ..............................
Nonmass explosion (EIDS article) ..............................................................................................
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00022
Fmt 4701
Sfmt 4702
Shape
E:\FR\FM\29MRP2.SGM
29MRP2
Cross.
(g) NFPA Standard no. 704 standard
system for the identification of the
hazards of materials for emergency
response. NFPA Standard No. 704
provides a simple, readily recognized
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
and understood system of marking
which many fire departments prefer for
response. This system identifies the
hazard and severity of materials and
may be used in lieu of the DoD fire
PO 00000
Frm 00023
Fmt 4701
Sfmt 4702
16059
hazard symbols. The system identifies
the hazards of a material in terms of
three categories: Health, flammability
and stability. This system indicates the
degree of severity by a numerical rating
E:\FR\FM\29MRP2.SGM
29MRP2
EP29MR05.000
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
16060
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
relative rather than absolute values. For
assignment of hazards, see NFPA
Standard No. 49 and NFPA Standard
No. 325.4 Figure 2 to § 184.10 through
Figure 4 to § 184.10. present an
overview of the NFPA marking system.
4 NFPA Standard No. 704, NFPA Standard No. 49
and NFPA Standard No. 325 are all contained in
‘‘Fire Protection Guide to Hazardous Materials,’’
2001 Edition, ISBN# 087765435, available at
https://www.nfpa.org/catalog/home/index.asp.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00024
Fmt 4701
Sfmt 4725
E:\FR\FM\29MRP2.SGM
29MRP2
EP29MR05.001
which ranges from four (4), indicating
severe hazard, to zero (0), indicating
minimal hazard. The system is based on
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
known hazards and conditions existing
at the scene of the fire before proceeding
to its location.
(ii) Fire involving AE shall be fought
according to the appropriate response
for hazard or fire division and the stage
of the fire.
(iii) All fires starting in the vicinity of
AE should be reported and should be
PO 00000
Frm 00025
Fmt 4701
Sfmt 4702
fought immediately with all available
means. However, if the fire involves
explosive substance, is supplying heat
to them, or if the fire is so large that it
cannot be extinguished with the
equipment at hand, the personnel
involved shall evacuate and seek safety.
E:\FR\FM\29MRP2.SGM
29MRP2
EP29MR05.002
(h) Firefighting procedures. (1)
General. (i) Firefighters of AE fires must
have a thorough knowledge of the
specific reactions of AE exposed to heat
or to fire. The firefighting forces and
other essential personnel shall be
briefed before approaching the scene of
the fire. They shall be informed of the
16061
16062
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(iv) Emergency withdrawal distances
for non-essential personnel are intended
for application in emergency situations
only and not facility siting. Emergency
withdrawal distances depend on fire
involvement and on whether fire
division and net explosive weight
(NEW) are known. Emergency
authorities shall determine the
withdrawal distance for essential
personnel at the fire. Emergency
authorities shall determine who are
essential personnel.
(v) If a fire involves explosive
substance, the initial withdrawal
distance applied shall be at least to the
inhabited building distance (IBD). See
Table 2 to § 184.10. If fire does not
involve explosive substances,
emergency authorities shall determine
the withdrawal distance based on the
situation at hand.
(vi) Structures or protected locations
offering equivalent protection for the
distances listed in Table 2 to § 184.10
may be used in lieu of relocating
personnel from the structure and/or
location to the specified emergency
withdrawal distance.
(vii) Contractors should develop
evacuation plans for their facilities
which reference the appropriate
withdrawal distances as part of the
emergency response plan. Contractor
personnel are responsible for alerting
local authorities of any imminent
explosive accident on the facility which
may affect the local community and for
providing local authorities with the
appropriate emergency withdrawal
distances.
(2) Specific. (i) Contractors shall train
operational personnel on the
characteristics of explosive substances,
including their reactions to heat and
fire, as well as what to do in case of fire.
Personnel shall not attempt to fight fires
involving Hazard Division (HD) 1.1 and
HD 1.2 AE. These AE detonate with a
fragmentation hazard, and personnel
shall evacuate immediately, using
protective cover where available and
activating deluge systems and fire
alarms while escaping. Individuals
remain in danger until they reach
shelter, although reaching IBD in the
open affords some safety. Exit drills
should be conducted annually and
during exit drills, employees shall be
advised of the safest escape routes and
evacuation points.
TABLE 2 TO § 184.10.—EMERGENCY WITHDRAWAL DISTANCES FOR NONESSENTIAL PERSONNEL
Unknown quantity
Known quantity
Unknown, located in facility, truck and or
tractor trailer
4,000 ft (1,220 m)
4,000 ft (1,220 m).
Unknown, located in railcar
5,000 ft (1,524 m)
5,000 ft (1,524 m).
1.1 and 1.5 1
For transportation, use 2,500 ft (762 m) minimum distance for 500 lb (227 kg) and below. Above
500 lb (227 kg), for rail cars use 5,000 ft (1,524 m) minimum distance, otherwise use 4,000 ft
(1,220 m) minimum distance. Use 4,000 ft (1,220 m) minimum distance for bombs and projectiles with caliber 5 in (127 mm) or greater.
For facilities, use 2,500 ft (762 m) minimum distance for 15,000 lb (6,804 kg) and below. Use
4,000 ft (1,220 m) minimum distance for net explosive weights above 15,000 lb (6,804 kg) and
less than or equal to 50,000 lb (22,680 kg). Above 50,000 lb (22,680 kg), use
d = 105 W 1⁄3.
VerDate jul<14>2003
Same as unknown facility,
truck trailer or railcar as
appropriate
21:15 Mar 28, 2005
Jkt 205001
PO 00000
Frm 00026
Fmt 4701
Sfmt 4702
E:\FR\FM\29MRP2.SGM
29MRP2
EP29MR05.003
Hazard division
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
16063
TABLE 2 TO § 184.10.—EMERGENCY WITHDRAWAL DISTANCES FOR NONESSENTIAL PERSONNEL—Continued
1.2 (1.2.1,
1.2.2, and
1.2.3) 1.6 1
2,500 ft (762 m)
2,500 ft (762 m).
1.3 2
600 ft (183 m)
Twice the IBD (Table C9.T10.) with a 600 ft (183 m) minimum range.
1.4
300 ft (91 m)
300 ft (91 m).
1 For
HD 1.1 and HE 1.2 AE, if known, the maximum range fragments and debris will be thrown (including the interaction effects of stacks of
items, but excluding lugs, strongbacks, or nose and tail plates) may be used to replace the minimum range.
2 For accidents involving propulsion units, it is not required to specify emergency withdrawal distances based upon the potential flight ranges of
these items.
3 This is the quantity-distance formula. 105 is the K-factor, a constant, and respresents the degree of damage which is acceptable in this situation. The distance d is in feet and W is the net explosive weight in pounds.
(ii) If the fire in a HD 1.1 or HD 1.2
building does not directly involve
explosive substances and is small or in
a segregated container, an attempt
should be made to extinguish the fire.
After summoning firefighters,
responsible contractor personnel shall
meet them as they approach the facility
to brief them. When HD 1.1 or HD 1.2
AE is directly involved, firefighting
forces should maintain IBD from the
fire. The safety of personnel fighting a
HD 1.1 or HD 1.2 fire depends on the
accuracy of the information made
available to all firefighting forces. No
person shall re-enter a burning building
containing HD 1.1 or HD 1.2 AE.
(iii) Personnel in the immediate
vicinity of HD 1.3 AE should activate
deluge systems and alarms. Unless the
fire is minor, involves no explosive, and
appears controllable, firefighters shall
confine their efforts to prevent it from
spreading to other buildings. Fire in HD
1.3 AE creates a wide area of intense
radiant heat, dangerous to personnel
and equipment. The firefighters should
exercise extreme caution.
(iv) HD 1.4 AE presents a moderate
fire hazard. Fires involving this material
shall be fought until extinguished
unless emergency authorities determine
to evacuate.
(i) Emergency planning. Contractors
shall develop procedures or plans to
provide safety, security, and
environmental protection. Plans shall be
coordinated with the applicable Federal,
state, and local emergency response
authorities (e.g., law enforcement, fire
departments, and hospitals, etc.). At a
minimum, those procedures or plans
shall include provisions for complying
with Section 301–312 of the Emergency
Planning Community Right to Know Act
(EPCRA).
(j) Automatic sprinkler systems.
Properly installed and maintained
automatic sprinklers reduce fire losses.
They are particularly useful for load
lines, AE manufacturing, receiving,
shipping, inspection, and workshops,
and demilitarization.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(k) Deluge systems. (1) Contractors
may use deluge systems to supplement
sprinklers, when the hazards are high,
such as in powder hoppers and cutters.
Rate of rise, light actuating, ultraviolet,
or other quick-action devices for
automatic control of deluge systems are
recommended. Part controls should
serve as backup.
(2) To ensure immediate drenching of
AE material, the distribution outlets
(nozzles, sprays, heads, etc.) should be
as near the explosive’s exposed surface
as permitted by the outlet discharge
pattern. When explosives are under
tight hoods or covers inside machines,
distributing outlets belong inside the
enclosed space.
(3) Nonmetallic, internally-springheld caps should protect outlets
exposed to explosive vapors, gases, or
dust. Upon exertion of pressure within
the outlet, the cap shall immediately
pop. Caps should be attached to outlets
to prevent their dropping into
equipment during a deluge.
(4) Water flow and pressure should be
determined for the hazard.
(5) Periodic inspections of deluge
systems shall ensure that they are in
proper operating condition.
(6) The deluge valve should allow for
automatic and part activation. Part
activation devices shall be placed at the
operator station or at exits in explosive
operating buildings as determine by a
hazard analysis.
(7) NFPA Standard No. 13 and NFPA
Standard No. 15 contain basic
installation rules.
(l) Firebreaks. A firebreak is an area of
bare ground or vegetation intended to
limit the probability of fires causing a
hazard to AE areas. A firebreak, at least
50 ft (15 m) wide shall be maintained in
all directions around magazine and AE
operating buildings or locations.
Barricades and other sloping ground,
within the firebreak area, should retain
enough vegetation to prevent significant
erosion. Growth of vegetation within a
firebreak shall be controlled to prevent
rapid transmission of fire. Relatively
PO 00000
Frm 00027
Fmt 4701
Sfmt 4702
long vegetation of 6 to 8 in (152 to 203
mm) in length, which is green or
sparsely spread, is acceptable. Do not
allow vegetation to become dry or
dense. This could allow rapid
transmission of fire.
§ 184.11 Risk identification and
management.
(a) General. AE operations involve
many hazards and risks. These include
the type of hazards associated with any
industrial enterprise (e.g., lifting,
slipping, tool use, toxic chemicals,
potential exposures to environmental
extremes, etc.).
(1) The evaluation of hazards and risk
of mishap addressed in this section
relate to processes not end products.
The safety of operations is a contractor
responsibility. Only the Government
can accept risk for the AE it acquires
and uses.
(2) A basic risk identification and
management system is a necessary
element of a comprehensive AE safety
program. The purpose of this chapter is
to address risk identification and
management for all AE operations.
(b) Risk management system.
Contractors shall have a risk
identification and management system,
which, as a minimum, results in the
analysis of materials, equipment, and
personnel capabilities. This analysis
will aide in the development of a
written SOP for AE contract operations.
The contractor shall document the
analysis and keep it as long as the SOP
is active.
The analysis shall include such
factors as: Initiation sensitivity, quantity
of materials, heat output, rate of
burning, potential ignition and
initiation sources, protection
capabilities of shields, various types of
clothing, fire protection systems, and
personnel exposure with special
considerations (such as toxic or
corrosive chemicals).
(1) The contractor shall perform risk
analysis using personnel knowledgeable
in the process, materials, equipment and
relevant safety requirements.
E:\FR\FM\29MRP2.SGM
29MRP2
16064
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(2) Hazard and risk. (i) A hazard is
any condition, which, by itself or by
interacting with other variables, may
result in death or injury to personnel or
damage to property. Controls only
reduce the likelihood or severity of
hazards. They do not eliminate them.
(ii) After identifying a hazard,
qualified contractor personnel shall
determine the associated risk. The risk
analysis shall address both the severity
of a resulting mishap and the
probability of occurrence of a mishap. A
risk deals with the mishap which arises
from a hazard, considering both the
severity of its potential consequences,
and its likelihood of occurrence over
time.
(iii) Evaluation of the hazard provides
information useful for ranking the
degree of risk associated with a hazard.
The degree of risk indicates which
hazardous conditions should receive
priority for corrective action when
compared to other hazardous
conditions. One technique for ranking
hazardous conditions is the assignment
of a Risk Assessment Code (RAC). Table
1 to § 184.11 is an example of a risk
matrix. The evaluation of the hazard
results in the assignment of a narrative
or numerical risk assessment such
which management can judge the
seriousness of the risk before and after
action is taken to control it. Table 1 to
§ 184.11 shows one risk matrix used by
the Department of Defense. Definitions
of the code numbers and letters are
contained in Table 2 to § 184.11.
TABLE 1 TO § 184.11.—SAMPLE RISK
MATRIX FORMAT
Mishap probability
Mishap
severity
A
B
C
D
I .................
II ................
III ...............
IV ..............
1
1
2
4
1
2
3
4
2
3
4
5
4
4
5
5
TABLE 2 TO § 184.11.—RISK ASSESSMENT DEFINITIONS
Risk assessment
codes (RAC)
Mishap severity
Mishap probability
I. A mishap which could result in the death or permanent disability, or result in
the inability to deliver the contract item.
II. A mishap which could result in permanent partial disability or temporary total
disability, in excess of three months, or result in late delivery, 30 days or
more, of the contract item.
III. A mishap which could result in lost workdays or compensation for employees, or result in the late delivery, less that 30 days, of the contract item.
IV. A mishap which could result in first aid or minor supportive medical treatment, or damage to process equipment or product but would not affect the
delivery of the contract item.
A. Likely to occur immediately ..............
1. Critical.
B. Probably will occur in time ................
2. Serious.
C. Possible to occur in time ..................
3. Moderate.
D. Unlikely to occur ...............................
4. Minor
5. Negligible.
(c) Analytical methods. There are a
number of analytical methods or
approaches to the performance of
hazard/risk analyses. The complexity of
the process involved, the number of
variables, and the severity of the
consequences of failure should
determine the level and methodology of
the analysis used. The contractor shall
select the level and best method for
performing the analysis.
(1) As a minimum, contractors shall
break the total process into successive
steps and assess the hazards and risks
for each process step. A sample format
for conducting such an analysis is
contained in Table 1 to § 184.11. Any
format, which provides essentially the
same information, is acceptable.
(2) A significant percentage of
accidents occur during intermittent
operations such as setup, startup,
maintenance, repair, response to out-oftolerance operation, and shut down/
clean-up. Therefore analyses must
consider intermittent operations as well
as normal operations.
(3) Risk decisions must not only
consider the severity and probability of
a process change failure, but also
recognize the criticality of operations
(e.g., dollar value, lead time to procure,
significance to end item or process,
etc.).
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(d) Information for analysis. (1)
Contractors shall develop and use a
methodology to address any change to
an AE operation which may present a
new hazard or increase the risk of a
present hazard before incorporating the
change into an operation.
(2) Before introducing a change to an
AE operation, contractors shall perform
a hazard analysis. Contractors shall
maintain documentation explaining
how they will control the hazard or
hazards if the analysis indicates the
change will result in any new hazards,
or increase the risk of present hazards.
Contractors shall validate the hazard
controls for the changed operation, and
maintain documentation of the
validation.
(3) Contractors shall use the
information acquired from the hazard
analysis and validation process to revise
SOPs and retrain employees.
§ 184.12
AE building design and layout.
(a) General. The design and layout of
AE buildings are critical considerations
in explosive safety and directly impact
Q–D requirements and hazardous
exposures to operating personnel and
valuable equipment. Preplanning and
proper design can significantly reduce
risk of injury and property loss.
PO 00000
Frm 00028
Fmt 4701
Sfmt 4702
(b) Building exteriors. Fire, fragment
generation, venting, and evacuation are
critical design parameters. Exterior wall
and roof coverings of AE operating
buildings shall be designed with
noncombustible and, whenever
possible, frangible (breakaway)
construction. AE buildings should be
one story, except to meet process
requirements. Basements should not be
used, since they expose personnel above
and make evacuation difficult.
(c) Interior walls, roofs and ceilings.
Roofs and walls of AE buildings shall be
as light as practicable to vent an internal
explosion and produce the smallest
number of fragments. Firewalls and
dividing walls constitute exceptions. AE
buildings which might house loose,
finely divided explosive substances
require smooth, fire resistive walls and
ceilings which are free from cracks and
crevices. When appropriate, paint walls
and ceilings with high gloss paint to
minimize dust accumulation and
facilitate cleaning. Avoid ledges that
collect dust. Bevel and keep clean all
existing ledges. Seal all wall joints and
openings for wiring and plumbing
against dust. Do not install suspended
ceilings or construct hollow walls in
Class II Hazardous Locations as defined
by the NFPA Standard No. 70. Install
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
insulation and covering directly on the
underside of the roof deck.
(d) Floors and work surfaces.
Construct and finish floors and work
surfaces to facilitate cleaning, with no
cracks or crevices in which explosives
could lodge and no exposed nails,
screws, or bolts. Cove bases at the
junctions of walls and floors should be
used. All locations where exposed
explosives or hazardous concentrations
of flammable vapor or gas are present
require non-sparking floors and work
surfaces.
(e) Substantial dividing wall. (1)
Substantial dividing walls, constructed
in accordance with the requirements of
Army TM 5–1300, Navy NAVFAC P–
397, or Air Force AFR 88–22 (different
designations for the same publication),
separate independent quantities of HE
so they do not need to be added when
determining Q–D requirements.
(2) Avoid openings in dividing walls
for conveyors, pass-through boxes, or
other uses when possible. When
operationally necessary, design closures
with equivalent wall-strength
characteristics.
(f) Exits and doors. Facility design
and operational flow shall eliminate all
explosive hazards between an operator
and an exit. AE building design should
include casement-type exit doors glazed
with non-shattering plastic material. All
interior doors should open in the
direction of the flow of material through
the building and should open onto
unobstructed passageways.
(g) Emergency egress. When hazard
analysis determines that standard exits
and fire escapes are inadequate from
work levels above the ground floor,
other means of emergency egress (e.g.,
safety chutes) shall aid evacuation.
(h) Passageways. Design of weatherprotected passageways between
buildings or magazines should include
noncombustible construction and fire
stops.
(i) Roads and walkways. The road
system should provide alternate routes
between inert locations without entering
AE areas. Roads in AE areas shall not
dead end unless they dead end at, and
serve a single AE location. Facility
design should provide hard-surface
walkways and roads at the entrance to
or between AE buildings to prevent
employees from tracking such potential
hazards as stones, grit, and other foreign
material into operating buildings.
(j) Windows and skylights. The use of
conventional glass in areas with a
potential blast overpressure hazard
creates a serious secondary
fragmentation hazard. Use safety glass
or non-shattering plastic materials (e.g.,
Lexan, Plexiglas) when practical. When
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
glazing with conventional glass is used,
properly fixed plastic or wire mesh
screening may reduce the hazard.
(k) Drains and sumps. (1) All drain
lines handling explosive wastes shall
have sumps or basins of sufficient
capacity for the removal of explosives
by settling. The drains shall have
adequate capacity. be free of pockets.
and have slopes of at least 0.25 in/ft (21
mm/m) to prevent explosives settlingout in the drain line. Design of sumps
shall prevent suspended and settleable
solid explosive material from passing
beyond the sumps in the wash water,
and prevent overflow from disturbing
any floating solids. The settling rate of
the material and the usual rate of flow
shall determine the sump capacity. The
design shall also permit easy removal of
collected explosives, and shall allow for
retention of those that float on water
until they can be removed. Sump tanks
or other types of construction (e.g.,
bolted) that permit the explosives to
settle in obscure or hidden spaces are
not acceptable.
(2) Care shall be taken to preclude
deposition of explosives from sump
effluent due to drying, temperature
changes, or interaction with other
industrial contaminations. Sweeping
and other dry collecting measures
should be used to keep appreciably
water-soluble explosives out of the
drainage system.
(3) Drains between the source of
explosive and the sump shall have
troughs with rounded bottoms and with
removable ventilated covers to facilitate
inspection for accumulation of
explosives. Waste liquids shall not run
into closed drains and sewers. Inspect
and clean out drains periodically to
prevent the excessive buildup of
explosives. Drains and sewers
containing explosive waste materials
shall not connect into the normal
sewage systems.
(l) Hardware. (1) Facility design shall
provide for non-sparking hardware in
AE areas when hazard analyses
determine sparks provide sufficient
energy to initiate exposed explosive
materials, explosive dusts, or flammable
vapors. Avoid installing hardware (e.g.,
piping and ducts) on blowout panels or
walls
(2) Some fasteners (e.g., nuts and
bolts) on or near operating equipment
can fall into explosives or explosive
constituents and cause friction, heat,
and initiation. Operating personnel
shall secure such fasteners using safety
wire or other methods.
(m) Ventilation. Exhaust fans through
which combustible dust or flammable
vapor pass shall use nonferrous blades,
or a casting lined with nonferrous
PO 00000
Frm 00029
Fmt 4701
Sfmt 4702
16065
material. Motors shall meet NFPA
Standard No. 70 rating for the hazard
classification of its location.
Maintenance personnel shall electrically
bond and ground the entire exhaust
system and clean and service it on a
regular schedule.
(n) Steam for processing and heating.
Process steam is that which is in direct
contact with explosives, used directly in
their manufacture, or which, in case of
equipment failure, would exhaust
directly into contact with explosives or
explosive fumes. Avoid steam or hot
water pipes contacting wood, paper, or
other combustible materials.
(1) Steam temperature. The exterior of
pipes shall not exceed 160 °F (71 °C).
Maximum steam temperature should
not exceed 228 °F (109 °C). When steam
temperature must exceed 228 °F (109 °C)
in hazardous locations, cover and paint
the steam lines with an impervious
material or otherwise protect them
against contact with explosives.
(2) Steam pressure. Steam used for
heating AE operating buildings should
have a maximum pressure of 5 psi (34.5
kPa). Steam pressure shall not exceed 15
psi (103.4 kPa). When a reducing valve
is used, never bypass the relief valve in
a manner permitting circumvention of
the pressure reduction equipment.
Positive means shall prevent the
production of superheated steam caused
by the throttling action of reducing
valves. The use of a ‘‘water leg’’ or water
column is recommend to control steam
pressure of 5 psi (34.5 kPa) or less.
When close control of steam
temperature is necessary, install
indicating and recording pressure or
temperature gauges. Maintenance
personnel should test such devices
periodically and record the test results.
When electrical resistance to ground is
high, properly ground steam lines where
they enter buildings.
(o) Tunnels. The design and
construction of tunnels between AE
buildings requires special consideration
due to possible communication of an
explosion by shockwave and blast.
§ 184.13 Safety requirements for specific
AE and AE operations.
(a) General. This section provides the
minimum safety requirements necessary
for the prevention of mishaps involving
specific AE and AE operations. The
contractor is responsible for analyzing
each operation and developing
procedures to control or eliminate
hazards.
(b) Properties of explosives.
Knowledge of properties of specific
types of explosives is critical to the
establishment of proper hazard controls.
E:\FR\FM\29MRP2.SGM
29MRP2
16066
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(1) Primary (initiating) explosives.
Initiating explosives include lead azide,
lead styphnate, and tetracene. They are
extremely sensitive to friction, heat,
electrostatic discharge and impact.
When involved in a fire, they may
detonate.
(i) In storage, initiating explosives
shall be kept wet with water or water/
alcohol mixtures to reduce sensitivity.
Take every precaution to prevent the
liquid from freezing since this increases
sensitivity. Handling of frozen initiating
explosives is prohibited. Assure the
water used for storage is free of bacteria
forming impurities which could react to
form gases and rupture containers.
(ii) Operators shall keep work areas
and equipment clean and maintain good
housekeeping to prevent contamination
of these explosives with foreign,
particularly gritty, material markedly
increases their sensitivity.
(iii) Do not allow lead azide to contact
copper, zinc, or alloys containing any
concentration of such metals because of
the likely formation of other azides that
are more sensitive than the original.
Similar hazards exist for other
explosives.
(2) Secondary (boostering and
bursting) explosives. Boostering and
bursting explosives include tetryl, RDX,
PETN, HMX and compositions
manufactured with these explosives.
These explosives have sensitivities
between initiating explosives and those
of explosives used as main charges such
as TNT. They may be ignited by heat,
friction, or impact and may detonate
when burned in large quantities or at
too great a depth. Some of these
materials are toxic when taken
internally or by skin contact and special
precautions are necessary to protect
personnel. Use local exhaust
ventilation, enclosed process systems,
automatic handling systems, etc., to
minimize dust in the employee’s
breathing zone.
(3) Main charge explosives. Main
charge explosives include TNT, tritonal,
RDX , HMX, CL–20, and compositions
manufactured with these explosives.
Use process hazard analysis to evaluate
the safety of the processing
methodology, (e.g., melt-cast, extrusion,
press and machine, and mix-cast-cure
versus sensitivity characteristics). Do
not permit alkaline cleaning agents or
other alkaline products in buildings
where large quantities of these
explosives are handled.
(4) Other explosives. Other common
military explosives encountered include
black powder and nitroglycerin (NG).
Black powder is a mixture of potassium
or sodium nitrate, charcoal, and sulfur,
which is highly sensitive to friction,
heat, and impact. It deteriorates rapidly
after absorption of moisture, but retains
its explosive properties indefinitely if
kept dry. NG’s extreme sensitivity to
impact and friction is such that it is
manufactured only as needed. Frozen
nitroglycerin, while less sensitive than
liquid, may undergo internal changes
upon thawing and, if enough heat is
generated, may detonate.
(5) Research of additional properties.
Contractors must investigate pertinent
properties before handling other
explosive substances. Sensitivity data
for the same characteristic, generated on
different types of equipment, are not
necessarily comparable. Contractors
must thoroughly understand the
sensitivity test method employed, the
unit of measure in which data are
presented, and the relative ranking of
the explosive verses other similar
explosives.
(c) Laboratory operations. (1)
Research and development laboratories
and testing facilities constitute a
separate category involving guidance,
restrictions, and relief from certain
requirements prescribed in this part.
(2) Review each operation at facilities
designed for blast and fragment
confinement to ensure that the
explosives limits are within the
laboratory or test area capability.
Decrease explosives limits and increase
safe separation distances as the
capability to confine fragment and blast
decreases.
(3) Inspect a total confinement facility
after a detonation to ensure structural
integrity. It may become necessary to
reduce the explosives limits to prevent
future blasts from exceeding the
retention capability.
(4) Review each proposed program for
the laboratory or test facility to
determine all potential hazards
including the following considerations:
(i) Structural limitations of the
facility.
(ii) Remote control viewing and
operating equipment, if required.
(iii) Special safety precautions for
personnel elsewhere in the building.
(iv) Safe separation distances.
(v) Required deviations from other
sections of this part.
(vi) SOP, which shall, at a minimum,
include the following:
(A) Protective clothing.
(B) Warning signals.
(C) Fire and other emergency
procedures.
(D) Special testing of equipment
needed before operations (e.g., stray
voltage and calibration checks).
(E) Removal of all explosives not
needed for the operation.
(F) Arrangements for overnight
storage of necessary explosives.
(G) Inspection and cleanup
procedures after a test or detonation.
(5) Use no more explosives than
absolutely required for a given
operation. Perform particularly
hazardous laboratory operations
involving new or relatively unknown
explosives by remote control. Use
operational shields in these operations
and in new or untested applications of
explosives.
(6) When laboratories and testing
facilities are shielded properly to
prevent the release of fragments, the
minimum incremental safe separation
distances shown in Table 1 to § 184.13
apply to operations, facilities, and
personnel.
(7) If the proposed storage facilities
will confine the blast and fragments, or
if the incremental safe separation
distances are as indicated in paragraph
(c)(6) of this section, up to 15 lbs (6.8
kg) of explosive substance may be stored
without consideration of storage
compatibility. Review the operation to
determine all potential hazards prior to
use as outlined in paragraph (c)(6) of
this section.
TABLE 1 TO § 184.13—LABORATORY Q–D REQUIREMENTS
Distance (ft) 1
Quantity (lbs)
Over
Not over
IBD
PTRD
ILD
Hazard Division 1.1
0
1
2
5
VerDate jul<14>2003
21:15 Mar 28, 2005
1
2
5
10
Jkt 205001
PO 00000
Frm 00030
40
50
70
90
Fmt 4701
Sfmt 4702
E:\FR\FM\29MRP2.SGM
25
30
40
55
29MRP2
20
25
30
35
16067
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
TABLE 1 TO § 184.13—LABORATORY Q–D REQUIREMENTS—Continued
Distance (ft) 1
Quantity (lbs)
Over
Not over
IBD
10
20
30
40
20
30
40
50
PTRD
110
125
140
150
Quantity (lbs)
Over
ILD
65
75
85
90
45
50
55
60
Distance (ft)
Not over
IBD
PTRD
ILD
Hazard Division 1.3
0
5
10
20
30
50
80
100
150
5
10
20
30
50
80
100
150
200
10
15
20
25
30
35
40
45
50
10
15
20
25
30
35
40
45
50
10
15
20
25
30
35
40
45
50
1 The distance above may be used only when structures, blast mats, and so forth, can completely contain fragments and debris. If fragments
cannot be contained or the quantity of high explosives exceeds 50 pounds, then the distances shall be obtained from the Q/D tables of DoD
6055.9 (reference (a)).
(d) Heat conditioning of AE. (1) All
ovens, conditioning chambers, dry
houses and other devices and facilities
which are capable, in ordinary service,
of heating AE to temperatures in excess
of 90° F (32° C) are heat-conditioning
devices. Provide heat-conditioning
devices with dual independent fail-safe
heat controls. For devices or facilities
heated by steam only, the requirement
for dual heat controls is satisfied if the
steam pressure is controlled by a
reducing valve (maximum pressure of 5
psi, (34.45 kPa), unless otherwise
authorized) on the main building steam
supply, and a thermostat.
(2) Ensure heat-conditioning devices
are able to discharge overpressure from
an internal explosion. Use barriers or
catching devices to restrain blowout
panels, doors, and other venting
apparatus and prevent excessive
displacement during an accidental
explosion.
(3) Heat-conditioning devices must be
vented to allow any gases produced to
escape.
(4) Steam heat conditioning devices
are preferred. However, when using
electrical heating elements, locate them
where there is no possibility of contact
with explosives or flammable materials.
(5) Ensure the blades of a fan in a
heat-conditioning device are nonsparking and install its electric motor
externally. Do not re-circulate the air if
the heating surfaces exceed 228° F (109°
C) or if the air contains materials which
could collect on the heating coils.
(6) Permit only electrical equipment
and fixtures approved for use in the
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
hazardous atmosphere in question in or
on a heat-conditioning device used for
explosives or flammable material.
(7) Ensure the interior of a heatconditioning device is free of crevices,
openings, and other protuberances not
easily cleaned, where dust or flammable
material could lodge.
(8) Interconnect and electrically
ground all non-current-carrying metal
parts of a heat-conditioning device.
(9) Install heat-conditioning devices
in isolated locations, set up to give
personnel maximum protection from the
effects of an explosion. Use operational
shields and other personnel protection
measures when warranted.
(10) Safe separation distances or
protective construction ensures against
an explosives accident in one heatconditioning device from propagating to
others. Do not place hazardous materials
in a room or cubicle containing a heatconditioning device, unless it can be
shown that a mishap in the conditioning
device would not involve the other
materials.
(11) Operating procedures for heatconditioning devices must:
(i) Limit the explosive materials in the
device to the type and quantity
authorized for the specific device.
(ii) Address the critical parameters of
explosives compositions before
processing in a heat-conditioning
device. Ensure the device does not
exceed limits established for the
hazardous composition being
conditioned.
PO 00000
Frm 00031
Fmt 4701
Sfmt 4702
(iii) Check heat-conditioning device
temperatures at specified intervals
during operation.
(iv) Clean the conditioning devices,
ducts, vacuum lines, and other parts of
the equipment subject to contamination
by hazardous materials, before
introducing a different item or
composition for conditioning.
(e) Spray painting. (1) Do not
electrostatically spray paint loaded AE.
(2) Use water wash or dry filter-type
spray booths for loaded AE.
(3) Interlock controls for ventilating
fan motors for spray painting booths
with the controls for the paint sprayer.
With this arrangement, failure of the
ventilating system will shut off power to
the paint sprayer.
(4) Install high-voltage, electricallypowered, paint-spraying equipment in
accordance with the requirements of
NFPA Standard No. 33 as applicable.
(5) Ensure conventional equipment
used for spray painting in standard
spray booths meets the requirements of
NFPA Standard No. 33. Electrically
ground the nozzles of all spray guns to
suppress static electricity.
(f) Drying AE. Use ovens which
comply with the NFPA Standard No. 70
to dry loaded AE. Other requirements
include the following:
(1) Ensure automatic thermostatic
controls regulate temperatures once they
reach a maximum determined by the AE
involved.
(2) Equip each oven with automatic
internal sprinkler systems which
conform with NFPA Standard No. 13.
Approved electrical heat actuated
E:\FR\FM\29MRP2.SGM
29MRP2
16068
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
devices, installed as required for NFPA
Standard No. 70, Class I, Division 1,
Group D, hazardous locations may be
used for automatic operation of the
system.
(3) Hot air or other means may supply
heat, provided AE does not contact
coils, radiators, and heating elements.
(4) In case of power failure, the heat
supply for any conveyor system must
automatically stop.
(5) Design electric drying units not
approved for use in Class I hazardous
locations so that solvent vapor
concentration in the oven is kept below
25% of its lower explosive limit.
(g) Rework, disassembly, renovation,
and maintenance. (1) Avoid conducting
AE rework and disassembly operations
with other AE or inert operations. When
concurrent scheduling cannot be
avoided, operations shall be sufficiently
separated from one another to protect
adjacent personnel and equipment, and
prevent propagation to adjacent AE.
Separation may be accomplished with
Q–D, operational shielding, or the
remote control of operations.
(2) Protect the worker and all other
personnel from possible initiation when
the force applied during rework or
disassembly is known or expected to
exceed assembly force.
(3) Personnel protection required
during assembly operations is normally
also required during disassembly or
rework operations. Use lesser protection
only if fully supported by a risk
assessment. Verify that assembly was
within specification, the surfaces are not
corroded and whether sealant is present.
(4) Request specific safety guidance
through contract channels when
renovation or maintenance is not
adequately addressed in the contract.
(h) AE loading and associated
operations. (1) Screening and blending
HE. Screen or visually inspect and pass
over a magnetic separator bulk HE
intended for processing to detect
extraneous material. Do not subject HE
to pinching, friction or impact in
screening equipment. Thoroughly clean
HE screening units without exhaust
ventilation as necessary and after every
shift, to prevent hazardous
accumulations of explosives dusts.
(2) Screening and blending initiating
explosives. Provide suitable operational
shields for screening and blending
operations involving initiating
explosives. As an alternative, locate
operators at barricaded ILD from
screening and blending facilities.
(3) Explosives melting. (i) Do not
exceed 228 °F (109 °F) when melting
explosives and keeping explosives
molten. It is permissible to use steam
pressures up to 15 psi (103.35 kPa) (250
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
°F (121 °C) to melt or maintain TNTbased explosives in a molten state.
(ii) Construct and maintain melt unit
valves and melt mix draw-off or other
lines carrying molten explosives to
prevent friction or impact capable of
igniting the explosives. Disassemble and
regularly inspect diaphragm type valves.
Replace damaged or old diaphragms
before cracks develop to prevent metalto-metal contact. Construct draw-off
lines to prevent exposure of threads,
fastening screws, and bolts, both outside
and between the flanges. Use a sealing
compound to prevent explosives
seepage or vapor condensation on the
contacting surfaces of the bolts, flanges,
screws, and nuts. Electrically bond melt
mix kettle draw-off pipes to items being
filled during draw-off operations.
Individually ground AE unless tests
indicate that contact ground is adequate.
(iii) Wet-type collectors remove dust
and vapors from exhausted air, and are
effective for melt mix exhausting
systems. Do not re-circulate water in the
wet collector unless the system removes
hazardous suspensions. Discharge water
retaining explosives to a containment
unit designed to keep them wet.
Regularly inspect and flush the exhaust
and collecting equipment of explosives
accumulations. Equip each kettle with a
complete dust and vapor collection
system when protective construction
prevents propagation of a detonation
between melt kettles.
(4) Agitation. Equip agitation
nitrators, washers, and other machines
with at least two means of agitation,
each operating from an independent
power source. A loss of power if using
only one power source could result in
material decomposition.
(5) Explosives machining. Awareness
of the friction sensitivity of explosives
to be machined is required. Friction
sensitivity values of explosives listed in
paragraphs (h)(5)(ii) and (h)(5)(iii) of
this section are available for
comparison. Compare sensitivity values
only for identical test, methods and
equipment.
(i) HE, cased or uncased, may be
machined without special personnel
protection and without coolant, if no
metal-to-metal contact is involved,
include: TNT, composition B with RDX
at or below 60%, RDX compositions
containing 60% or less RDX and HMX
compositions containing 60% or less
HMX.
(ii) HE, cased or uncased, may be
machined without special personnel
protection provided a coolant is
directed on the tool and explosives at
their point of contact and no metal-tometal contact is involved, include:
Octol, Pentolite (50–50 and 10–90),
PO 00000
Frm 00032
Fmt 4701
Sfmt 4702
HMX compositions with greater than
60% HMX, Cyclotols, Composition B
and RDX compositions with
concentrations of RDX greater than
60%.
(iii) Machine other HE by remote
control, and protect the operators by a
suitable operational shield. Do not
machine primary explosives if you can
obtain desired shapes or sizes by other
means (e.g., forming).
(iv) Use only a single drill bit with a
diameter greater than 0.25 in (0.064 cm)
when an unprotected operator is
involved in drilling.
(v) Permit machining of cased
explosives in an operation requiring
removal of metal before or after tool
contact with the explosives filler.
Protect operators with operational
shields and machine by remote control.
(vi) Where wet machining is
performed, use automatic interlocking
devices to prevent machining unless
coolant is flowing. Establish controls
capable of stopping the machining if the
coolant flow is interrupted. When
coolant flow must stop for adjustment of
machining tools, provide positive means
to ensure that flow of coolant is restored
and all automatic control devices are
operating before machining resumes.
(vii) Maintain the lineal and rotational
speeds of tools used for the machining
of explosives at the minimum required
to perform the operation safely and
efficiently. The rate of feed should be
consistent with the hazard analysis.
(viii) Use pneumatically-or
hydraulically-driven machine tools
whenever possible for machining
operations on HE. Install control
mechanisms for hydraulic and
pneumatic equipment to prevent
unauthorized personnel from tampering
with speeds.
(ix) In all machining operations on
cased or uncased HE, ensure tool
adjustments prevent contact between
moving parts of the machining
equipment and metallic parts of the case
or holding fixtures.
(x) Use machining tools compatible
with the HE being processed. Remove
dull or damaged tools from HE
machining operations.
(xi) Remove explosives products
resulting from machining operations
with an exhaust system meeting NFPA
Standard No. 70 requirements or by
immersion in a stream of water flowing
away from the operation.
(xii) Machine HE with unknown
physical or chemical characteristics, by
remote control with operators protected
by operational shields during AE
operations.
(i) Assembly and crimping of
complete rounds. Separate each
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
assembly and crimping operation from
other operations by structures or
shielding sufficient to contain any
fragments produced by an accidental
detonation.
(j) Pressing explosives. (1) Conduct
each pelleting operation involving black
powder, tetryl, TNT, or other explosives
of similar sensitivity and each operation
involving the pressing or
reconsolidation of explosives in a
separate room or cubicle having walls of
sufficient strength to withstand an
explosion of all explosives present.
(2) Perform pressing or
reconsolidating of explosives in small
caliber rounds, tracer bodies, tetryl leadins, detonators, and similar items on
machines having consolidating stations
designed to preclude propagation
between stations and provide adequate
operator protection. Ensure operators
stay behind tested protective barriers
during such operations.
(3) Only use punches and dies in
matched sets which have passed
inspection and are calibrated. Regularly
inspect and test by magnaflux, X-ray or
similar means, all punches and dies
used in explosives pressing operations.
(k) Protection of primers. Design
equipment, transportation, and
operations to protect loose primers or
primers in components from accidental
impact or pressure. When feasible, use
a protecting cap to cover the primer.
(l) Explosives washout and flashing
facilities. Separate washout operations
in operating buildings or other locations
from other operations by operational
shields or proper distances. Inspect AE
subjected to washout operations to
ensure against residual explosives
contamination. When contamination is
confirmed, decontaminate prior to
disposal.
(m) Heat-sealing equipment. Separate
electric heat-sealing machines from
other operations. Establish temperature
limits for heat-sealing equipment with a
safety factor below the ignition
temperature of the explosives,
propellants, or pyrotechnics involved.
(n) Rebowling operations. Perform
rebowling operations involving primary
explosives or primer mixes by remote
control, with the operator protected by
an operational shield.
(o) Thread cleaning. (1) Use
nonferrous picks for thread cleaning.
Stainless steel brushes are acceptable or
use to clean threads of explosivesloaded projectiles if a fuze seat liner
separates the thread cleaning operation
from the explosive charge. Operators
may use operational shields or quantity
distance separation to protect them from
unrelated operations.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(2) Power-actuated, thread-chasing
tools may be used to clean loaded
projectiles when threads are imperfect
because of previously applied sealers.
However, the operation must be
performed within a separate cubicle and
by remote control. Hand-operated
thread-chasing tools may be used when
no explosives are present in the threads.
(3) Do not cut threads or correct cross
threads on projectiles containing
explosives. Straightening crossed
threads is considered thread cutting.
(p) Profile and alignment gaging
operations. (1) Use operational shields
to enclose each profile and alignment
gauging operation, excluding small arms
ammunition, to protect adjacent
operations. Develop the layout of
equipment and operational procedures
to minimize personnel injury and
property damage in case of an accident.
(2) When chamber gauging large
caliber fixed ammunition, point the
gauge toward a dividing wall or other
barrier. Use the same operator to insert
and remove each round. Never leave a
round in the gauge. Gauge rounds of
mortar ammunition before attaching
propellant increments and, unless
prohibited by the design characteristics,
before assembly of the ignition system.
§ 184.14
Test and testing requirements.
(a) General. The contractor is
responsible for the safety of testing
programs. Test programs include any
and all tests, evaluations, quality
assurance functions tests, or similar
situations where AE response to
stimulus is the objective.
(b) Basic principles for test
operations. The following safety
precautions apply where pertinent:
(1) Conduct all test operations in
accordance with procedures developed
in accordance with § 184.3 (c) and
§ 184.6(i), using a hazard analysis as the
basis for the procedures.
(2) Wherever possible, substitute inert
materials for live AE. When only live
AE will meet test objectives, protect test
personnel. Use remote control of
operations, barricades, shields, remote
methods of shutting down the test
operation, or other appropriate methods
of eliminating exposure to personnel. By
definition, all tests involve some level of
uncertainty. Therefore test methods and
procedures must address all credible
malfunctions, or non-function potentials
and the appropriate reaction to them.
(3) Assembly and testing requirements
specific to each ammunition and
weapon system are contained in the
appropriate technical part and end-item
specifications which should be
incorporated into procedures. The
hazard analysis process should identify
PO 00000
Frm 00033
Fmt 4701
Sfmt 4702
16069
specific hazards of assembly and test. It
is particularly important to develop
procedures for the guidance of unique
tests (e.g., fuze function, fragmentation,
thermal effects, barricade test) which do
not duplicate assembly, disassembly, or
test requirements described in technical
parts or other government publications.
Include disposal procedures for
damaged energetic materials and
ordnance items. The following are
general assembly and testing safety
requirements.
(4) Do not allow test conditions to
compromise basic AE safety
considerations, for example,
compatibility of materials, quantity
control, quantity distance, exposure of
personnel to blast (including hazardous
noise levels), fragments and thermal
effects, bonding and grounding, and
personal protective equipment.
(5) Recognize and plan for the
mitigation of overpressure (including
sound), fumes, dust, fragments, thermal
effects and catastrophic failure of test
equipment or barricades which can
occur during or as the result of testing.
(6) Clearly identify expended
ordnance contaminated with residual
energetic or other hazardous materials.
Include decontamination steps in the
test operations procedure.
(7) Some testing, such as electrical
continuity, built-in-test, or weapon
functionality on components or all-uprounds will require remote operations.
Perform this testing with approved test
equipment at a facility site-approved for
the operation. When this is the case, the
following requirements apply:
(i) Do not expose any test personnel
to operations that have a high
probability of resulting in a detonation,
or to test operations that involve
intentional detonations. Protecting
personnel from all fragments and from
overpressures exceeding 2.3 psi
(overpressure at k24) meets that
requirement. Distance, operational
shields (see paragraph § 184.3(g) of this
part), or structural design of buildings
and bays involved, or a combination of
these, can provide this protection.
(ii) Protection by distance must
include consideration of fragments as
well as overpressure. For many test
operations involving relatively small
quantities of explosives, the distance at
which the blast over pressure drops to
the 2.3-psi level is less than the
minimum fragment distance. When this
occurs, the minimum distance between
the operation and any personnel is the
fragmentation distance. Use of
barricades, earth covered shelters, or
structural elements to control the
fragmentation hazard are acceptable
when it is possible to demonstrate this
E:\FR\FM\29MRP2.SGM
29MRP2
16070
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
protection by test or engineering design.
Tests normally require an overcharge of
25% NEW greater than the maximum
expected charge weight for testing,
when testing is the sole proof of
protection.
(iii) Provision of protection by
structural design, whether by itself or in
conjunction with distance, requires
specialized structural designs. Army TM
5–1300, Navy NAVFAC P–397, or Air
Force AFR 88–22 (different designations
for the same publication, provides
assistance for these designs. When using
this publication, Protection Category 1
is the level of design for personnel
protection. Designs based on lesser
levels of protection are acceptable,
depending upon the level of risk to
contract performance deemed
acceptable by the PCO when personnel
exposure is not an issue.
(iv) Spalling and other phenomena of
structural failure are part of the design
considerations when using the
referenced part for protection. Spalling
is the ejection of material from the back
face of a slab or beam as the result of
an explosion adjacent to the front face.
When not using the part for structural
designs, spalling protection must be part
of the design and test of structural
elements. When test cell walls do not
extend through the ceiling of the
structure, it is possible for overpressure
and debris from an explosion to escape
over the top of the cell and injure
personnel near the cells. Designs must
provide protection from such an
eventuality. Similarly, when cell walls
extend through ceilings and roofs, these
structural elements must be strong
enough to resist the effects of
overpressure and fragments, protecting
personnel below.
(v) Install interlocks to prevent
operator exposure to operations when
doors on any equipment or cells used
for explosives processing function as
operational shields. Do not install door
closure controls within cells. Design cell
door release devices to prevent
personnel from being stuck by a closing
door and to allow egress from the cell.
These may require designs to become
inoperative to prevent the overpressure
of an explosion from opening the door.
Ensure that any pass-throughs between
cells prevent the transmission of
fragments or damaging overpressures.
Typically, such pass-throughs have
doors interconnected so that only one
door can open at a time.
(vi) Establish a warning system of
flags, lights or sound signals during
testing operations. Provide personnel
who are not familiar with the warning
system in test areas, and equipped test
areas with a telephone and/or radio to
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
permit communication during testing
operations.
§ 184.15 Collection and destruction
requirements for AE.
(a) General. This section provides
safety requirements for the collection
and destruction of AE. It contains more
detailed information than other portions
of this part due to the higher risks of
these operations. The Environmental
Protection Agency (EPA) has developed
regulations which apply to contractors
and may impose requirements beyond
those in this part. Contractors shall
avoid compromising explosive safety for
environmental considerations.
(b) Protection during disposal
operations. (1) Operational shields or
special clothing shall protect personnel
during disposal operations.
Fragmentation hazards require, at a
minimum, overhead and frontal
protection for personnel. Contractors
detonating AE may locate personnel
shelters at the appropriate IBD for the
AE NEW. Personnel shall use protective
structures when destroying AE by
detonation and when burning AE that
may detonate. Personnel shall not
approach the burning site, but shall
observe an appropriate waiting period
after the fire is out.
(2) Personnel shall never work alone
during disposal and destruction
operations. Warning signs or lights,
roadblocks, or other effective means
shall restrict the area. One person,
available in an emergency, should
observe from a safe distance while
another performs the operations.
(c) Collection of AE. (1) Water-soluble
materials. Use sufficient water to
neutralize ammonium picrate
(Explosive D), black powder, and other
soluble materials to ensure their
complete dissolution. Dissolve as little
material as practicable at one time.
Sweeping floors before washing them
down reduces the amount of dissolved
material in the wash water. Consult
experts when uncertainty exists
concerning the purity and composition
of wash water.
(2) Solid wastes. Collect explosivescontaminated solid waste material,
place in closed containers, and
promptly deliver to buildings for
treatment or holding, or to the burning
ground for destruction.
(3) Explosives dusts. (i) The contractor
may use a vacuum system to remove HE
dusts such as TNT, tetryl, Explosive D,
Composition B, and Pentolite. The
preferred removal method for explosives
is a ‘‘wet collector’’ which moistens the
dust near the point of intake and keeps
it wet until disposal. Collect Explosive
D in a dry system.
PO 00000
Frm 00034
Fmt 4701
Sfmt 4702
(ii) The contractor may collect more
sensitive explosives such as black
powder, lead azide, lead styphnate,
tracer, igniter, incendiary compositions,
and pyrotechnic materials by vacuum,
provided they are kept wet close to the
point of intake. Collect each type
representing a different hazard
separately so that black powder, for
example, cannot mix with lead azide.
The vacuum system should release any
build up of gases. Confine the use of
vacuum systems for collection of
sensitive explosive substances to
operations involving small quantities of
explosives, that is, operations with
fuzes, detonators, small-arms
ammunition, and black powder igniters.
To minimize the fire and explosion
hazard, collect scrap pyrotechnic, tracer,
flare, and similar mixtures in No. 10
mineral oil or equivalent. Collect dry
explosive dust in an oil-filled receptacle
available at each operation throughout
the shift. The oil level shall maintained
at least 1 inch above the level of any
pyrotechnic mixture in the container.
Some pyrotechnic compositions float on
oil. If it occurs use a wooden plunger to
submerge the material. Remove
containers of scrap explosive for
disposal from the operating buildings at
least once per shift. When using oil, use
the appropriate rated Class B firefighting
equipment.
(d) Design and operation of collection
systems. (1) Design collection systems
and chambers to prevent pinching thin
layers of explosives or explosives dust
between metal parts. Pipes or ducts
used to convey dusts require flanged,
welded, or rubber connections. The
contractor shall not use threaded
connections. The system shall prevent
explosive dusts from accumulating in
parts outside the collection chamber.
Pipes or ducts conveying high
explosives shall have long radius bends.
Systems for propellant powder may use
short radius bends, provided they are
stainless steel, with polished interiors.
Minimize the number of vacuum
application points. Use wet primary
collectors when possible. The design of
the vacuum collection system should
provide a separate exhaust line to the
primary collection chamber from each
room. If this is not possible, a common
header shall service no more than two
bays. Keep short lengths of vacuum
lines from the application points to the
wet collectors. A single secondary
collector shall service as few primary
collectors as possible. The contractor
shall connect not more than two dry
primary collectors to a single secondary
collector (wet or dry type). Vacuum
systems that are permanently attached
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
to the explosive dust-producing
machine may increase the likelihood of
detonation propagation through the
collection system. Recommend using
partly operated vacuum systems unless
dust concentrations pose an explosion
or health hazard. Partly operated hose
connections to explosive dustproducing machines should not
interconnect.
(2) Install two collection chambers in
series ahead of the pump or exhauster
to prevent explosives dust from entering
the vacuum producer in a dry vacuum
collection system.
(3) There shall be no metal-to-metal
contact on slide valves for vacuum
collection systems. An aluminum slide
operating between two ebonite spacer
bars or similar compatible materials will
eliminate unacceptable metal-to-metal
contact.
(4) Install dry-type portable vacuum
collectors, limited to 5 lbs (2.3 kg) of
explosives, in a separate cubicle having
substantial dividing walls, or outside
the building. Never install type of
collector in the bay or cubicle with the
explosives. The contractor may use wettype portable vacuum collectors in
explosives operating bays or cubicles,
provided limited quantities of
explosives in the collector meet the
requirements of paragraphs (e)(1)
through (e)(3) of this section. For dry
collection over 5 lbs (2.3 kg) or wet
collection over 8 lbs (3.64 kg) of
explosives, the provisions of paragraphs
(e)(1) through (e)(3) of this section also
apply.
(5) The design of wet collectors shall
provide for:
(i) Proper immersion of explosives.
(ii) Breaking up of air bubbles to
prevent release of airborne particles,
and
(iii) Prevent moistened particles of
explosives from entering the small
piping between the collector and the
exhauster or pump
(6) At least once every shift, remove
the explosives dust from the collection
chamber to eliminate unnecessary and
hazardous concentrations of explosives.
Clean entire system on a regular basis to
remove residual contamination, with
parts dismantled as necessary.
(7) Electrically bond the entire
explosives dust collection system to the
grounding system. Test the electrical
bonding/grounding system in
accordance with § 184.6(f)(5).
(8) Shield personnel workstations
from vacuum systems.
(e) Location of collection chambers.
(1) Whenever practicable, locate drytype explosives dust collection
chambers, except portable units, in the
open, outside operating buildings, or in
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
buildings set-aside for that purpose.
Provide a barricade or operational
shield appropriate for the NEW
involved to protect operating personnel
from blast (2.3 psi) and fragments from
the collection chamber. At least 3 ft (1
m) should separate the collection
chamber from the barricade or
operational shield.
(2) When locating dry-type collection
chambers outside the operating building
is not feasible, set aside a separate room
for this purpose in the building. The
contractor shall not allow personnel to
work or pass through the dry-type
collection chamber room. Walls
separating the room from other portions
of the operating building shall meet the
requirements for operational shields for
the NEW in the collection chamber.
Subdivide rooms with multiple
collection chambers into cubicles with
only one collection chamber per
cubicle.
(3) Stationary and portable wet-type
collectors in operating bays or cubicles
shall not exceed 5 lbs (2.3 kg) NEW.
When placed in separate cubicles,
quantities may increase to 8 lbs (3.64
kg). See paragraphs (e)(1) and (e)(2) of
this section for location requirements of
wet collectors, containing more than 8
lbs (3.64 kg),
(f) AE awaiting destruction. Maintain
IBD from AE destruction sites and
explosives stored in the open. If
adequately protected from frontal and
overhead hazards, ILD separation
between AE material awaiting
destruction and AE destruction sites is
acceptable. Protect all AE awaiting
destruction from accidental ignition or
explosion from fragments, grass fires,
burning embers, or blast originating
from the destruction site.
(g) Containers for waste explosives.
Use appropriate containers for AE waste
to prevent leakage and spillage of
contents. The contractor shall not pinch
or rub explosives during container
closing and opening. Clearly mark
containers to identify contents. Do not
use containers constructed of sparkproducing or easily ignited material.
(h) Destruction sites. (1) Site criteria.
(i) Locate AE destruction sites as far as
possible from magazines, inhabited
buildings, public highways, runways,
taxiways, and operating buildings. The
minimum separation distance is 1,250 ft
(381 m) or the applicable fragmentation
distance, unless pits or similar aids (e.g.,
natural barricades) limit the range of
fragments. Since burning explosives
may detonate, contractor shall use
appropriate protective barriers or
separation distances for the safety of
personnel and property. To prevent
secondary fragments, do not burn or
PO 00000
Frm 00035
Fmt 4701
Sfmt 4702
16071
detonate AE on concrete, or in areas
having large stones or crevices.
(ii) For separation distances less than
1250 ft (381 m), use DoD approved
documentation to determine fragment
and debris throw in calculating the
appropriate IBD based on the maximum
NEW of AE present.
(iii) Recommend keeping firefighting
equipment available to extinguish grass
fires and to wet down the area between
burnings and at the close of operations.
(iv) The contractor should not dispose
of ordinary combustible rubbish near
AE and AE-contaminated material
destruction sites.
(2) Materials and equipment for
detonating explosives. (i) Contractor
should initiate detonations of AE with
electric blasting caps and blasting
machines or permanently installed
electric circuits energized by storage
batteries or conventional power lines.
When covering AE for disposal with
earth, do not bury the blasting cap.
Prime the initiating explosives with
sufficient primacord to allow
connecting the blasting cap above
ground level.
(ii) Special requirements for using
electric blasting caps and electric
blasting circuits follow.
(A) Never hold a blasting cap at the
explosive (output) end. Hold the wire
lead end of the cap between the thumb
and the index finger. Whenever
possible, point the explosive end of a
hand-held cap down, away from the
body, and to the rear.
(B) Do not remove the shunt from the
lead wires of the blasting cap until
ready to connect them to the blasting
circuit, except during electrical
continuity test of the blasting cap and
lead wires.
(C) Carefully hold the lead wires so
that there is no tension where they
connect to the cap and partly straighten
the lead wires. Do not throw, wave
through the air, or uncoil by snapping
as a whip.
(D) Use blasting circuit wires in
twisted pairs. Operators shall keep
blasting circuit wires twisted together
and connected to ground at the power
source and twisted at the opposite end
at all times except when actually firing
the charge or testing circuit for
continuity and extraneous electricity.
Never connect the blasting cap to the
blasting circuit wires unless the blasting
circuit wires are shorted and grounded
at the ends near the power source.
(E) Maintain safe distances between
radio frequency (RF) energy transmitters
and electric blasting, demolition
operations, and unshielded electric
blasting caps.
E:\FR\FM\29MRP2.SGM
29MRP2
16072
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(F) Transport blasting caps in closed
metal boxes wherever exposure to RF
energy and extraneous electricity is
possible (i.e., vehicles equipped with
two-way radios).
(G) Operators should follow these
procedures when connecting electric
blasting cap lead wires to the blasting
circuit wires.
(1) Test the blasting circuit wires for
electrical continuity.
(2) Test the blasting circuit for
extraneous electricity. To test, arrange a
dummy test circuit similar to the actual
blasting circuit, except substitute a radio
pilot lamp of suitable voltage for the
blasting cap. If the pilot lamp glows,
indicating potentially dangerous
amounts of RF energy, stop blasting
operations using electric blasting caps.
Blasting operations may resume using
non-electric blasting caps and safety
fuse. The contractor may substitute
other test instruments (e.g. the DuPont
‘‘Dectect-A-Meter’’ or ‘‘Voltohmeter,’’)
for the radio pilot lamp. If the potential
source of extraneous electricity is radar,
television, or microwave transmitters,
test the actual blasting circuit, including
the blasting cap but without other
explosives, for extraneous electricity.
Protect personnel performing such tests
from the effects of an exploding blasting
cap.
(3) Test the blasting cap and its lead
wires for electrical continuity. The
individual who removes the shunt
should ground himself or herself by
grasping the blasting circuit wire prior
to performing the operation in order to
prevent accumulated static electricity
from firing the blasting cap.
(4) Assure the blasting circuit wires
are shorted and grounded at the power
source and connect the blasting cap lead
wires to the blasting circuit wires.
(5) Evacuate all but two persons from
the area. One person shall partially
retreat and act as safety observer. The
other person shall maintain physical
possession of a safety device that locks
out the blasting circuit (e.g., plug, key,
pigtail, etc.) and shall place blasting cap
onto charge. Both persons will then
retreat to personnel shelter.
(6) Untwist blasting circuit wires at
power source and test for continuity. A
galvanometer shall be used to test the
firing circuit for electric continuity
before connection to the blasting
machine.
(7) The individual assigned to make
the connections shall confirm that
everyone in the vicinity is in a safe
place before connecting the blasting
circuit wires to the power source and
signaling for detonation. This individual
shall not leave the blasting machine or
its actuating device for any reason and
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
when using a panel, shall lock the
switch in the open position until ready
to fire, retaining the only key. Connect
blasting circuit wires to power source
and fire the charge.
(8) After firing, disconnect blasting
circuit wires from power source, twist
the wires together, and connect to
ground.
(9) Suspend blasting and demolition
operations when electrical storms are in
the vicinity. At the first sign of an
electrical storm, short-circuit the
blasting cap lead wires and the blasting
circuit wires, and evacuate all personnel
from the demolition area to a safe
location.
(H) Use non-electric blasting caps and
safety fuses when conditions prevent
the use of electrical initiators for
detonation. At the beginning of each
day’s operation and whenever using a
new coil, test the safety fuse’s burning
rate. The fuse shall be long enough for
personnel to evacuate to a safe distance.
Under no circumstances shall the fuse
length be less than that required for a 2minute burn time. Use appropriately
designed crimpers to affix fuses to
detonators. Use only fuses small enough
in diameter to enter the blasting cap
without forcing. All personnel, except
the fuse-actuator, shall move to the
personnel shelter or leave the
demolition area before ignition.
(3) Servicing of destruction site. (i)
Vehicles transporting AE to burning or
demolition grounds shall meet the
requirements of this part. No more than
two persons shall ride in the cab. No
one shall ride in the truck bed.
(ii) The contractor should unload
vehicles immediately then move the
vehicle from the burning or demolition
area until completion of destruction
operations. The contractor should not
open AE containers before the vehicle
departs.
(iii) The contractor shall place and
open all AE containers set for
destruction at least 10 ft (3.1 m) from
each other and from explosives material
previously set out to prevent rapid
transmission of fire if premature
ignition occurs.
(iv) Close and move empty containers
to prevent charring or damage during
destruction of AE. Delivery vehicles
shall pick up and remove empty
containers on the next trip.
(i) Destruction by burning. (1) No
mixing of an explosive with extraneous
material, other explosives, metal
powders, detonators, or similar items
shall occur without authorization.
(2) Because of the danger of
detonation, do not burn AE in large
quantities or in containers.
PO 00000
Frm 00036
Fmt 4701
Sfmt 4702
(3) Beds for burning explosives. (i) A
bed of easily combustible material at
least two inches thick should be
positioned under the explosive bed to
ensure complete consumption of wet
explosives. The combustible material
should extend at least two inches
beyond the edges of the explosive bed.
If necessary, the thickness and extent of
the combustible material may be
adjusted, based on actual experience at
the site.
(ii) The explosive bed shall be no
more than 3 in (76 mm) deep.
(iii) The ignition train of combustible
material leading to the explosives bed
shall be positioned so that both it and
the explosive bed can burn in a
controlled fashion and not propagate to
any other explosive treatment areas.
(iv) No burning shall take place when
wind velocity exceeds 15 mph (24 km/
h).
(v) For direct ignition of a
combustible train, use either a safety
fuse long enough to permit personnel to
reach protective shelter or a black
powder squib initiated by an electric
current controlled from a distance or
protective structure. Tying two or more
squibs together may be necessary to
ensure ignition of the combustible train.
(vi) Burning solid propellants ignited
by squibs do not require combustible
materials.
(vii) Evacuate sites of misfires for at
least 30 minutes, after which two
qualified persons shall approach the
position of the explosives. One shall
examine the misfire and the other shall
act as backup. The backup shall watch
the examination from a safe distance,
behind natural or artificial barriers or
other obstructions for protection. The
backup shall follow contractor
procedures should an accident occur.
(4) Burn loose, dry explosives without
combustible material, if the ground can
remain uncontaminated. Check the
ground for residual unburned explosive
for the safety of personnel and
operations. Do not pour volatile
flammable liquids, at any stage, over
explosives or the underlying
combustible material to accelerate
burning.
(5) Always burn wet explosives on
beds of non-explosive materials.
(6) Burn explosive powders (e.g.,
RDX, HMX, etc.) in desensitized form to
promote safe handling and prevent
detonation.
(7) Empty oil-covered pyrotechnic
materials from containers into shallow
metal pans before burning. The
contractor may burn explosives in the
open containers.
(8) Prepare separate parallel beds of
explosives for burning by not less than
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
150 ft (46 m). Take care to prevent
material igniting from smoldering
residue or from heat retained in the
ground from previous burning
operations. Saturate a burned-over plot
with water, then check for hot spots, or
allow 24 hours to elapse before the next
burn.
(j) Destruction by detonation. (1)
Detonation of AE should occur in a pit
of at least 4 ft (1.3 m) deep and be
covered by at least of 2 ft (0.6 m) of
earth. Place the components on their
sides or in a fashion to enhance
complete destruction. Place demolition
blocks on top of the AE and secure them
with earth packed over them. Under
certain circumstances, the contractor
may substitute bangalore torpedoes or
bulk HE for the demolition blocks.
(Note: Detonations do not require a pit
at remote demolition areas.)
(2) Local regulations, atmospheric
conditions, earth strata, etc. shall dictate
quantities destroyed at one time, both in
pits and open sites. Considering these
variables, determine the acceptable
NEW based on criteria in Chapter 9,
DoD 6055.9–STD. The contractor should
use this procedure for destruction of
fragmentation grenades, HE projectiles,
mines, mortar shells, bombs, photoflash
munitions, and HE rocket heads
separated from their motors.
(3) Search the surrounding area for
unexploded AE after each detonation.
(4) In cases of misfires, follow
established procedures. Wait a
minimum of 30 minutes before
approaching the site.
(k) Destruction by neutralization.
Methods of neutralization include
dissolving in water-soluble material or
chemical decomposition. The contractor
is responsible for investigating which of
these is most appropriate. The
contractor shall comply with all
applicable local, state, and Federal
requirements.
(l) Destruction chambers and
incinerators. (1) General. The contractor
should destroy small, loaded AE
components (e.g., primers, fuzes,
boosters, detonators, activators, relays,
delays, and all types of small-arms
ammunition) in destruction chambers or
deactivation furnaces. The contractor
should use explosives scrap incinerators
for burning tracer and igniter
compositions, small quantities of solid
propellant, magnesium powder, sump
cleanings, absorbent cleaning materials,
and similar materials. The contractor
should equip destruction chambers and
incinerators with suitable pollution
control devices (e.g., multiple chamber
incinerators with thermal incinerator
afterburners) and concrete barricades.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
The final incineration should take place
at 1400 °F (760 °C), minimum.
(2) Operation of incinerators. (i) The
contractor shall not operate the feeding
conveyor until the incinerator
temperature is high enough to ensure
complete destruction. The contractor
should install temperature recording
devices.
(ii) To remove accumulated residue,
shut down and thoroughly cool the
incinerators. Make repairs only during
shutdown. Personnel entering the
incinerator to clean it shall wear
respiratory protection to prevent
inhalation of toxic dusts or fumes (e.g.,
mercury from tracers or lead from smallarms ammunition).
(3) Operation of destruction chambers
and deactivation furnaces. (i) Operation
of destruction chambers and
deactivation furnaces requires remote
control.
(ii) Operators shall not approach the
unprotected side of the concrete
barricade, for any other reason, until
enough time has elapsed for explosives
in the chamber to react. Perform regular
inspections to keep the feed-pipe chute
or conveyor obstruction free.
(iii) Feed components into the
chamber a few at a time. Post the exact
number permitted at one time for each
type of component in a place easily seen
from the operator’s working position.
(iv) Install guards on conveyorfeeding mechanisms to facilitate feeding
and to prevent items from jamming or
falling.
(m) Support in disposal of waste. The
contractor shall request instructions
from the responsible ACO if, at end of
contract, there is excess or residual
Government-owned AE and the contract
does not address disposition. A
contractor having difficulty safely
disposing of residual (scrap) AE related
to contractual operations may request
help from the ACO.
§ 184.16
Construction and siting criteria.
Please refer to DoD 6055.9, Chapter 5
for guidance on facilities construction
and siting.
Appendix A to 32 CFR Part 184—
Glossary
This appendix defines terms and phrases
used in this part, which are associated with
ammunition, explosives, and other dangerous
materials. For those terms that are not found
in this glossary please refer to DoD 6055.9–
STD for Q–D terminology. Because of
contractual reasons some terms of this part
may be define differently.
(a) Aboveground magazine. Any open area
or any structure not meeting the
requirements of an ECM which is used for
explosives storage.
(b) Administration area. The area
encompassing administrative buildings
PO 00000
Frm 00037
Fmt 4701
Sfmt 4700
16073
which serve the entire installation. This
excludes offices located near and directly
serving explosives storage and operating
areas.
(c) Aircraft passenger transport operations.
Passenger transport operations for the
purpose of applying explosives Q–D tables
are defined as follows: Passenger transport
traffic involving military dependents and
civilians other than those employed or
working directly for DoD Components. The
following are not considered passenger
transport operations.
(1) Infrequent flights of base and command
administrative aircraft that may on occasion,
provide some space available travel to
authorized personnel.
(2) Travel of direct hire appropriated funds
personnel employed by any DoD Component.
(d) Ammunition and explosives. Includes
(but is not necessarily limited to) all items of
U.S.-titled (owned by the U.S. Government
through DoD Components) ammunition:
propellants, liquid and solid. pyrotechnics.
high explosives. guided missiles. warheads.
devices. devices, and chemical agent
substances and components presenting real
or potential hazards to life, property and the
environment. Excluded are wholly inert
items and nuclear warheads and devices,
except for considerations of storage and
stowage compatibility, blast, fire, and nonnuclear fragment hazards associated with the
explosives.
(e) Ammunition and explosives aircraft
cargo area. Any area specifically designated
for:
(1) Aircraft loading or unloading of
transportation configured ammunition and
explosives.
(2) Parking aircraft loaded with
transportation configured ammunition and
explosives.
(f) Ammunition and explosives area. An
area specifically designated and set aside
from other portions of an installation for the
development, manufacture, testing,
maintenance, storage or handling of
ammunition and explosives.
(g) Auxiliary building. Any building
accessory to or maintained and operated to
serve an operating building line, plant, or
pier area. Explosive materials are not present
in an auxiliary building, such as
powerplants, change houses, paint and
solvent lockers, and similar facilities.
(h) Barricade. An intervening barrier,
natural or artificial, of such type, size, and
construction as to limit in a prescribed
manner the effect of an explosion on nearby
buildings or exposures.
(i) Blast impulse. The product of the
overpressure from the blast wave of an
explosion and the time during which it acts
at a given point (that is, the area under the
positive phase of the overpressure-time
curve).
(j) Blast overpressure. The pressure,
exceeding the ambient pressure, manifested
in the shock wave of an explosion.
(k) Cavern storage site. A natural cavern or
former mining excavation adapted for the
storage of ammunition and explosives.
(l) Chamber storage site. An excavated
chamber or series or excavated chambers
especially suited to the storage of
E:\FR\FM\29MRP2.SGM
29MRP2
16074
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
ammunition and explosives. A cavern may be
subdivided or otherwise structurally
modified for use as a chamber storage site.
(m) Change house. A building provide with
facilities for employees to change to and from
work clothes. Such buildings may be
provided with sanitary facilities, drinking
fountains, lockers and eating facilities.
(n) Classification yard. A railroad yard
used for receiving, dispatching, classifying,
and switching of cars.
(o) Closure block. A protective constructive
feature designed to seal the entrance tunnel
to an underground storage chamber in the
event of an explosion within the chamber.
Magae blocks are passive closures that are
driven by the blast from a normally open to
a closed position. Klotz blocks area active
closures, operated by a hydraulic system to
move from normally closed to an open
position (for access).
(p) Compatibility. Ammunition or
explosives which may be stored or
transported together without significantly
increasing either the probability of an
accident or, for a given quantity, the
magnitude of the effects of such as accident.
(q) Debris. Any solid particle thrown by an
explosion or other strong energetic reaction.
For aboveground detonations, debris usually
refers to secondary fragments, which are
transported by a strong flow of detonation
gasses.
(r) Debris trap. A protective construction
feature in an underground storage facility
which is designed to capture fragments and
debris from a detonation within the facility.
This usually accomplished by using the
inertia of the material to separate from the
detonation gas stream.
(s) Deflagration. A rapid chemical reaction
in which the output of heat is enough to
enable the reaction to proceed and be
accelerated without input of heat from
another source. Deflagration is a surface
phenomenon with the reaction products
flowing away from the unreacted material
along the surface at subsonic velocity. The
effect of a true deflagration under
confinement is an explosion. Confinement of
the reaction increases pressure, rate of
reaction and temperature, and may cause
transition into a detonation.
(t) Demilitarize. Any disarming,
neutralizing, and any other action rendering
ammunition and explosives innocuous or
ineffectual for military use.
(u) Detonation. A violent chemical reaction
with a chemical compound or mechanical
mixture evolving heat and pressure. A
detonation which proceeds through the
reacted material toward the unreacted
material at a supersonic velocity. The result
of the chemical reaction is exertion of
extremely high pressure on the surrounding
medium forming a propagating shock wave
which is initially of supersonic velocity. A
detonation, when the material is located on
or near the surface of the found, is
characterized normally by a crater.
(v) Dividing wall. A wall designed to
prevent, control, or delay propagation of an
explosion between quantities of explosives
on opposite sides of the wall.
(w) DoD mishap. An unplanned event or
series of events which results in damage to
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
DoD property, occupational illness to DoD
military or civilian personnel, injury to DoD
military personnel on or off duty, injury to
on-duty civilian personnel, damage to public
and private property, or injury and illness to
non-DoD personnel as a result of DoD
operations.
(x) Donor/Acceptor. A total quantity of
stored ammunition may be subdivided into
separate storage units in order to reduce the
MCE, and, consequently, the Q–D of an
accidental detonation. The separation
distances, with or without an intervening
barrier, should be sufficient to ensure that a
detonation does not propagate from one unit
to another. For convenience, the storage unit,
which detonates, is termed the donor and
nearby units, which may be endangered, are
termed acceptors. The locations of the donor
and acceptor define the PES and ES,
respectively.
(y) Earth-Covered Magazine (ECM). Any
earth-covered structure that meets soil cover
depth and soil requirements of DoD 6055.9–
STD. ECM has three possible structural
strength designations (‘‘7-Bar’’, ‘‘3-Bar’’, or
‘‘Undefined’’). The strength of an ECM’s
headwall and door(s) determines its
designation.
(z) Energetic liquid. A liquid, slurry, or gel,
consisting of or containing an explosive,
oxidizer, fuel, or combination of the above,
may undergo, contribute to, or cause rapid
exothermic decomposition, deflagration, or
detonation.
(aa) Engineering controls. Regulation of
facility operations through the use of prudent
engineering principles, such as facility
design, operation sequencing, equipment
selection, and process limitations.
(bb) Expansion chambers. A protective
construction feature in an underground
storage facility which is designed to reduce
the blast shock and overpressure exiting the
facility by increasing the total volume of the
complex. It may also function as a operating
area within the underground facility, as well
as a debris trap.
(cc) Explosion. A reaction of any chemical
compound or mechanical mixture, which,
when initiated, undergoes a very rapid
combustion or decomposition releasing large
volumes of highly heated gases that exert
pressure on the surrounding medium. In
addition, a mechanical reaction in which
failure of the container causes the sudden
release of pressure from within a pressure
vessel, for example, pressure rupture of a
steam boiler. Depending on the rate of energy
release, an explosion can be categorized as a
deflagration, a detonation, or pressure
rupture.
(dd) Explosive. Any chemical compound or
mechanical mixture that, when subjected to
heat, impact, friction, detonation, or other
suitable initiation, undergoes a very rapid
chemical change with the evolution of large
volumes of highly heated gases which exert
pressures in the surrounding medium. The
term applies to materials which either
detonate or deflagrate.
(ee) Explosives facility. Any structure or
location containing ammunition and
explosives excluding combat aircraft parking
areas or ammunition and explosives aircraft
cargo areas.
PO 00000
Frm 00038
Fmt 4701
Sfmt 4700
(ff) Exposed Site (ES). A location exposed
to the potential hazardous effects (blast,
fragments, debris, and heat flux) from an
explosion at a potential site (PES). The
distance to a PES and the level of protection
required for an ES determine the quantity of
ammunition or explosives permitted in a
PES.
(gg) Firebrand. A projected burning or hot
fragment whose thermal energy is transferred
to a receptor.
(hh) Fire-resistive. Combustible materials
or structures that have been treated or have
surface coverings designed to retard ignition
of fire spread.
(ii) Flame-resistant. Combustible materials,
such as clothing, which have been treated or
coated to decrease their burning
characteristics.
(jj) Flammable. A material which ignites
easily and burns readily.
(kk) Fragmentation. The breaking up of the
confining material of a chemical compound
or mechanical mixture when an explosion
takes place. Fragments may be complete
items, subassemblies, pieces thereof, or
pieces of equipment or buildings containing
items.
(ll) General public. Persons not associated
with the DoD installation’s mission or
operations such as visitors, to include guests
of personnel assigned to the installation, or
persons not employed or contracted by DoD
or the installation.
(mm) Hazardous fragment. A hazardous
fragment is one having an impact energy of
58 ft-lb or greater.
(nn) Hazardous fragment density. A
density of hazardous fragments exceeding
one per 600 sq ft.
(oo) High explosive equivalent or explosive
equivalent. The amount of a standard
explosive that, when detonated, will produce
a blast effect comparable to that which
results at the same distances from the
detonation or explosion of a given amount of
the material or which performance is being
evaluated. It usually is expressed as a
percentage of the total net weight of all
reactive materials contained in the item or
systems. For the purpose of these standards,
TNT is used for comparison.
(pp) Hazard analysis. The logical,
systematic examination of an item, process,
condition, facility, or system to identify and
analyze the probability, causes, and
consequences of potential or real hazards.
(qq) Holding yard. A location for groups of
railcars, trucks, or trailers used to hold
ammunition, explosives, and dangerous
materials for interim periods before storage or
shipment.
(rr) Hybrid propellants. A propellant
charge using a combination of physically
separated solid and liquid (or jelled)
substances as fuel and oxidizer.
(ss) Hygroscopic. A tendency of material to
absorb moisture from its surroundings.
(tt) Hypergolic. A property of various
combinations of chemical to self-ignite upon
contact with each other without a spark or
other external initiation.
(uu) Inhabited buildings. Buildings or
structures, other than operating buildings
occupied in whole or in part by human
beings, both within and outside DoD
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
establishments. They include but are not
limited to schools, churches, residences
(quarters), service clubs, aircraft passenger
terminals, stores, shops, factories, hospitals,
theaters, mess halls, post offices, and post
exchanges.
(vv) Inspection station. A designated
location at which trucks and railcars
containing ammunition and explosives are
inspected.
(ww) Installation related personnel.
Military personnel (to include family
members), DoD employees, DoD contractor
personnel, and other personnel having either
a direct operational (military or other Federal
personnel undergoing training at an
installation) or logistical support (e.g.,
vendors) relationship with installation
activities.
(xx) Interchange yard. An area set aside for
the exchange of railroad cars or vehicles
between the common carrier and DoD
activities.
(yy) Intraline distance. The distance to be
maintained between any two operating
buildings and sites within an operating line,
of which at least one contains or is designed
to contain explosives, except that the
distance from a service magazine for the line
to the nearest operating building may be not
be less than the intraline distance required
for the quantity of explosives contained in
the service magazine.
(zz) K-Factor. The factor in the formula D
= kW1⁄3 used in quantity-distance
determinations where D represents distance
in feet and W is the net explosive weight in
pounds. The K-factor is a constant and
represents the degree of damage that is
acceptable. Typical constants range from 1.25
to 50. the lower the factor, the greater the
damage that is accepted.
(aaa) Launch pads. The load-bearing base,
apron, or platform upon which a rocket,
missile, or space vehicle and its launcher rest
during launching.
(bbb) Liquid propellants. Substances in
fluid form (including cryogenics) used for
propulsion for operating power for missiles,
rockets, ammunition and other related
devices (See DoD 6055.9–STD. For purposes
of this part, liquid fuels and oxidizers are
considered propellants even when stored and
handled separately.
(ccc) Loading density. Quantity of
explosive per unit volume usually expressed
as either pounds per cubic foot (lbs/ft3). As
applied to underground storage facilities,
there are two types of loading densities used
in Q–D calculations:
(1) Chamber loading density is based on
the NEW within an individual storage
chamber and the volume of the chamber
(Vch).
(2) The calculations of air blast peak
pressures and IBD’s for explosions in
underground storage facilities is based on the
shock-engulfed volume (Ve) of the facility.
This is the total volume filled by the
expanding gases at the time the blast front
reaches the point of interest (e.g., the
entrance to an adjacent chamber). It includes
volumes in any direction that the gases can
enter, to a distance from the explosion source
that equals the distance from the source to
the point of interest. For IBD, the point of
interest is the tunnel opening.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(ddd) Loading docks. Facilities, structures,
or paved areas, designed and installed for
transferring ammunition and explosives
between any two modes of transportation.
(eee) Lunchrooms. Facilities where food is
prepared or brought for distribution by food
service personnel. It may serve more than
one PES. A breakroom in an operating
building may be used by personnel assigned
to the PES to eat meals.
(fff) Magazine. Any building or structure,
except an operating building, used for the
storage of ammunition and explosives.
(ggg) Mass-detonating explosives. HE,
black powder, certain propellants, certain
pyrotechnics, and other similar explosives,
alone or in combination, or loaded into
various types of ammunition or containers,
most of the entire quantity of which can be
expected to explode virtually instantaneously
when a small portion is subjected to fire, to
severe concussion or impact, to the impulse
of an initiating agent, or to the effect of a
considerable discharge of energy from
without. Such an explosion normally will
cause severe structural damage to adjacent
objects. Explosion propagation may occur
immediately to other items of ammunition
and explosives stored sufficiently close to
and not adequately protected from the
initially exploding pile with a time interval
short enough so that two or more quantities
must be considered as one for Q–D purposes.
(hhh) Maximum Credible Event (MCE). In
hazards evaluation, the MCE from a
hypothesized accidental explosion, fire, or
agent release is the worst single event that is
likely to occur from a quantity and
disposition of ammunition and explosives.
The event must be realistic with a reasonable
probability of occurrence considering the
explosion propagation, burning rate
characteristics, and physical protection given
to the involved. The MCE evaluated on this
basis may then be used as a basis for effects
calculations and casualty predictions.
(iii) Module. A barricaded area comprised
of a series of connected cells with hard
surface storage pads separated from each
other by barricades.
(jjj) Military munitions. All ammunition
products and components produced or used
by for the U.S. Department of Defense or the
U.S. Armed Services for national defense and
security, including military munitions under
the control of the Department of Defense, the
U.S. Coast Guard, the U.S. Department of
Energy, and the National Guard personnel.
The term ‘‘military munitions’’ includes
confined gaseous, liquid, and solid
propellants, explosives, pyrotechnics,
chemical and riot control agents, smokes,
incendiaries used by the DoD Components,
including bulk explosives and chemical
warfare, mortar rounds, artillery ammunition,
small arms ammunition, grenades, mines,
torpedoes, depth charges, cluster munitions
and dispensers, demolition charges, and
devices and components thereof. ‘‘Military
munitions’’ do not include wholly inert
items, improvised explosive devices, and
nuclear weapons, nuclear devices, and
nuclear components thereof. However, that
term does include non-nuclear components
of nuclear devices, managed under the DoE’s
nuclear weapons program, after all required
PO 00000
Frm 00039
Fmt 4701
Sfmt 4700
16075
sanitizing operations under the ‘‘Atomic
Energy Act of 1954,’’ as amended, have been
completed (40 CFR 260.10).
(kkk) Navigable streams. Those parts of
streams, channels, or canals capable of being
used in their ordinary or maintained
condition as highways of commerce over
which trade and travel are or may be
conducted in the customary modes, not
including streams that are not capable of
navigation by barges, tugboats, and other
large vessels unless they are used extensively
and regularly for the operation of pleasure
boats.
(lll) NEQ. Net explosive quantity expressed
in kilograms.
(mmm) NEW. Net explosive weight
expressed in pounds.
(nnn) Nitrogen padding (or Blanket). Used
to fill the void or ullage of a closed container
with nitrogen gas to prevent oxidation of the
chemical contained therein and to avoid
formation of a flammable mixture, or to
maintain a nitrogen atmosphere in or around
an operation of a piece of equipment.
(ooo) Non-combustible. Not burnable.
(ppp) Non-DoD Components. Any entity
(government, private, or corporate) that is not
a part of the Department of Defense.
(qqq) Operating building. Any structure,
except a magazine, in which operations
pertaining to manufacturing, processing,
handling, loading, or assembling of
ammunition and explosives are performed.
(rrr) Operating line. A group of buildings,
facilities or related work stations so arranged
as to permit performance of the consecutive
steps in the manufacture of an explosive, or
in the loading, assembly, modification, and
maintenance of ammunition. Parallel
operating lines are adjacent buildings or
other facilities that process the same or
comparable ammunition or explosives,
presenting parallel operating lines but may
require physical separation or other control
measures to ensure inventory control and
management of explosives limits.
(sss) Operational shield. A barrier
constructed at a particular location or around
a particular machine or operating station to
protect personnel, material, or equipment
from the effects of a possible localized fire or
explosion.
(ttt) Parallel operating lines. Adjacent
buildings or other facilities that process the
same or comparable ammunition. or
explosives presenting the same or
comparable hazards and using the same or
comparable process methods. Such
ammunition or explosives processed at
related work stations in the same building or
facility are not parallel operating lines but
may require physical separation or other
control measures to ensure inventory control
and management of explosives limits.
(uuu) Passenger railroad. Any steam,
diesel, electric, or other railroad which
carries passengers for hire.
(vvv) Potential Explosive Site (PES). The
location of a quantity of explosives that will
create a blast, fragment, thermal, or debris
hazard in the event of an accidental
explosion of its contents. Quantity limits for
ammunition and explosives at a PES are
determined by the distance to an ES.
(www) Prohibited area. A specifically
designated area at airfields, seadromes, or
E:\FR\FM\29MRP2.SGM
29MRP2
16076
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
heliports in which all ammunition and
explosives facilities are prohibited.
(xxx) Propellant. Explosives compositions
used for propelling projectiles and rockets
and to generate gases for powering auxiliary
devices.
(yyy) Public highway. Any street, road, or
highway used by the general public for any
type of vehicular travel.
(zzz) Public traffic route. Any public street,
road, highway, navigable stream, or
passenger railroad (includes roads on a
military reservation that are used routinely
by the general public for through traffic).
(aaaa) Pyrotechnic material. The explosive
or chemical ingredients, including powdered
metals, used in the manufacture of military
pyrotechnics.
(bbbb) Quantity-Distance (Q–D). The
quantity of explosive material and distance
separation relationships that provide defined
types of protection. These relationships are
based on levels of risk considered acceptable
for the stipulated exposures and are tabulated
in the appropriate Q–D tables. Separation
distances are not absolute safe distances but
are relative protective or safe distances.
Greater distances than those shown in the
tables shall be used whenever practicable.
Tables are contained in DoD 6055.9–STD and
form a part.
(cccc) Ready ammunition storage. A
location where ammunition is stored for
near-term tactical or training use. Generally,
ready ammunition storage will supply one or
more armament pads.
(dddd) Renovation. The work performed
on ammunition, missiles, or rockets to restore
them to a completely serviceable condition.
this usually involves the replacement of
unserviceable or outmoded parts.
(eeee) Risk. The product of the probability
or frequency an accident will occur within a
certain time and the accident’s consequences
to people, property or the environment.
(ffff) Robust munitions. These are
munitions that meet two of the following
three criteria:
(1) Have a ratio of the explosive weight to
empty case weight less than 1.00;
(2) Have a normal wall thickness of at least
0.4 inches; and
(3) Have a case thickness/NEW1⁄3>0.05 in/
lb1⁄3. The following cartridges are by
definition, robust: 20mm, 25mm, and 30mm.
Other examples of robust ammunition
include MK 80 series bombs, M107
projectiles, Tomahawk and Harpoon
penetration warheads. (Changed at 319th
Board Meeting).
(gggg) Rock strength. Strong, moderately
strong, and weak rock are designators which
provide a general classification of a rock
body into one of these rankings is based on
the rock impedance factor:
Rock impedance factor = p.c.10–6
and p = y/g
where
y is the rock density, lbs/ft3
g is the gravitational acceleration, ft/sec2
p is mass density of the rock, lbs-sec2/ft4
c seismic velocity of the rock, ft/sec.
(1) The rock impedance factor will be 0.75
or more for strong rock. Between 0.75 and 0.5
for moderately strong rock. and less than 0.5
for weak rock.
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(2) Values of these parameters can usually
be estimated based on examinations of
exposed rock outcrops or core samples from
an exploratory drill hole. For the detailed
design of an underground storage facility
(maximum) span width, rock reinforcement,
etc.), standard rock mechanics classification
systems should be used.
(hhhh) Runway. Any surface on land
designated for aircraft takeoff and landing
operations, or a designated lane of water for
takeoff and landing operations of seaplanes.
(iiii) Secure explosives holding area. An
area designated for the temporary parking of
commercial carriers’ motor vehicles
transporting DoD-owned Arms, Ammunition,
Explosives (AA&E).
(jjjj) Secure non-explosives holding area.
An area designated for the temporary parking
of commercial carriers’ motor vehicles
transporting Categorized DoD Arms,
classified (SECRET or CONFIDENTIAL)
materials, and Controlled Cryptographic
Items (CCI).
(kkkk) Service magazine. A building of an
operating line used for the intermediate
storage of explosives materials.
(llll) Single-chamber storage site. An
excavated chamber with its own access to the
natural ground surface, not connected to any
other storage chamber.
(mmmm) Spall. Pieces of a material (and
the process by which they are formed) that
are broken lose from the surface of a parent
body by tensile forces created when a
compression shock wave travels through the
body and reflects from the surface. For
underground storage, spall normally refers to
the rock broken loose from the wall of an
acceptor chamber by the shock wave
transmitted through the rock from an
explosion in a nearby donor chamber.
(nnnn) Static missile battery. Deployed
ground-based missiles meant to be employed
in a non-mobile mission for offensive or
defensive purposes.
(oooo) Static test stand. Locations on
which liquid propellant engines or solid
propellant motors are tested in place.
(pppp) Substantial dividing wall. An
interior wall designed to prevent
simultaneous detonation of explosives on
opposite sides of the wall. however, such
walls may not prevent propagation
(depending on quantities and types of
explosives involved).
(1) Substantial dividing walls are one way
of separating explosives into smaller groups
to minimize the results of an explosion and
allow a reduction in Q–D. These walls do not
protect personnel near the wall from high
explosives because the spalling of wall
surface opposite the explosion source may
form dangerous secondary fragments.
(2) Reinforced concrete-type walls may
vary in thickness, but will be at least 12 in
(305 mm) thick. At a minimum, both will be
reinforced with rods at 1⁄2 in (12.7 mm) in
diameter. The rods will be spaced not more
than 12 in (305 mm) on centers horizontally
and vertically, interlocked with footing rods
and secured to prevent overturning. Rods on
one face will be staggered with regard to rods
on the opposite face and should be
approximately 2 in (50.8 mm) from each face.
Concrete should have a design compressive
PO 00000
Frm 00040
Fmt 4701
Sfmt 4700
strength on 2,500 psi (17.24 MPa) or more.
The capability to prevent simultaneous
detonation is based on a limit of 425 net lb
(193 kg) of mass-detonating explosives. All
storage plans and Q–D calculations shall be
based on the total quantity of massdetonating explosives on both sides of a
dividing wall when the quantity of either
side exceeds 425 lb (193 kg). Explosives
should be 3 ft (0.91 m) or more from the wall.
(3) Retaining walls filled with earth or sand
must be at least 5 ft (1.5 m) wide, with earth
or sand packed between concrete, masonry,
or wooden retaining walls.
(qqqq) Support facilities. Ammunition and
explosives storage or operations that support
solely the functions of tactical or using units
as distinguished from storage depots or
manufacturing facilities.
(rrrr) Suspect truck and car site. A
designated location for placing trucks and
railcars containing ammunition and
explosives that are suspected of being in a
hazardous condition. These sites area also
used for trucks and railcars that may be in
a condition that is hazardous to their
contents.
(ssss) Taxiway or taxilane. Any surface
designated as such in the basic airfield
clearance criteria specified by a DoD
Component publication or Federal Aviation
Regulation.
(tttt) Toxic area. A defined area in which
CG K or Class 6 chemical agents are handled
or stored.
(uuuu) Ufer ground. A Ufer Ground is an
earth electrode system which consists of
solid conductors encased along the bottom of
a concrete foundation footing or floor
indirect contact with the earth.
(vvvv) Unexploded ordnance. Explosive
ordnance which has been primed, fuzed,
armed or otherwise prepared for action, and
which has been fired, dropped, launched,
projected or placed in such. a. manner as to
constitute a hazard to operations,
installations, personnel or material and
remains unexploded either by malfunction or
design for any other cause.
(wwww) Unit risk. The risk to personnel
and/or facilities that is associated with
debris, fragment and/or blast hazards that is
result of the detonation of a single round of
ammunition.
(xxxx) Waste military munitions. Military
munitions are waste when they are solid or
hazardous waste under the regulations (42
U.S.C. 9601, et seq. implementing the
Resource Conservation and Recovery Act
(RCRA) subpart EE of part 264 of 40 CFR),
or defined as a waste under a DoD
Component’s written procedures. Waste
military munitions are defined in §266.202 of
40 CFR). (Note: Decision about whether
specific munitions are or are not waste
should be made with reference to §260.10
and §§266.200 through 266.206 of 40 CFR).
(1) An unused military munition is a solid
waste when any of the following occurs:
(A) The munition is abandoned by being
disposed of, burned, detonated (except
during intended use), incinerated, or treated
before disposal.
(B) The munition is removed from storage
in a military magazine or other storage area
for the purpose of being disposed of, burned,
or incinerated, or treated prior to disposal.
E:\FR\FM\29MRP2.SGM
29MRP2
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 / Proposed Rules
(C) The munition is deteriorated or
damaged (e.g.< the integrity of the munition
is compromised by cracks, leaks, or other
damage) to the point that it cannot be put
into serviceable condition, and cannot
reasonably be recycled or used for other
purposes. or,
(D) An authorized military official has
declared the munition a solid waste. (Note:
Declaration by and ‘‘authorized military
official’’ that munitions are waste (Section
266.202(b)(4) of 40 CFR) has a very limited
meaning and applicability. The only example
is a declaration by the Army in 1984 that
M55 rockets are waste. The environmental
Protection Agency expects that such a
declaration would be in writing. A decision
that munitions are unserviceable, or that they
are to be transferred into a demilitarization
account does not, by itself, constitute a
decision that the munitions are solid waste).
(2) A used or fired military munition is a
solid waste, it follows:
VerDate jul<14>2003
21:15 Mar 28, 2005
Jkt 205001
(A) When transported off range or from the
site of use, where the site of use is not a
range, for the purposes of storage,
reclamation, treatment, disposal, or treatment
before disposal. or,
(B) If recovered, collected, and then
disposed of by burial, or land filling either
on or off a range.
(C) For the RCRA (section 1004(27) of 40
CFR), a used or fired military munition is a
solid waste, and therefore, is potentially
subject to RCRA corrective action authorities
under Section 3004(u) and 3004(v), and
3008(h) of 40 CFR, the munition lands offrange and is not promptly rendered safe and/
or retrieved. Any imminent and substantial
threats associated with any remaining
material must be addressed. If remedial
action is not possible, the operator of the
range must maintain a record of the event for
as long as any threat remains. The record
must include the type of munition and its
location (to the extent the location is known).
PO 00000
Frm 00041
Fmt 4701
Sfmt 4700
16077
(For further clarification see 40 CFR 266.202
under ‘‘Definition of Solid Waste.’’).
(yyyy) Waiver. A written authority that
provides a temporary exception, permitting
deviation from mandatory requirements of
this Part. It generally is granted for short
periods of time pending cancellation as a
result of termination of scheduled work
commitment or correction of the waived
conditions.
(zzzz) Wharf. A landing place or platform
built into the water or along the shore for the
berthing of vessels.
(aaaaa) Wharf yard. A yard that is close to
piers or wharves in which railcars or trucks
are held for short periods of time before
delivery to the piers or wharves.
Dated: March 15, 2005.
Jeannette Owings-Ballard,
OSD Federal Register Liaison Officer,
Department of Defense.
[FR Doc. 05–5429 Filed 3–28–05; 8:45 am]
BILLING CODE 5001–06–P
E:\FR\FM\29MRP2.SGM
29MRP2
Agencies
[Federal Register Volume 70, Number 59 (Tuesday, March 29, 2005)]
[Proposed Rules]
[Pages 16038-16077]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-5429]
[[Page 16037]]
-----------------------------------------------------------------------
Part III
Department of Defense
-----------------------------------------------------------------------
Office of the Secretary
-----------------------------------------------------------------------
32 CFR Part 184
Contractors' Safety for Ammunition and Explosives; Proposed Rule
Federal Register / Vol. 70, No. 59 / Tuesday, March 29, 2005 /
Proposed Rules
[[Page 16038]]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
Office of the Secretary
32 CFR Part 184
RIN 0790-AH76
[DoD 4145.26-M]
Contractors' Safety for Ammunition and Explosives
AGENCY: Office of the Secretary of Defense.
ACTION: Proposed rule for comment.
-----------------------------------------------------------------------
SUMMARY: The Department of Defense (DoD) is codifying its revised
explosives safety standards for ammunition and explosives (A&E) work
performed under DoD contracts. This proposed rule is necessary to
minimize the potential for mishaps that could interrupt DoD operations,
delay project completion dates, adversely impact DoD production base or
capability, damage or destroy DoD-owned material/equipment, cause
injury to DoD personnel, or endanger the general public. The benefits
of this proposed rule in terms of the protection of the public and
ensuring contract performance are expected to balance its potential
cost or administrative impacts. Only provisions related to conventional
AE operations have been included in this proposed rule. No attempt was
made to encompass general industrial safety, occupational health
concerns, chemical warfare agents, radiation, or over-the-road
transportation requirements, because these are either the
responsibility of other regulatory agencies (for example DOT, DOL/OSHA,
or NRC) or may be addressed elsewhere in the contract by the procuring
activity. Budgetary effects of this proposed rule are minimal since
existing DoD Federal Acquisition Regulation Supplement coverage already
requires compliance with safety requirements in AE solicitations and
contracts. Finally, because this proposed rule is needed to minimize
the potential for AE mishaps that could adversely impact DoD and the
public, timely publication in the Federal Register is important.
DATES: Comments are to be received not later than May 31, 2005.
FOR FURTHER INFORMATION CONTACT: Dr. Jerry M. Ward, Director, Engineer
Technical Programs Division, DDESB, telephone (703) 325-2525, fax:
(703) 325-6227; e-mail: Jerry.Ward@DDESB.OSD.mil.
SUPPLEMENTARY INFORMATION: Pursuant to the authority vested in the
Secretary of Defense in accordance with 10 U.S.C. 172, DoD Directive
6055.9 established the Department of Defense Explosives Safety Board as
a joint activity of the Department of Defense subject to the direction,
authority and control of the Secretary of Defense. The majority of the
standards impacting upon the public were adopted prior to the enactment
of the Administrative Procedure Act. This proposed rule is intended to
ensure public awareness of the extent of the explosives safety
standards as well as offer the public an opportunity to comment on the
standards. The information addresses the HCSDS sometimes furnished with
solicitations or contracts to provide an insight into potentially
hazardous characteristics of the materials involved in the production
of the item addressed in the solicitation. Contractors retain the
ultimate responsibility for assuring the safety of their personnel and
establishment. Information provided by the HCSDS is derived from other
sources. Verification of such data as shipping and storage hazard
division and storage compatibility group information must be done
through the DoD Joint Hazard Classification System (JHCS) or Title 49,
Code of Federal Regulations.
These classifications pertain to AE packaged for transportation or
storage. Such hazard classification information may not be valid when
applied to the hazards associated with manufacturing or loading
processes. For such processes, the materials and processes must be
analyzed on a case-by-case basis. Sources of information to support
this analysis are available from service research and development
organizations through contract channels and other sources.
Executive Order 12866
This proposed rule does not:
(1) Have an annual effect of the economy of $100 million or more or
adversely affect in a material way the economy, a sector of the
economy, productivity, competition, jobs, the environment, public
health or safety, or state, local, or tribal governments.
(2) Create a serious inconsistency or otherwise interfere with an
action taken or planned by another agency.
(3) Materially alter the budgetary impact of entitlement, grants,
user fees, or loan programs or the rights and obligations of recipients
thereof; or
(4) Raise novel legal or policy issues arising out of legal
mandates, the President's priorities, or the principles set forth in
this Executive Order.
Regulatory Flexibility Act of 1980 (5 U.S.C. 605(b))
Regulatory Flexibility Act. It has been certified that this
proposed rule, if promulgated, shall be exempt from the requirements
under 5 U.S.C. 601-612. This proposed rule does not have a significant
economic impact on small entities as defined in the Act.
Unfunded Mandates Act of 1995 (Sec. 202, Pub. L. 104-4)
This proposed regulatory action does not contain a Federal mandate
that will result in the expenditure by State, local, and tribal
governments, in aggregate, or by the private sector of $100 million or
more in any one year.
Paperwork Reduction Act of 1995 (44 U.S.C. Chapter 35)
Paperwork Reduction Act. The proposed rule imposes no obligatory
information requirements beyond internal Department of Defense needs.
Federalism (Executive Order 13132)
This proposed regulatory action does not have federalism
implications, as set forth in Executive Order 13132. It will not have
substantial direct effects on the States, on the relationship between
the national government and the States, or on the distribution of power
and responsibilities among the various levels of government.
Section 202, Public Law 104-4, ``Unfunded Mandates Reform Act''
It has been determined that this rule does not involve a Federal
mandate that may result in the expenditure by State, local and tribal
governments, in the aggregate, or by the private sector, of $100
million or more and that such rulemaking will not significantly or
uniquely affect small governments.
List of Subjects in 32 CFR Part 184
Ammunition and explosives, DoD contractors.
Accordingly, 32 CFR part 184 is proposed to be added to read as
follows:
PART 184--DOD CONTRACTORS' SAFETY MANUAL
Sec.
184.1 Introduction.
184.2 Mishap investigation and reporting.
184.3 General safety requirements.
184.4 Quantity-distance and siting.
184.5 Hazard classification, storage principles, and compatibility
groups.
184.6 Electrical safety requirements for AE facilities.
184.7 Manufacturing and processing propellants.
184.8 Safety requirements for manufacturing and processing
pyrotechnics.
184.9 Storage of ammunition and explosives.
184.10 Fire protection.
184.11 Risk identification and management.
[[Page 16039]]
184.12 AE building design and layout.
184.13 Safety requirements for specific AE and AE operations.
184.14 Test and testing requirements.
184.15 Collection and destruction requirements for AE.
184.16 Construction and siting criteria.
Appendix A to 32 CFR Part 184--Glossary
Authority: 10 U.S.C. 172.
Sec. 184.1 Introduction.
(a) Purpose. This part provides safety requirements, guidance and
information to minimize potential mishaps which could interrupt
Department of Defense (DoD) operations, delay production, damage DoD
property, cause injury to DoD personnel, or endanger the public during
contract work or services involving ammunition and explosives (AE). The
part contains the minimum contractual safety requirements to support
the objectives of DoD. These requirements are not a complete safety
program and this part does not relieve a contractor from complying with
Federal, State and local laws and regulations.
(b) Applicability. These safety requirements apply to contractors
performing AE work or AE services on DoD contracts, subcontracts,
purchase orders, or other procurement methods. The requirements also
apply to non-DoD contractor operations to the extent necessary to
protect DoD work or services.
(c) Mandatory and advisory requirements. The part uses the term
``shall'', or an affirmative statement, to indicate mandatory
requirements. The terms ``should'' and ``may'' are advisory. When
advisory provisions are not met, adverse consequences might develop and
become proximate causes of AE mishaps.
(d) Compliance with mandatory requirements. (1) The Department of
Defense requires compliance with mandatory provisions of this part and
applicable portions of DoD 6055.9-STD.\1\ Siting criteria for AE are
provided in quantity distance (Q-D) standards contained in Chapter 9 of
DoD 6055.9-STD. In order to provide consistent and current information
to all DoD AE contractors, Q-D requirements of DoD 6055.9-STD are
incorporated by reference in paragraph C317.
---------------------------------------------------------------------------
\1\ Copies may be obtained via Internet at https://www.dtic.mil/
whs/directives.
---------------------------------------------------------------------------
(2) Waivers. Procuring contracting officers (PCO) may grant
contract-specific waivers to mandatory provisions of this part.
Rationale for waiver of DoD pre-award safety surveys must be documented
and provided to the cognizant ACO for transmittal to the cognizant DoD
Component explosives safety office for their records. Military or
commercial ammunition and explosives shall not be procured unless their
use is authorized by the cognizant DoD Component explosives safety
approval authority. Methods of addressing non-compliance with mandatory
requirements and requests for waivers are different during the pre- and
post-award phases of a contract.
(3) In the pre-award phase, the PCO will request a DoD pre-award
safety survey to help determine contractor capability. During pre-award
surveys, noncompliance with mandatory safety requirements normally
results in a recommendation of ``no award.'' Any noncompliance should
be resolved during the pre-award survey. Contractors may choose to
correct the deficiencies immediately, may offer a letter of intent to
correct the deficiencies (which will become binding upon award of
contract), or may request that the PCO accept specifically identified
existing conditions of facilities (contract-specific waiver).
(4) In the post-award phase, the contractor has 30 days from the
date of notification by the administrative contracting officer (ACO) to
correct the noncompliance and inform the ACO of the corrective actions
taken. The contracting officer may direct a different time period for
the correction of any noncompliance. If the contractor refuses or fails
to correct any noncompliance within the time period specified by the
ACO, the Government has the right to direct the contractor to cease
performance on all or part of affected contracts. When the contractor
cannot comply with the mandatory safety requirements of the contract,
the contractor will develop and submit a request for a waiver through
the ACO to the PCO for the final determination. The request will
contain complete information concerning the requirements violated,
actions planned to minimize the hazard, and a proposed date for
correction of the deficiency.
(e) Pre-award safety survey. DoD safety personnel conduct pre-award
surveys to evaluate each prospective contractor's ability to comply
with contract safety requirements. The pre-award safety survey is also
an opportunity for the contractor to request clarification of any
safety requirement or other AE issue that may affect the contractor's
ability to comply. During pre-award surveys, the contractor shall
provide the following:
(1) Site plans conforming to paragraphs (h)(5)(i) through
(h)(5)(iv) of this section for proposed facilities to be used in
contract performance.
(2) Evidence of implementation of a safety program containing at
least mandatory requirements described in Sec. 184.3.
(3) General description of proposed contract facilities, including
size, building layouts, construction details, and fire resistive
capabilities.
(4) Fire prevention program and available firefighting resources
including local agreements or other documentation demonstrating
coordination.
(5) Copies of required licenses and permits or demonstration of the
ability to obtain approvals necessary to support the proposed contract.
(6) A safety history including mishap experience, safety survey or
audit reports by insurance carriers or Federal, State, and local
authorities, and any variances, exemptions or waivers of safety or fire
protection requirements issued by Federal, state or local authorities.
(7) Details of proposed operations and equipment to include process
flow narrative/diagram, proposed facility or equipment changes, hazard
analysis, and proposed procedures for all phases of AE operations.
(8) Subcontractor information. (i) Identification of all
subcontractors proposed for the AE work.
(ii) Methods used to evaluate capability of subcontractor to comply
with the requirements of this part.
(iii) Methods used to manage subcontractor compliance.
(f) Preoperational safety survey. The DoD reserves the right to
conduct a preoperational survey after contract award of new items with
limited contractor experience, after major new construction or major
modifications, or after an AE mishap. When these situations occur, the
contractor shall notify the ACO, sufficiently in advance, to provide
the Department of Defense the opportunity to schedule and perform a
preoperational survey.
(g) Post-award contractor responsibilities. The contractor shall:
(1) Comply with the requirements of this part and any other safety
requirements contained within the contract.
(2) Develop and implement a demonstrable safety program, including
operational procedures, intended to prevent AE-related mishaps.
(3) Designate qualified individuals to administer and implement
this safety program.
(4) Prepare, and keep available for review, all hazard analyses
used to justify alternative methods of hazards control that differ from
those recommended in this part.
[[Page 16040]]
(5) Provide access to facilities and safety program documentation
to Government safety representatives.
(6) Report and investigate AE mishaps in accordance with Sec.
184.2.
(7) Provide identification and location of subcontractors to the
ACO for notification or approval in accordance with terms of the
contract.
(8) Establish and implement management controls to ensure AE
subcontractors comply with paragraphs (g)(1) through (g)(7) of this
section.
(h) Site and construction plans. (1) Contractors must prepare site
and construction plans for support of the pre-award process, and for
any change in layout or construction potentially affecting Q-D incident
to the contract. Contractors shall also maintain a current site map
depicting Q-D relationships for all AE locations within the facilities.
(2) When the place of performance of the contract is at a DoD-owned
facility, site and construction plans shall be prepared and processed
(content and staffing) in accordance with the requirements of DoD
6055.9-STD, as well as, appropriate military service regulations
contained within the contract.
(3) For contractor-owned, contractor-operated (COCO) facilities,
the contractor shall submit, through the ACO to the PCO, site and
construction plans for all new construction or major modification of
facilities for AE activities and for the facilities that may be exposed
to AE hazards if improperly located. The contractor shall provide
sufficient copies for the review process. The contractor shall not
begin construction or modification of proposed facilities until
receiving site and construction plan approval from the PCO through the
ACO.
(4) Minor new construction, changes, and modifications of existing
AE facilities involving Hazard Class/Division (HC/D) additions and
deletions or that add or remove small portable operating buildings and
magazines may not require formal site plan submission. Minor applies to
all changes that involve only 1.4 HC/D materials. Minor also applies to
changes of other HC/D materials that do not increase the existing
maximum credible event (MCE) for an AE facility or do not extend any
quantity distance arcs beyond existing fragment, inhabited building,
and public traffic route distance arcs for other nearby potential
explosion sites (PES). When the contractor thinks a modification/change
is minor, he shall notify the ACO and request a determination. The ACO
shall make the final determination as to whether a formal site plan
submission is necessary.
(5) Site plans shall comply with the following:
(i) Plans shall include maps and drawings which are legible,
accurate, and of a scale which permits easy determination of essential
details. For general layout of buildings, this is normally a scale of 1
inch to 400 feet (or metric equivalent) or less. Site plans may require
other-scaled drawings, which provide details of construction, structure
relationships within the project area, barricades, or other unique
details. Plans may also include pictures to illustrate details and
videotapes of MCE testing data.
(ii) Maps and drawings shall identify distances between all PESs,
all exposed sites (ESs) within the facility, the facility boundary, any
additional property under contractor control, ESs on adjacent property
when applicable, public railways and highways, power transmission lines
and other utilities.
(iii) Plans shall identify and briefly describe all PESs and all
ESs within any applicable fragmentation distance and/or inhabitable
building distance of a PES. Site plans for major new construction or
modification shall also identify and briefly describe all PESs whose
inhabitable building distance are includes the proposed new or modified
site.
(iv) Plans shall include the maximum net explosive weight(s) (NEW)
and the HC/Ds of all PESs and, when applicable, shall include MCE
information and maximum NEW for each room or bay. Plans shall also
include engineering or test data when substituting construction or
shielding for distance to protect from fragmentation or overpressure.
(v) Plans shall include a topographical map in sufficient detail to
permit evaluation, when the contractor uses natural terrain for
barricading to reduce fragment distance.
(6) Construction plans for proposed facilities shall contain the
information required in paragraphs (h)(5)(i) through (h)(5)(v) of this
section and construction details of dividing walls, venting surfaces,
firewalls, roofs, operational shields, barricades, exits, ventilation
systems and equipment, AE waste disposal systems, lightning protection
systems, grounding systems, processing equipment auxiliary support
structures, and, general materials of construction, as applicable.
Sec. 184.2 Mishap investigation and reporting.
(a) General. This section contains requirements for investigating
and reporting mishaps involving AE.
(b) Reporting criteria. The contractor shall investigate and report
to the ACO and cognizant Defense Contract Management Agency (DCMA)
contract safety specialist all mishaps involving ammunition or
explosives that result in one or more of the following:
(1) One or more fatalities.
(2) One or more lost-work day cases with days away from work as
defined by 29 U.S.C. 651-678.
(3) Five or more non-fatal injuries (with or without lost
workdays).
(4) Damage to government property exceeding $20,000.
(5) Delay in delivery schedule exceeding 24 hours. (This
requirement does not constitute a waiver or amendment of any delivery
schedule required by the contract.).
(6) Contractually required notifications of mishaps other than in
paragraphs (b)(1) through (b)(5) of this section; or
(7) Any mishap that may degrade operational or production
capability, or is likely to arouse media interest.
(c) Mishap investigation requirements. Paragraph (e) of this
section contains the elements of information which a basic
investigation shall produce. Based upon the seriousness of the mishap
and impact on munitions or munitions systems involved, the ACO or PCO
may require an additional, more comprehensive investigation. The PCO
retains the right to participate in contractor investigations, or to
perform an independent DoD investigation. In the event the PCO directs
DoD participation, or an independent DoD investigation, the contractor
shall preserve the mishap scene, taking only those actions necessary to
protect life and health, preclude further damage, or prevent access by
unauthorized persons in order to preserve investigative evidence. The
contractor shall obtain the PCO's permission to disturb the evidence,
with the exception of paragraph (b)(2) of this section. Nothing in the
reporting requirements contained in this part relieve the contractor of
making other notifications required by Federal, State, or local
requirements.
(d) Telephone report. The contractor shall report any mishap
described in paragraph (b) of this section by telephone to the ACO and
cognizant DCMA contract safety specialist as soon as practicable, but
not later than three hours after the mishap.
(e) Written report. (1) The contractor shall submit a written
report to the ACO and cognizant DCMA contract safety specialist by the
end of the second business day after mishap occurrence.
(i) Contractor's name and location.
[[Page 16041]]
(ii) Date, local time, and plant facility/location of the mishap.
(iii) Type of mishap (explosion, fire, loss, other).
(iv) Contract, subcontract, or purchase order.
(v) Item nomenclature, hazard classification, lot number.
(vi) Mishap narrative.
(vii) Number of injuries, fatalities, degree of injuries. (viii)
Description of property damage and cost.
(ix) Quantity of energetic material involved (pounds, units,
rounds).
(x) Probable cause(s).
(xi) Corrective action taken or planned.
(xii) Effect on production.
(xiii) Name, title or position, and phone number of person
submitting the report.
(xiv) Remarks.
(2) The contractor shall provide to the ACO supplemental
information to the initial report within 30 days of mishap occurrence.
(f) Special technical mishap investigations and reports. When
warranted by the circumstances of a mishap, the PCO may require a
special technical investigation conducted by DoD personnel. The PCO may
also direct the contractor to conduct a special technical
investigation. In either case, the investigation report shall provide
details such as fragmentation maps, photographs, more detailed
description of events of the mishap, effects on adjacent operations,
structural and equipment damage, Q-D drawings, detailed description of
occurrence and related events, findings and conclusions. If the
contractor performs the special technical mishap investigation, the
contractor shall forward the report through the ACO to the PCO within
60 days of the direction by the PCO to perform the investigation. Upon
determination by the PCO that a DoD investigation is required, the PCO
will immediately advise the contractor.
Sec. 184.3 General safety requirements.
(a) General. This section provides general safety requirements for
all AE operations addressed in this part. When these practices exceed
or differ from local or national codes or requirements, the more
restrictive shall apply.
(b) Personnel and material limits. (1) Control of all locations or
operations presenting real or potential hazards to personnel, property,
or the environment is essential for safety and efficiency. Control
measures include minimizing the number of personnel exposed, minimizing
the duration of the exposure, and minimizing the amount of hazardous
material consistent with safe and efficient operations.
(2) All buildings, cubicles, cells, rooms, and locations containing
AE shall have AE and personnel limits prominently posted. Include
supervisors, production workers, and transient personnel when
determining personnel limits. Posted personnel limits are not required
in storage magazines, magazine areas, or transfer points.
(3) All buildings, cubicles, cells, rooms or locations containing
AE shall have prominently posted limits for the quantities of AE
permitted. The posted limits shall not exceed the quantity stipulated
in the site plan, and shall accurately reflect current process
requirements. Post AE limits in storage magazines when the limit
differs from that for other magazines in the block, or when
circumstances prevent the limit from being readily apparent. It is not
required to express AE limits in units of weight or in the number of
items. Express limits in terms of trays, boxes, racks, or other units
more easily observed and controlled.
(c) Standard operating procedures (SOP). (1) Clearly written
procedures are essential to avoid operator errors and ensure process
control. Therefore, before commencing manufacturing operations
involving AE, qualified personnel shall develop, review, and approve
written procedures.
(2) Preparation. The contractor shall prepare and implement written
procedures which provide clear instructions for safely conducting AE
activities. The use of controlled tests is an acceptable method for
developing and validating SOPs. SOPs shall include the following:
(i) The specific hazards associated with the process.
(ii) Indicators for identifying abnormal process conditions.
(iii) Emergency procedures for abnormal process conditions or other
conditions which could affect the safety of the process.
(iv) Personal protective clothing and equipment required by process
personnel.
(v) Personnel and AE limits.
(vi) Specific tools permitted for use by the process operator.
(vii) The chronological sequence of job steps the operator is to
follow in performing the work.
(viii) Procedures for disposing of any scrap and waste AE.
(3) Dissemination. Personnel involved with AE processes, and
personnel who maintain AE equipment, shall have written operating
procedures readily accessible.
(4) Training. Personnel shall receive appropriate training before
performing work involving exposure to AE. The training shall include
emphasis on the specific safety and health hazards, emergency
operations including shutdown, and safe work practices applicable to
the employee's job tasks. The contractor shall ascertain that each
employee involved in an AE process has received and understood the
training. The contractor shall prepare a record that contains the
identity of the employee, the date of training, and the means used to
verify that the employee understood the training.
(5) Emergency procedures. The contractor shall instruct employees
on procedures to follow in the event of electrical storms, utility or
mechanical failures, equipment failures, process abnormalities, and
other emergencies occurring during the manufacturing, handling, or
processing of AE.
(6) Revalidation. Qualified personnel shall review SOPs on a
regular basis. The managing authority shall change and validate SOPs as
often as necessary to reflect improved methods, equipment
substitutions, facility modifications, or process revisions.
(d) Storage in operating buildings. (1) The contractor may store
limited quantities of hazardous materials, other than AE materials,
which are essential for current operations in an operating building.
(2) The contractor shall store AE materials that exceed minimum
quantity necessary for sustained operations in a service magazine
located no closer than the intraline distance (ILD) (based on the
quantity in the magazine) from the operating building or area. If ILD
distance is not available for a separate service magazine, the
contractor may designate storage locations within the operating
building. Designated storage locations shall preclude immediate
propagation from the operational location to the storage location. The
quantity of AE material in the internal storage location shall not
exceed that needed for one half of a work shift. The contractor should
consider personnel exposure, structural containment afforded, and the
venting ability of the proposed storage location when determining where
to locate a designated storage location. When storage containers
completely contain all fragments, debris, and overpressure, AE material
may be stored without regard to Q-D requirements.
(3) At the end of the workday, personnel should remove all AE
material from processing equipment and store it in an appropriate
magazine or designated storage location. If operationally required,
personnel may store in-process AE materials in the
[[Page 16042]]
building during non-operating hours provided the physical
characteristics and stability of the AE materials are not degraded, and
the AE material would not compromise the safety of the process
equipment or personnel when the process is restarted.
(4) The contractor may use a separate enclosed room or bay in an
operating building specifically adapted for the interim storage of
production items awaiting the results of testing before final pack-out.
The room or bay must afford the equivalent of service magazine distance
protection to other parts of the building, and ILD to other buildings.
Such a room or bay is limited to its defined and designed function and
items, but is not subject to the four-hour supply limitation for the
building or the ultimate pack-out operation.
(e) Housekeeping in hazardous areas.
(1) The contractor shall keep structures containing AE clean and
orderly.
(2) Explosives and explosive dusts shall not accumulate on
structural members, radiators, heating coils, steam, gas, air or water
supply pipes, or electrical fixtures.
(3) Written procedures shall include instructions for the removal
of spilled material.
(4) Floor cleaning methods shall not create an ignition hazard or
alter the conductive ability of floors in AE areas, nor should they
result in an environmental contamination potential.
(5) Cleaning methods for AE processing equipment shall not result
in any foreign material or AE remaining in the equipment.
(f) Precautions for maintenance and repairs to equipment and
buildings. (1) The contractor shall examine and test all new or
repaired AE processing equipment prior to placing the equipment in
service in order to ensure that it is safe to operate.
(2) Before proceeding with maintenance or repairs to AE processing
equipment, contractor personnel shall decontaminate the equipment to
the degree necessary to perform the work safely. The contractor shall
protect maintenance personnel from the effects of a reaction resulting
from AE material in or on other parts of the equipment. Contractor
personnel shall tag AE processing equipment before proceeding with
repairs. The tag shall identify the decontaminated parts of the
equipment, and those parts that contain AE.
(3) The contractor shall have SOPs for maintenance personnel
performing work on AE equipment or performing building maintenance,
repair, or modification activities in AE areas. The SOPs shall include
a provision for inspecting equipment after maintenance work to ensure
no tools or foreign materials remain in AE equipment. The SOPs shall
identify the specific tools required to perform work on equipment which
may contain explosive residues or areas which could have an explosive
atmosphere.
(4) Before performing any building repair, modification or
maintenance activity, the contractor shall ensure the removal of all AE
materials from areas that may pose a hazard. The contractor shall also
ensure the decontamination of all places where AE material could
accumulate, such as, equipment, crevices, vents, ducts, wall cavities,
pipes and fittings.
(g) Operational shields. (1) The purpose of operational shields is
to prevent propagation of AE material from one AE operation or location
to another, protect facilities and equipment, and provide personnel
protection. Shields used for these purposes require an evaluation to
determine their suitability for their intended purpose. All AE
operations and processes require a hazard assessment prior to work
performance to determine the type of hazard involved, the level of risk
associated with the AE material or item, and the corresponding level of
protection required.
(2) The primary hazards that accompany explosions and deflagrations
are blast overpressure, fragmentation (primary and secondary) and
thermal effects. The hazard assessment shall consider these hazards and
the quantity of AE materials, initiation sensitivity, heat output, rate
of burning, potential ignition and initiation sources, protection
capabilities of shields, various types of protective clothing, fire
protection systems, and the acute and chronic health hazards of vapors
and combustion products on exposed personnel.
(3) When the hazard assessment indicates an unacceptable
probability of explosion or deflagration, conduct operations or
processes remotely. When an analysis of the hazard assessment indicates
the hazards associated with an explosion or deflagration are
controllable by using operational shields, the contractor shall design,
install, and use shields which effectively protect personnel from the
hazards. Shields complying with MIL-STD-398 are acceptable protection.
(4) The contractor shall test operational shields under conditions
that simulate the operational environment. AE materials or items used
in the test shall correspond to those that may be involved in a maximum
credible event (MCE), plus 25 percent. The contractor shall maintain
records of the test that demonstrate the shields will function as
planned. Analysis rather than testing of shields may be acceptable on a
case-by-case basis.
(5) When the doors of AE processing equipment function as
operational shields, interlocking devices are required to prevent the
operator from opening the door while the equipment is in operation.
(h) Protective clothing. (1) All AE operations require a hazard
assessment to determine the need for protective clothing and personal
protective equipment. The assessment shall include an evaluation of all
hazards and factors contained in paragraph (g)(2) of this section.
(2) The contractor shall provide a changing area for employees who
must remove their street clothes to wear protective clothing, such as
explosive plant clothing, anti-contamination clothing, impervious
clothing, and so forth. To avoid exposing personnel not involved in AE
operations to unnecessary risks, employees shall not wear or remove
protective clothing from the premises. Employees shall not wear any
static producing clothing in areas where static electricity is a
hazard.
(3) Explosives plant clothing, generally referred to as powder
uniforms, shall have nonmetallic fasteners and be easily removable.
(4) When sending explosives-contaminated clothing to an off-plant
laundry facility, the contractor is responsible for informing the
laundry of the hazards associated with the contaminants and any special
laundering or disposal requirements.
(i) Material handling equipment. (1) The contractor shall not
refuel gasoline, diesel or liquefied petroleum gas (LPG) powered
equipment inside buildings containing AE. Refueling shall take place at
least 100 feet from structures or sites containing AE. Doors and
windows through which vapors may enter the building shall not be open
during refueling. Position refueling vehicles at least 100 feet from
structures or sites containing AE during refueling.
(2) Gasoline-, diesel- or LPG-powered equipment shall not be stored
in buildings, loading docks, or piers containing AE. The contractor
shall store gasoline-, diesel-, and LPG-powered equipment at the
appropriate fire protection distance from buildings containing AE.
(3) Gasoline, diesel, and LPG powered equipment shall have spark
arrestors. The contractor shall perform and document inspections of the
exhaust and electrical systems of the equipment
[[Page 16043]]
as necessary to ensure that the systems are functioning within the
manufacture's specifications. The contractor shall maintain
documentation of the inspections for a period of one year.
(j) Parking of privately owned vehicles. (1) Control of parking of
privately owned vehicles within an AE establishment minimizes fire and
explosion hazards and prevents congestion in an emergency.
(2) Parking lots serving multiple PESs shall not be closer than the
ILD from each PES. Parking lots serving a single PES shall not be
closer than 100 feet to the associated facility to protect it from
vehicle fires, and shall be at least public traffic route distance from
unassociated PESs. Parking lots for administration areas shall be
located at public traffic route distance from all PESs.
(3) Vehicles shall not obstruct access to buildings by emergency
equipment or personnel.
(k) Ignition sources in hazardous areas. The contractor shall not
permit any nonessential ignition sources in operating buildings.
(l) Operational explosives containers. (1) Containers shall be
compatible with the material they contain.
(2) Containers used for intraplant transportation or storage of
process explosives and energetic materials shall not leak. Because of
their fragility and potential for fragmentation, glass containers are
not acceptable.
(m) Intraplant rail transportation. (1) The contractor shall
develop written procedures to ensure safe and efficient rail movement
of AE. The SOPs shall include information covering the inspection of
the engine, car mover, and cars, normal and emergency operating
procedures for the engine and car mover, AE loading and unloading
procedures, and emergency procedures including fire fighting.
(2) Railcars positioned for loading shall have their brakes engaged
to prevent movement. Contractor personnel shall inspect each railcar
before loading to ensure it is suitable to carry the specific AE cargo.
Contractor personnel shall check the cargo to ensure it is stable and
secure, and close the railcar doors before car movement. If using an
engine to move railcars, the contractor shall ensure that personnel
have connected the air brakes of the railcars in sequence to the
engine. If moving a railcar with a car mover the contractor shall
station an individual at the hand brake of the railcar.
(3) A single parked railcar shall have the hand brakes set and the
wheels chocked. When more than one railcar is parked, personnel shall
set hand brakes on enough railcars to ensure the cars will not move.
Personnel shall set hand brakes on the downgrade end of a group of
parked railcars. Do not rely on the automatic air brakes to hold parked
railcars.
(4) Contractor personnel shall avoid rough handling of railcars.
Personnel shall not disconnect railcars containing AE from each other
or a locomotive while in motion. Personnel shall couple railcars gently
in order to avoid damaging the AE cargo or shipping containers.
Disconnected railcars shall not strike railcars containing AE.
(5) The contractor shall maintain all rolling stock used for
intraplant transportation of AE in a safe and good working condition.
(6) Portable transmitters and railroad locomotives equipped with
two-way radios shall not transmit when passing AE operating buildings
where electro-explosive devices are in use. The contractor shall
determine minimum safe distances based on radio frequency and power
output of the transmitter.
(n) Intraplant motor vehicle transportation of AE. (1) The
contractor shall develop written procedures for the safe transportation
of AE in motor vehicles. The SOP shall include procedures for vehicle
inspection, vehicle operation, loading and unloading AE materials, and
emergency procedures, including fire fighting.
(2) The operator responsible for transporting AE material shall
perform a daily inspection of the vehicle before transporting
materials. The operator shall verify that the fire extinguisher is
charged and in working order, there are no fuels or other fluid leaks,
and that brakes, tires, steering, and other equipment are in good
operating condition. Before transporting AE, the operator shall inspect
the cargo compartment to ensure it does not contain any residual AE
material or any object which could present a hazard to the cargo.
(3) When loading or unloading AE, the operator shall shutoff the
vehicle's engine, unless the engine is required to provide power to
equipment for loading or unloading. The operator shall engage the
emergency brake and use wheel chocks when the vehicle could move during
loading or unloading. The operator shall stabilize and ensure the load
is secure to prevent damage to containers or their contents. The
operator shall not transport AE material in the passenger compartment
of the vehicle.
(4) The vehicle operator shall understand and follow established
procedures involving a vehicle fire, breakdown, accident, damaged or
leaking containers, and spilled material.
(5) Transportation containers shall not allow the contents to leak
or spill in transit.
(6) Non-sparking material shall cover the cargo compartment when
transporting AE in containers capable of exposing their contents if
damaged.
(7) Motor vehicles transporting AE within the establishment
boundaries but outside the AE area shall bear at least two placards.
Placards based on the fire division symbols discussed in Sec. 184.10,
``Fire Protection,'' are acceptable. Motor vehicles or equipment with
internal combustion engines, used near explosives scrap, waste, or
items contaminated with explosives shall have exhaust system spark
arresters and carburetor flame arresters (authorized air cleaners).
(8) The contractor shall maintain vehicles and material handling
equipment used to load and transport AE in a safe operating condition.
(9) Batteries and wiring shall be located to prevent contact with
containers of AE material.
(o) Inspection of AE mixing equipment. (1) The contractor shall
establish a preventative maintenance program which includes the
inspection of all AE mixing equipment on a periodic basis. The SOP for
the inspection shall include criteria for inspecting the blades to bowl
clearances, alignment of the blades and bowl, and detection of any
distortion of the blades or bowl. The inspection procedures shall also
include instructions for checking critical drive system components for
wear, damage or misalignment. The procedures shall include criteria for
determining that associated equipment used to control the mixer is
functioning as designed. The contractor shall maintain a record of all
inspections. After performing maintenance of the equipment, the
contractor shall run the equipment under load to ensure it is safe to
operate.
(2) The SOPs for operating mixing equipment shall include
instructions for inspecting specific equipment components before each
use.
(p) Facility requirements. (1) Buildings. The design, construction
techniques, process layout, and siting of AE buildings are important
considerations in explosives safety and directly influence quantity
distance (Q-D) requirements and the degree of exposure to personnel,
equipment, and facilities. Construction features which limit the amount
of explosives involved, attenuate the resulting blast overpressure or
thermal radiation, and reduce the quantity and range of
[[Page 16044]]
hazardous fragments and debris will help to minimize the effects of an
explosion. Incorporating Q-D criteria, when locating an exposed site
(ES) in relation to a potential explosive site (PES), will reduce the
amount of damage and injuries in the event of an incident.
(2) Building exteriors. The contractor should design and erect AE
buildings with the ability to allow for the venting of an internal
explosion without collapsing. The use of lightweight materials in
exterior wall and roof sections designed to vent the effects of an
explosion will help reduce the number of large fragments. Exceptions
from using lightweight materials include earth-covered magazines,
containment type structures, firewalls, substantial dividing walls,
special roof loadings, and walls and roofs used for external
overpressure protection. Non-combustible exterior wall and roof
coverings of operating buildings help prevent the spread of fire from
one area of a building to another and from building to building.
(3) Interior walls, roofs, and ceilings. (i) Non-combustible
material is preferred for the interior surfaces of buildings. The
contractor should treat or cover exposed combustion supporting building
materials with fire retardant material.
(ii) Where hazardous locations exist, interior surfaces shall be
smooth, free from cracks, crevices and openings which may create a
hazardous condition. This is important to prevent the accumulation or
migration of explosive dust and vapors which could result in an
incident. The National Fire Protection Association (NFPA), Standard 70
\2\ provides criteria for determining if a location is hazardous.
---------------------------------------------------------------------------
\2\ Obtain NFPA publications from the National Fire Protection
Association at https://www.nfpa.org/catalog/home/index.asp.
---------------------------------------------------------------------------
(iii) The contractor should use hard gloss, easily cleanable, paint
on painted surfaces.
(iv) Periodically clean any surface where explosive dust could
accumulate. Establish cleaning schedules on information obtained from
the job hazard analysis.
(v) Do not use suspended ceilings in hazardous locations.
(4) Floors and work surfaces. (i) Locations where exposed
explosives or hazardous concentrations of flammable vapor or gas are
present require non-sparking floors and work surfaces.
(ii) Sec. 184.12 provides requirements for conductive non-sparking
floors and work surfaces.
(iii) Floors and work surfaces require periodic cleaning to prevent
the accumulation of energetic materials. In addition, all conductive
and non-sparking floors and work surfaces require preventative
maintenance to ensure their functional integrity.
(5) Substantial dividing walls. The contractor shall design and
construct substantial dividing walls to prevent simultaneous detonation
of explosives on opposite sides of the wall. The design and
construction shall meet the criteria contained in Army TM 5-1300, Navy
NAVFAC P-397, or Air Force AFR 88-22 (different designations for the
same publication).
(6) Exits and doors. (i) All AE buildings require adequate exits
and doors. NFPA Standard No. 101, ``Life Safety Code,'' provides
information concerning exits and doors.
(ii) NFPA Standard No. 80, ``Standard for Fire Doors, Fire
Windows,'' provides information on the selection and installation of
fire doors and windows.
(iii) No AE hazards shall occupy space between an operator and an
exit.
(7) Safety chutes. Multi-storied locations where rapid egress is
vital and not otherwise possible require safety chutes.
(8) Passageways. (i) Weather-protected passageways and ramps for
travel between buildings or magazines should include features to help
prevent fire from spreading from one building to another. Fireproof
construction materials, fire stops, fire doors, and fire suppression
systems aid in preventing the spread of fire.
(ii) The incorporation of weak sections, openings, or abrupt change
in direction of passageways will aid in the prevention of funneling the
explosion forces from one building to another.
(9) Roads and walkways. (i) Only roads servicing a single magazine
or AE processing building, including its service facilities, may dead
end at the magazine or building.
(ii) Hard surfaced roads and walkways at the entrances to or
between adjacent operating buildings containing AE will help reduce the
amount of foreign material tracked into the building by personnel.
(iii) Avoid a road system which requires personnel to pass through
an AE area when traveling from one area to another.
(10) Windows and skylights. (i) Inhabited building distances do not
protect against glass breakage and the hazards of flying glass.
Buildings separated by inhabited building distance should not have
windows or other glass surfaces exposed to PESs.
(ii) Minimize personnel hazards from glass breakage by means such
as building orientation and/or keeping the number of exposed glass
panels and panel size to a minimum. When window panels are necessary
and risk assessment determines a glass hazard will be present, blast
resistant windows must be used. The framing and/or sash of such panels
must be of sufficient strength to retain the panel in the structure.
(11) Hardware. (i) AE operations and hazardous locations require an
evaluation to determine the safest type of hardware and fasteners to
use in order to reduce the risk of an accidental ignition. Consider
using non-sparking hardware and fasteners if they will meet the design
parameters of the intended application. Depending on the potential
hazard, a locking device or some other installation technique shall
retain the hardware and fasteners securely in place. This will prevent
the hardware and fasteners from becoming loose, entering process
equipment and creating a spark or pinch point.
(ii) The contractor should avoid installing hardware, pipes, ducts,
and other items on blowout panels in order to prevent the materials
from becoming secondary fragments. If it is necessary to install items
on blowout panels, select items made of materials which will not yield
heavy fragments in an explosion.
(12) Ventilation systems. (i) Well-designed ventilation systems
reduce personnel exposures to airborne contaminants and prevent the
accumulation of flammable or explosive concentrations of gases, vapors
or dusts. A local ventilation system, which removes the gases, vapors,
or dusts at the source, is more effective than a general ventilation
system.
(ii) A ventilation system is required in areas of buildings
generating potentially explosive dusts, gases or vapors. Testing,
inspection, and maintenance of ventilation systems used for contaminant
control require documentation.
(iii) Exhaust fans through which combustible dust or flammable
vapor pass shall have nonferrous blades or a casing lined with
nonferrous material. The electrical wiring and equipment of the system
should comply with provisions of NFPA Standard No. 70, ``National
Electrical Code''. Bonding and grounding of the entire system is
required.
(iv) A slight negative pressure is required in rooms where AE
operations generate explosive dust.
(v) NFPA Standard No. 91, ``Standard for Exhaust Systems for Air
Conveying of Vapors, Gases, Mists, and Noncombustible Particulate
Solids,'' provides standards for exhaust systems.
[[Page 16045]]
(13) Steam for processing and heating. (i) Steam used to heat
buildings containing explosives shall not exceed 228 [deg]F (108.9
[deg]C) or have a pressure greater than 5 psi (34.48 kPa).
(ii) Process steam shall not exceed 249.5 [deg]F (120.8 [deg]C), or
exceed 15 psi (103.43 kPa). Steam pressure greater than 15 psi (103.43
kPa) requires procuring contracting officer (PCO) approval.
(iii) The surface temperature of steam and hot water pipes in
contact with combustible materials shall not exceed 160 [deg]F (71
[deg]C). Pipes with an ambient temperature greater than 160 [deg]F (71
[deg]C) shall not contact combustible materials. An insulating pipe
covering capable of reducing the surface temperature of the covering to
160 [deg]F (71 [deg]C) or less is acceptable.
(iv) In AE handling or storage locations where resistance to ground
is high, ground steam and hot water lines where they enter the
building.
(v) When using a reducing valve, consider installing a relief valve
on the low-pressure piping. The throttling action of reducing valves
requires a positive means to prevent the production of superheated
steam.
(14) Tunnels. Tunnels between buildings that contain AE shall
incorporate features that resist the shock wave of an explosion. This
is important in order to minimize the possibility of an explosion in
one building from affecting the operations in the other building. For
further information on tunnels go to DoD 6055.9-STD.\3\
---------------------------------------------------------------------------
\3\ See footnote 1 to Sec. 184.1(d)(1).
---------------------------------------------------------------------------
(q) Quantity-distance (Q-D) requirements. (1) Minimum Q-D
requirements are contained in DoD 6055.9-STD, DoD Ammunition and
Explosives Safety Standards.
(2) For AE work involving an MCE of 0.25 kg (0.55 lbs) or less of
HD 1.1 materials, the use of the separation distances listed in Table 1
to Sec. 184.3 are acceptable for meeting minimum Q-D requirements.
Table 1 to Sec. 184.3.--Minimum Q-D Requirements for Small Quantities of Hazard Division 1.1 Material
----------------------------------------------------------------------------------------------------------------
Inhabited building and Public traffic route Intraline and fragment
Net explosive weight fragment distance and fragment distance distance
----------------------------------------------------------------------------------------------------------------
Less than 0.003 kg (0.0066 lb)....... 0...................... 0...................... 0.
0.003 kg-0.01 kg (0.0066 lb-0.022 lb) 5 m (16.5 ft).......... 3 m (9.9 ft)........... 2 m (6.6 ft).
0.01 kg-0.25 kg (0.022 lb-0.55 lb)... 15 m (49.5 ft)......... 9 m (29.7 ft).......... 5 m (16.5 ft).
----------------------------------------------------------------------------------------------------------------
Sec. 184.4 Quantity-distance and siting.
Refer to DoD 6055.9, Chapter 9 for guidance.
Sec. 184.5 Hazard classification, storage principles, and
compatibility groups.
Please refer to DoD 6055.9, Chapter 3 for guidance.
Sec. 184.6. Electrical safety requirements for AE facilities.
(a) General. Initiation systems often use the controlled input of
electrical energy to initiate explosive mixtures and compounds, which
start an explosive train. The uncontrolled release of electrical energy
in explosive atmospheres or near explosives and explosive-loaded
articles can result in unintended initiation and serious mishaps.
Electrical energy manifests itself in many forms (e.g., standard
electrical installations, lightning, electrostatic discharge,
electrical testing) and with various intensities which require special
precautions. This chapter contains minimum electrical safety
requirements for existing, new, or modified explosives facilities and
equipment.
(b) Electrical installations. (1) National Fire Protection
Association (NFPA) Standard No. 70 and this section are minimum
requirements for areas containing explosives. NFPA Standard No. 70 does
not specifically address explosives, but it does establish standards
for the design and installation of electrical equipment and wiring in
atmospheres containing combustible dusts and flammable vapors and
gasses which, in general, are comparably hazardous. NFPA Standard No.
70 (Article 500) defines ``hazardous locations'' according to the
hazard presented by electrical equipment installed in environments
where flammable gases or vapors, combustible dusts or flyings may
exist. The presence of AE may or may not result in rating a particular
location as a ``hazardous location.'' The following exceptions shall be
used by DoD contractors when applying the NFPA Standard No. 70
definitions of Class I, Division 1, and Class II, Division 1 hazardous
locations:
(i) Classify areas containing explosive dusts or explosive
substances which may produce dust capable of suspension in the
atmosphere as Class II, Division 1 hazardous locations.
(ii) Classify areas where explosive sublimation or condensation may
occur as both Class I Division 1 and Class II Division 1 hazardous
locations.
(iii) Exceptions are extraordinarily hazardous explosive
substances, such as nitroglycerin (NG), which require special
consideration, including physical isolation from electric motors,
devices, lighting fixtures and the like.
(2) Multiple classifications. In some potential explosion sites
(PES) (e.g., powder blending with solvents), hazards resulting from
both dusts and flammable vapors may exist. In these cases, it is
necessary for that area to have a dual, or multiple, classification.
Use only electrical equipment listed by Underwriters Laboratories (UL)
or other recognized testing laboratory as suitable for use in all
classes of hazardous locations.
(3) Change of classification. The specific processes performed in
operating buildings and magazines dictate the requirements for
electrical equipment installation. If functions performed in the
facility change, responsible personnel shall inspect, approve, or
reclassify the hazardous locations.
(4) Alternate power source. Facilities shall have an alternate
power source for special processes and operations requiring a
continuous supply of power, whenever the loss of power will result in a
more hazardous condition.
(5) Portable engine-driven generators. The exposed, non-current-
carrying, metallic frame and parts shall be electrically grounded. In
addition, observe the following requirements when supplying power to
magazines or explosives operating facilities.
(i) Place generating units at least 50 ft (15.2 m) from magazines
or hazardous (classified) locations.
(ii) Keep the ground area between and around the generator and the
NFPA Standard No. 70 hazardous (classified) location clear of debris
and other combustible materials.
(iii) The exhaust from the generator shall not impinge on grass or
any other combustible material.
(iv) Position the power cord connecting the generator to the load
to
[[Page 16046]]
prevent trucks or personnel from running over or otherwise damaging the
cord.
(v) Do not use cable-to-cable splices within a magazine, explosive
operating facility, or other NFPA Standard No. 70 hazardous
(classified) location. Use only three-wire, three-prong, approved
service type plugs and connectors.
(vi) Refer to Sec. 184.3(i)(1) for refueling procedures.
(6) Electric supply systems. Electrical and explosives hazards may
mutually exist when PES are in close proximity to electric supply
lines. To protect these hazards from each other, the following
separation requirements shall apply:
(i) Separate overhead service lines from a PES of combustible
construction or a PES in the open by the distance between the poles or
towers supporting the lines, unless an effective means is provided to
ensure that energized lines cannot contact the facility or its
appurtenances if they are severed. Four acceptable alternatives are
cable trays and messenger lines, a ground-fault circuit-interrupter
which causes a disconnecting means to open all ungrounded conductors of
the faulted circuit, weighted triangle line separators or similar
weights which ensure broken lines fall straight down away from PES, and
constructed physical barriers.
(ii) Separate electric distribution lines carrying less than 69 kV,
the tower or poles supporting those lines, and unmanned electrical
substations from PES by public traffic route distance (PTRD).
(iii) Separate electric transmission lines carrying 69 kV or more
and the tower or poles supporting them from PES by:
(A) Inhabited building distance (IBD) if the line in question is
part of a grid system serving a large area off the establishment.
(B) PTRD if loss of the line does not create serious social or
economic hardships. (Note: Base PTRD and IBD on airblast overpressure
only. Fragment distances shall not apply.)
(C) Distances in accordance with paragraph (b)(6)(1) of this
section when the line(s) in question can be interrupted without loss of
power (i.e., other lines or networks exist for rerouting power).
(iv) Avoid locating permanent electric installations in NFPA
Standard No. 70 Class I or Class II hazardous locations. When practical
operating reasons prevent locating permanent electrical installations
outside of hazardous locations, or require the use of portable
electrical equipment (e.g., lighting equipment) in hazardous locations,
contractors shall only install or use electrical equipment approved for
the National Electric Code (NEC) defined ``hazardous location'' and
listed by Underwriters Laboratories (UL) or other nationally recognized
testing agencies.
(c) Primary electric supply. The primary electric supply to an
entire explosives area should be arranged to allow cutting off the
supply by remote switches located at one or more central points away
from the area.
(d) Ventilation. Equip exhaust fans, through which combustible dust
or flammable vapor pass, with nonferrous blades, or line the casing
with nonferrous material. Motors shall meet the proper NEC class for
the hazard (NFPA Standard No. 70). Clean and service exhaust systems on
a regular schedule. Bond and ground the entire system.
(e) Lightning protection. When lightning protection systems are
installed, the installation, inspection, and maintenance shall comply
with the NFPA Standard No. 780, at a minimum. Typically, six month
visual tests and 24-month electrical tests of installed systems are
acceptable.
(f) Static electricity and grounding. (1) Two unlike materials (at
least one of which is non-conductive) produce static electricity due to
contact and separation. Contact creates a redistribution of charge
across the area of contact and establishes an attractive force.
Separation of the materials overcomes these attractive forces and sets
up an electrostatic field between the two surfaces. If no conducting
path is available to allow the charges to equalize on the surfaces, the
voltage difference between the surfaces can easily reach several
thousand volts as they separate.
(2) The potential hazard of static electricity arises when an
accumulated electrical charge subsequently discharges as a spark in the
presence of hazardous atmospheres, flammable vapors, dusts, exposed
sensitive explosives, or electro-explosive device (EED). Electrostatic
discharge (ESD) does not present a substantial hazard during the
handling of most bulk explosive substances if the explosives are in
approved containers. It also does not present a hazard near explosives
totally contained and unexposed within loaded articles. It is not
possible to prevent the generation of static electricity entirely.
Elimination of potential ESD hazards requires proper grounding to
dissipate static charges before they accumulate to dangerous levels.
The NFPA, UL and the U.S. Department of Commerce publish detailed
discussions of the hazards of static electricity and ways of reducing
it. Where static spark discharge may be hazardous, NFPA Standard No.
77, shall apply, except as otherwise specified.
(3) Static ground system. A static ground system consists of one or
more electrodes in contact with the earth and a conductor (i.e., metal
wire) bonded to the electrode and routed throughout the protected
facility.