Notice of Issuance of Partial Conditional Exemption; Portland General Electric Company, Trojan Independent Spent Fuel Storage Facility, 15369-15371 [05-5901]
Download as PDF
Federal Register / Vol. 70, No. 57 / Friday, March 25, 2005 / Notices
by 22.5 percent but provides for a rate
adjustment in accordance with the
procedures set forth in section 119(c)(1)
of the Copyright Act.
On March 8, 2005, the Copyright
Office received a letter from EchoStar
Satellite L.L.C., DirecTV, Inc., Program
Suppliers, and the Joint Sports
Claimants requesting that the Office
begin the process of setting the rates for
the retransmission of digital broadcast
signals by initiating a voluntary
negotiation period so that rates for both
digital and analog signals ‘‘will be in
place before the July 31, 2005 deadline
for satellite carriers to pay royalties for
the first accounting period of 2005.’’ 2
Letter at 2. The Office sees no reason not
to grant this request. Accordingly,
today’s notice begins the process
mandated by statute.
Voluntary Negotiation Period
Section 119(c)(2) of the Copyright Act,
17 U.S.C., provides that ‘‘[t]he process
and requirements for establishing the
royalty fee payable . . . for the secondary
transmission of the primary digital
transmissions of network stations and
superstations shall be the same’’ as that
set forth in section 119(c)(1) for the
amendment of the rates paid for the
retransmission of analog signals. Section
119(c)(1) provides that ‘‘the Librarian of
Congress shall cause to be published in
the Federal Register [notice] of the
initiation of the voluntary negotiation
proceedings for the purpose of
determining the royalty fee to be paid by
satellite carriers’’ for the retransmission
of digital broadcast signals. This notice
initiates the voluntary negotiation
period.
The statute does not specify how long
the voluntary negotiation period is to
last. However, the regulations governing
CARP proceedings provide for a ‘‘30–
day period for negotiation of a
settlement’’ when adjusting rates under
the cable, phonorecord and jukebox
statutory licenses. 37 CFR 251.63(a).
Since the rates will be determined
under the current CARP system3 should
parties be unable to negotiate a
2 We note that the letter referenced Docket No.
2004–9 CARP SRA, which is the proceeding to
adjust the rates for the retransmission of analog
signals. As the parties state in their letter, ‘‘the
analog rates and digital rates are distinct and
separate.’’ Letter at 1. We agree. Therefore, we have
assigned a separate docket number to this
proceeding.
3 On November 30, 2004, the President signed
into law the Copyright Royalty and Distribution Act
of 2004, Pub. L. 108–419, which phases out the
CARP system and replaces it with three permanent
Copyright Royalty Judges. However, SHVERA calls
for satellite royalty rates to be determined ‘‘under
chapter 8 as in effect on the day before the date of
enactment of the Copyright Royalty and
Distribution Act of 2004.’’ 17 U.S.C. 119(c)(1)(F).
VerDate jul<14>2003
16:11 Mar 24, 2005
Jkt 205001
voluntary agreement or an objection to
such agreement is raised, the Library
sees no reason not to adopt the period
set forth in § 251.63(a) here. Therefore,
the voluntary negotiation period
commences today, March 25, 2005, and
concludes April 25, 2005.
If a voluntary agreement is reached by
the end of the negotiation period, the
parties can request that the Librarian
publish the agreement for notice and
comment in accordance with section
119(c)(1)(D)(ii)(II) and adopt the rates in
the voluntary agreement if no objections
are received from a party with a
significant interest and an intention to
participate in a CARP proceeding. 17
U.S.C. 119(c)(1)(D)(ii)(III). Voluntary
agreements must be submitted no later
than April 25, 2005. If no agreements
are received by that time, the Library
will proceed in accordance with the
rules and regulations of 37 CFR part
251.
Dated: March 22, 2005
David O. Carson,
General Counsel.
[FR Doc. 05–5953 Filed 3–24–05; 8:45 am]
BILLING CODE 1410–33–S
NUCLEAR REGULATORY
COMMISSION
[Docket No. 72–17]
Notice of Issuance of Partial
Conditional Exemption; Portland
General Electric Company, Trojan
Independent Spent Fuel Storage
Facility
Nuclear Regulatory
Commission.
ACTION: Notice of partial conditional
exemption.
AGENCY:
FOR FURTHER INFORMATION CONTACT:
Christopher M. Regan, Senior Project
Manager, Spent Fuel Project Office,
Office of Nuclear Material Safety and
Safeguards, U.S. Nuclear Regulatory
Commission, Washington, DC 20555.
Telephone: (301) 415–8500; fax number:
(301) 415–8555; e-mail: cmr1@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
Portland General Electric Company
(PGE) is the licensee and holder of
License No. SNM–2509 for the Trojan
Independent Spent Fuel Storage Facility
(Trojan ISFSI). In addition, PGE holds
License No. NPF–1, pursuant to 10 CFR
part 50, for the Trojan Nuclear Plant.
The licensee will complete
decommissioning of the Trojan Nuclear
Plant and intends to terminate its Part
50 license for the Trojan Nuclear Plant.
PO 00000
Frm 00094
Fmt 4703
Sfmt 4703
15369
The Trojan ISFSI contains the spent fuel
removed from the Trojan Nuclear Plant.
Currently, the licensee provides
financial assurance for the Trojan ISFSI
pursuant to 10 CFR 72.30(c)(5), which
allows a part 50 license holder to use
the financial assurance provisions of
part 50 to provide financial assurance
for an ISFSI. The licensee maintains an
external sinking fund for
decommissioning funds pursuant to 10
CFR 50.75(e). However, when its part 50
license is terminated, it will no longer
meet the condition of 10 CFR 72.30(c)(5)
that allows it to use its existing external
sinking fund to provide financial
assurance for its ISFSI.
On April 29, 2004, PGE filed a request
for NRC approval of a partial exemption
from the provision of 10 CFR 72.30(c)(5)
that requires an ISFSI licensee to
additionally hold a part 50 license in
order to use an external sinking fund as
the exclusive means of financial
assurance for decommissioning costs of
an ISFSI.
II. Requested Action
Pursuant to the requirements of 10
CFR 72.7, PGE requested a partial
exemption from the financial assurance
requirements of 10 CFR 72.30(c)(5). The
exemption request was ‘‘partial’’
because it would apply only to the
requirement that the ISFSI licensee also
hold a Part 50 license to use an external
sinking fund as its exclusive method of
providing financial assurance for its
ISFSI. The licensee will continue to
provide financial assurance conforming
to the requirements of 10 CFR 50.75(e)
and (h), although it reserved the right to
change to another method as provided
in other sections of 10 CFR 72.30(c). The
licensee pointed out that the wording of
10 CFR 72.30(c)(5) allowed an ‘‘electric
utility’’ to use an external sinking fund
as the exclusive method of providing
financial assurance when its part 72
ISFSI license was first issued. However,
the rule was amended effective on
December 24, 2003, which resulted in
the change of the condition from
‘‘electric utility’’ to ‘‘a part 50 licensee.’’
PGE stated that it will remain an electric
utility after the termination of its part 50
license, hence it will continue to meet
the intent of the rule as originally
issued.
III. Discussion
The Commission may grant a specific
exemption to the financial assurance
requirements of 10 CFR 72.30(c)(5)
provided that the requirements of 10
CFR 72.7 are satisfied. The Commission
determined that a partial exemption
from 10 CFR 72.30(c)(5) meets the
E:\FR\FM\25MRN1.SGM
25MRN1
15370
Federal Register / Vol. 70, No. 57 / Friday, March 25, 2005 / Notices
requirements of 10 CFR 72.7, as
discussed below:
Specific Exemption Is Authorized by
Law
Prior to December 24, 2003, any ISFSI
licensee that met the definition of
‘‘electric utility’’ in 10 CFR 50.2 was
eligible to use the financial assurance
methods of 10 CFR 50.75(e) to provide
financial assurance for its ISFSI. As a
result, the NRC approved use of an
external sinking fund conforming to the
requirement of 10 CFR 50.75(e)(1)(ii)(A)
as financial assurance for the Trojan
ISFSI pursuant to 10 CFR 72.30(c)(5).
The amendment to 10 CFR 72.30(c)(5)
that became effective December 24,
2003, was incidental to the primary
changes in Part 50 issued at the same
time with regard to reactor
decommissioning trust funds. The
amendment to 10 CFR 72.30(c)(5) was in
response to a comment that suggested
the change to maintain consistency
between parts 72 and 50, but did not
change the basis of the regulations.
The basis of 10 CFR 50.75(e)(1)(ii)(A)
is that a licensee that recovers
decommissioning costs through rates
established through ‘‘cost of service’’ or
similar rate-making authority may use
an external sinking fund as its exclusive
means of financial assurance. A licensee
that is a public utility is presumed to
meet that basis. Because PGE will
remain a public utility after termination
of its part 50 license, it will continue to
meet the basis for allowing a part 72
licensee to provide financial assurance
using the methods of part 50. Therefore,
the partial exemption from part 72 is
authorized by law.
Specific Exemption Will Not Present an
Undue Risk to the Public Health and
Safety
The specific exemption requested is
administrative in nature. The exemption
does not have any reasonable potential
to (1) foreclose release of the Trojan
ISFSI site for unrestricted use; (2) result
in significant environmental impacts
not previously reviewed; or (3) result in
there no longer being reasonable
assurance that adequate funds will be
available for decommissioning. The
exemption will allow use of a financial
assurance method currently in use that
has been approved by the NRC.
Therefore, the partial exemption will
not present an undue risk to the public
health.
Specific Exemption Will Not Endanger
the Common Defense and Security
The partial exemption is
administrative in nature and does not
involve information of activities that
VerDate jul<14>2003
16:11 Mar 24, 2005
Jkt 205001
could potentially impact the common
defense and security of the United
States. Therefore, partial exemption will
not endanger the common defense and
security.
Specific Exemption Is Otherwise in the
Public Interest
PGE’s 2003 Annual Financial
Statement (Form 10–K, submitted to the
U.S. Securities and Exchange
Commission (SEC) on March 19, 2004)
stated that PGE will collect $14 million
annually, until 2011, from its customers
to pay for decommissioning. This
includes funding for radiological and
non-radiological decontamination as
well as on-site spent nuclear fuel
storage. Those collections will occur
whether or not the exemption is
granted. However, if the exemption is
not granted, PGE will incur higher costs
due to the expense of providing a
second independent financial assurance
instrument, which would lead to
unnecessary additional costs. Therefore,
the exemption is in the public interest.
Financial Ability of PGE To Fund the
ISFSI Decommissioning Cost
The Trojan ISFSI decommissioning
cost estimate was $7.9 million in 1997.
Adjusting for inflation to 2004 would
increase the cost to about $10 million.
In order to assess the ability of PGE to
finance that cost, the staff reviewed
PGE’s 2003 Form 10–K. The financial
statements show that PGE possesses
$3.37 billion in assets and earns $1.7
billion annually in revenues. The
financial report stated that PGE
maintained a strong financial position
with stable cash flow, and will receive
$14 million per year through 2011 for
decommissioning costs. The cost of
decommissioning the Trojan ISFSI
appears well within the licensee’s
financial ability.
At the time of filing its exemption
request, PGE was a wholly owned
subsidiary of Enron Corporation. The
staff determined that Enron’s
bankruptcy will not adversely affect
PGE’s ability to fund decommissioning
of its Trojan ISFSI. Although Enron filed
for bankruptcy protection, PGE did not.
Regulatory ‘‘ring-fencing’’ effectively
insulated PGE and its customers from
the effects of Enron’s bankruptcy. (Ring
fencing is a state public utility board’s
regulatory strategy that prevents a
utility’s assets from being pledged as
security for a parent company’s
obligations.) PGE’s Quarterly Report,
Form 10–Q, submitted to the SEC on
November 5, 2004, states on page 41:
PGE, as a separate corporation, owns or
leases the assets used in its business and
PGE’s management, separate from Enron, is
PO 00000
Frm 00095
Fmt 4703
Sfmt 4703
responsible for PGE’s day-to-day operations.
PGE maintains its own cash management
system and finances itself separately from
Enron, on both a short- and long-term basis.
Neither PGE nor Enron have guaranteed the
obligations of the other and there are no
loans between them. Under Oregon law and
specific conditions imposed on Enron and
PGE by the Oregon Public Utilities
Commission (OPUC) in connection with
Enron’s acquisition of PGE in the merger of
Enron and Portland General Corporation in
1997, Enron’s access to PGE cash or utility
assets (through dividends or otherwise) is
limited.
Therefore, PGE’s assets will be
available to provide funding for
decommissioning if it continues as an
Enron subsidiary. However, Enron
entered into an agreement with Oregon
Electric Utility Company, LLC, to sell all
issued and outstanding PGE stock to
Oregon Electric. In the event the sale is
consummated, the Enron bankruptcy
will be of no further concern.
IV. Conclusion
The Commission determined that the
specific exemption to the financial
assurance requirements of 10 CFR
72.30(c)(5) is authorized by law and will
not endanger life or property, or the
common defense and security and is
otherwise in the public interest.
In connection with the issuance of the
exemption, an Environmental
Assessment and Finding of No
Significant Impact was noticed in the
Federal Register on March 17, 2005 (70
FR 13052).
Therefore, the Commission grants a
partial exemption from the requirement
of 10 CFR 72.30(c)(5) that the licensee
must hold a part 50 license in order to
provide financial assurance using the
methods of 10 CFR 50.75(e) and (h);
however, the exemption is granted
subject to the following two conditions:
1. The exemption shall not become
effective until the licensee submits,
within 30 days of the issuance of this
grant of exemption, documentation
adequate to demonstrate that funding
for the Trojan ISFSI decommissioning
has been approved for recovery in rates
by a rate making authority; and
2. The exemption shall cease to be
effective in the event that funds
remaining to be placed into the Trojan
ISFSI decommissioning external sinking
fund are no longer approved for
recovery in rates by a competent rate
regulating authority.
This exemption is effective upon
satisfaction of Condition 1 above, and
shall cease being effective in the event
Condition 2 above is triggered.
FURTHER INFORMATION: Supporting
documentation, with respect to this
exemption request, is available for
E:\FR\FM\25MRN1.SGM
25MRN1
Federal Register / Vol. 70, No. 57 / Friday, March 25, 2005 / Notices
inspection at NRC’s Public Electronic
Reading Room at https://www.nrc.gov/
reading-rm/ADAMS.html. A copy of the
PGE request for NRC approval of a
partial exemption from the provision of
10 CFR 72.30(c)(5), dated April 29,
2004, can be found at this site using the
Agencywide Documents Access and
Management System (ADAMS)
accession No. ML041260470. Any
questions should be referred to
Christopher M. Regan, Spent Fuel
Project Office, Office of Nuclear
Material Safety and Safeguards, U.S.
Nuclear Regulatory Commission,
Washington, DC 20555, Mailstop O
13D13, telephone (301) 415–8500, fax
(301) 415–8555.
Dated at Rockville, Maryland this 17th day
of March, 2005.
For the Nuclear Regulatory Commission.
Christopher M. Regan,
Senior Project Manager, Licensing Section,
Spent Fuel Project Office, Office of Nuclear
Material Safety and Safeguards.
[FR Doc. 05–5901 Filed 3–24–05; 8:45 am]
BILLING CODE 7590–01–P
NUCLEAR REGULATORY
COMMISSION
Notice of Availability of Interim Staff
Guidance Documents For Fuel Cycle
Facilities
Nuclear Regulatory
Commission.
ACTION: Notice of availability.
AGENCY:
FOR FURTHER INFORMATION CONTACT:
Wilkins Smith, Project Manager,
Technical Support Group, Division of
Fuel Cycle Safety and Safeguards, Office
of Nuclear Material Safety and
Safeguards, U.S. Nuclear Regulatory
Commission, Washington, DC 20005–
0001. Telephone: (301) 415–5788; fax
number: (301) 415–5370; e-mail:
wrs@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Introduction
The Nuclear Regulatory Commission
(NRC) is preparing and issuing Interim
Staff Guidance (ISG) documents for fuel
cycle facilities. These ISG documents
provide clarifying guidance to the NRC
staff when reviewing licensee integrated
safety analyses, license applications or
amendment requests or other related
licensing activities for fuel cycle
facilities under subpart H of 10 CFR part
70. The NRC is soliciting public
comments on two ISG Draft documents
(ISG–01 and –04) which will be
considered in the final versions or
subsequent revisions. ISG–03 has been
issued and is provided for information.
VerDate jul<14>2003
16:11 Mar 24, 2005
Jkt 205001
II. Summary
The purpose of this notice is to
provide the public an opportunity to
review and comment on the Interim
Staff Guidance documents for fuel cycle
facilities. Draft Interim Staff Guidance–
01, Version 02, provides guidance to
NRC staff relative to methods for
qualitative evaluation of likelihood in
the context of a review of a license
application or amendment request
under 10 CFR part 70, subpart H. ISG–
01, Version 02, has been generally
revised based on NRC staff and public
comments on the initial version. Interim
Staff Guidance–03, Revision 0 has been
approved and issued and provides
guidance to NRC staff relative to
relationships between 10 CFR part 70,
subpart H, nuclear criticality safety
performance requirements and the
double contingency principle. Draft
Interim Staff Guidance–04, Version 0
provides guidance to NRC staff relative
to baseline design criteria for new
facilities and new processes at existing
facilities.
III. Further Information
Documents related to this action are
available electronically at the NRC’s
Electronic Reading Room at https://
www.nrc.gov/reading-rm/adams.html.
From this site, you can access the NRC’s
Agencywide Document Access and
Management System (ADAMS), which
provides text and image files of NRC’s
public documents. The ADAMS
accession numbers for the documents
related to this notice are provided in the
following table. If you do not have
access to ADAMS or if there are
problems in accessing the documents
located in ADAMS, contact the NRC
Public Document Room (PDR) Reference
staff at 1–800–397–4209, 301–415–4737,
or by e-mail to pdr@nrc.gov.
Interim staff guidance
Interim Staff Guidance–01, Version
02.
Interim Staff Guidance–03, Revision
0.
Interim Staff Guidance–04, Version 0.
ADAMS accession
number
ML050690286.
ML050690302.
ML050690296.
These documents may also be viewed
electronically on the public computers
located at the NRC’s PDR, O 1 F21, One
White Flint North, 11555 Rockville
Pike, Rockville, MD 20852. The PDR
reproduction contractor will copy
documents for a fee. Comments and
questions on ISG–01 and ISG–04 should
be directed to the NRC contact listed
below by April 25, 2005. Comments
PO 00000
Frm 00096
Fmt 4703
Sfmt 4703
15371
received after this date will be
considered if it is practical to do so, but
assurance of consideration cannot be
given to comments received after this
date. Wilkins Smith, Project Manager,
Technical Support Group, Division of
Fuel Cycle Safety and Safeguards, Office
of Nuclear Material Safety and
Safeguards, U.S. Nuclear Regulatory
Commission, Washington, DC 20005–
0001. Comments can also be submitted
by telephone, fax, or e-mail which are
as follows: Telephone: (301) 415–5788;
fax number: (301) 415–5370; e-mail:
wrs@nrc.gov.
Dated in Rockville, Maryland this 18th day
of March, 2005.
For the Nuclear Regulatory Commission.
David H. Tiktinsky,
Acting Chief, Technical Support Group,
Division of Fuel Cycle Safety and Safeguards,
Office of Nuclear Material Safety and
Safeguards.
[FR Doc. 05–5902 Filed 3–24–05; 8:45 am]
BILLING CODE 7590–01–P
SECURITIES AND EXCHANGE
COMMISSION
Sunshine Act Meetings
Notice is hereby given, pursuant to
the provisions of the Government in the
Sunshine Act, Pub. L. 94–409, that the
Securities and Exchange Commission
will hold the following meetings during
the week of March 28, 2005:
An open meeting will be held on
Tuesday, March 29, 2005, at 10 a.m. in
Room 1C30 and closed meetings will be
held on Tuesday, March 29, 2005, at 11
a.m. and Thursday, March 31, 2005, at
2 p.m.
Commissioners, Counsel to the
Commissioners, the Secretary to the
Commission, and recording secretaries
will attend the closed meeting. Certain
staff members who have an interest in
the matters may also be present.
The General Counsel of the
Commission, or his designee, has
certified that, in his opinion, one or
more of the exemptions set forth in 5
U.S.C. 552b(c)(3), (5), (7), (9)(B), and
(10) and 17 CFR 200.402(a)(3), (5), (7),
9(ii) and (10), permit consideration of
the scheduled matters at the closed
meeting.
Commissioner Goldschmid, as duty
officer, voted to consider the items
listed for the closed meeting in closed
session.
The subject matter of the open
meeting scheduled for Tuesday, March
29, 2005, will be:
The Commission will hear oral argument
on appeals by Robert W. Armstrong, III and
E:\FR\FM\25MRN1.SGM
25MRN1
Agencies
[Federal Register Volume 70, Number 57 (Friday, March 25, 2005)]
[Notices]
[Pages 15369-15371]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-5901]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 72-17]
Notice of Issuance of Partial Conditional Exemption; Portland
General Electric Company, Trojan Independent Spent Fuel Storage
Facility
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of partial conditional exemption.
-----------------------------------------------------------------------
FOR FURTHER INFORMATION CONTACT: Christopher M. Regan, Senior Project
Manager, Spent Fuel Project Office, Office of Nuclear Material Safety
and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC
20555. Telephone: (301) 415-8500; fax number: (301) 415-8555; e-mail:
cmr1@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Background
Portland General Electric Company (PGE) is the licensee and holder
of License No. SNM-2509 for the Trojan Independent Spent Fuel Storage
Facility (Trojan ISFSI). In addition, PGE holds License No. NPF-1,
pursuant to 10 CFR part 50, for the Trojan Nuclear Plant. The licensee
will complete decommissioning of the Trojan Nuclear Plant and intends
to terminate its Part 50 license for the Trojan Nuclear Plant. The
Trojan ISFSI contains the spent fuel removed from the Trojan Nuclear
Plant.
Currently, the licensee provides financial assurance for the Trojan
ISFSI pursuant to 10 CFR 72.30(c)(5), which allows a part 50 license
holder to use the financial assurance provisions of part 50 to provide
financial assurance for an ISFSI. The licensee maintains an external
sinking fund for decommissioning funds pursuant to 10 CFR 50.75(e).
However, when its part 50 license is terminated, it will no longer meet
the condition of 10 CFR 72.30(c)(5) that allows it to use its existing
external sinking fund to provide financial assurance for its ISFSI.
On April 29, 2004, PGE filed a request for NRC approval of a
partial exemption from the provision of 10 CFR 72.30(c)(5) that
requires an ISFSI licensee to additionally hold a part 50 license in
order to use an external sinking fund as the exclusive means of
financial assurance for decommissioning costs of an ISFSI.
II. Requested Action
Pursuant to the requirements of 10 CFR 72.7, PGE requested a
partial exemption from the financial assurance requirements of 10 CFR
72.30(c)(5). The exemption request was ``partial'' because it would
apply only to the requirement that the ISFSI licensee also hold a Part
50 license to use an external sinking fund as its exclusive method of
providing financial assurance for its ISFSI. The licensee will continue
to provide financial assurance conforming to the requirements of 10 CFR
50.75(e) and (h), although it reserved the right to change to another
method as provided in other sections of 10 CFR 72.30(c). The licensee
pointed out that the wording of 10 CFR 72.30(c)(5) allowed an
``electric utility'' to use an external sinking fund as the exclusive
method of providing financial assurance when its part 72 ISFSI license
was first issued. However, the rule was amended effective on December
24, 2003, which resulted in the change of the condition from ``electric
utility'' to ``a part 50 licensee.'' PGE stated that it will remain an
electric utility after the termination of its part 50 license, hence it
will continue to meet the intent of the rule as originally issued.
III. Discussion
The Commission may grant a specific exemption to the financial
assurance requirements of 10 CFR 72.30(c)(5) provided that the
requirements of 10 CFR 72.7 are satisfied. The Commission determined
that a partial exemption from 10 CFR 72.30(c)(5) meets the
[[Page 15370]]
requirements of 10 CFR 72.7, as discussed below:
Specific Exemption Is Authorized by Law
Prior to December 24, 2003, any ISFSI licensee that met the
definition of ``electric utility'' in 10 CFR 50.2 was eligible to use
the financial assurance methods of 10 CFR 50.75(e) to provide financial
assurance for its ISFSI. As a result, the NRC approved use of an
external sinking fund conforming to the requirement of 10 CFR
50.75(e)(1)(ii)(A) as financial assurance for the Trojan ISFSI pursuant
to 10 CFR 72.30(c)(5).
The amendment to 10 CFR 72.30(c)(5) that became effective December
24, 2003, was incidental to the primary changes in Part 50 issued at
the same time with regard to reactor decommissioning trust funds. The
amendment to 10 CFR 72.30(c)(5) was in response to a comment that
suggested the change to maintain consistency between parts 72 and 50,
but did not change the basis of the regulations.
The basis of 10 CFR 50.75(e)(1)(ii)(A) is that a licensee that
recovers decommissioning costs through rates established through ``cost
of service'' or similar rate-making authority may use an external
sinking fund as its exclusive means of financial assurance. A licensee
that is a public utility is presumed to meet that basis. Because PGE
will remain a public utility after termination of its part 50 license,
it will continue to meet the basis for allowing a part 72 licensee to
provide financial assurance using the methods of part 50. Therefore,
the partial exemption from part 72 is authorized by law.
Specific Exemption Will Not Present an Undue Risk to the Public Health
and Safety
The specific exemption requested is administrative in nature. The
exemption does not have any reasonable potential to (1) foreclose
release of the Trojan ISFSI site for unrestricted use; (2) result in
significant environmental impacts not previously reviewed; or (3)
result in there no longer being reasonable assurance that adequate
funds will be available for decommissioning. The exemption will allow
use of a financial assurance method currently in use that has been
approved by the NRC. Therefore, the partial exemption will not present
an undue risk to the public health.
Specific Exemption Will Not Endanger the Common Defense and Security
The partial exemption is administrative in nature and does not
involve information of activities that could potentially impact the
common defense and security of the United States. Therefore, partial
exemption will not endanger the common defense and security.
Specific Exemption Is Otherwise in the Public Interest
PGE's 2003 Annual Financial Statement (Form 10-K, submitted to the
U.S. Securities and Exchange Commission (SEC) on March 19, 2004) stated
that PGE will collect $14 million annually, until 2011, from its
customers to pay for decommissioning. This includes funding for
radiological and non-radiological decontamination as well as on-site
spent nuclear fuel storage. Those collections will occur whether or not
the exemption is granted. However, if the exemption is not granted, PGE
will incur higher costs due to the expense of providing a second
independent financial assurance instrument, which would lead to
unnecessary additional costs. Therefore, the exemption is in the public
interest.
Financial Ability of PGE To Fund the ISFSI Decommissioning Cost
The Trojan ISFSI decommissioning cost estimate was $7.9 million in
1997. Adjusting for inflation to 2004 would increase the cost to about
$10 million. In order to assess the ability of PGE to finance that
cost, the staff reviewed PGE's 2003 Form 10-K. The financial statements
show that PGE possesses $3.37 billion in assets and earns $1.7 billion
annually in revenues. The financial report stated that PGE maintained a
strong financial position with stable cash flow, and will receive $14
million per year through 2011 for decommissioning costs. The cost of
decommissioning the Trojan ISFSI appears well within the licensee's
financial ability.
At the time of filing its exemption request, PGE was a wholly owned
subsidiary of Enron Corporation. The staff determined that Enron's
bankruptcy will not adversely affect PGE's ability to fund
decommissioning of its Trojan ISFSI. Although Enron filed for
bankruptcy protection, PGE did not. Regulatory ``ring-fencing''
effectively insulated PGE and its customers from the effects of Enron's
bankruptcy. (Ring fencing is a state public utility board's regulatory
strategy that prevents a utility's assets from being pledged as
security for a parent company's obligations.) PGE's Quarterly Report,
Form 10-Q, submitted to the SEC on November 5, 2004, states on page 41:
PGE, as a separate corporation, owns or leases the assets used
in its business and PGE's management, separate from Enron, is
responsible for PGE's day-to-day operations. PGE maintains its own
cash management system and finances itself separately from Enron, on
both a short- and long-term basis. Neither PGE nor Enron have
guaranteed the obligations of the other and there are no loans
between them. Under Oregon law and specific conditions imposed on
Enron and PGE by the Oregon Public Utilities Commission (OPUC) in
connection with Enron's acquisition of PGE in the merger of Enron
and Portland General Corporation in 1997, Enron's access to PGE cash
or utility assets (through dividends or otherwise) is limited.
Therefore, PGE's assets will be available to provide funding for
decommissioning if it continues as an Enron subsidiary. However, Enron
entered into an agreement with Oregon Electric Utility Company, LLC, to
sell all issued and outstanding PGE stock to Oregon Electric. In the
event the sale is consummated, the Enron bankruptcy will be of no
further concern.
IV. Conclusion
The Commission determined that the specific exemption to the
financial assurance requirements of 10 CFR 72.30(c)(5) is authorized by
law and will not endanger life or property, or the common defense and
security and is otherwise in the public interest.
In connection with the issuance of the exemption, an Environmental
Assessment and Finding of No Significant Impact was noticed in the
Federal Register on March 17, 2005 (70 FR 13052).
Therefore, the Commission grants a partial exemption from the
requirement of 10 CFR 72.30(c)(5) that the licensee must hold a part 50
license in order to provide financial assurance using the methods of 10
CFR 50.75(e) and (h); however, the exemption is granted subject to the
following two conditions:
1. The exemption shall not become effective until the licensee
submits, within 30 days of the issuance of this grant of exemption,
documentation adequate to demonstrate that funding for the Trojan ISFSI
decommissioning has been approved for recovery in rates by a rate
making authority; and
2. The exemption shall cease to be effective in the event that
funds remaining to be placed into the Trojan ISFSI decommissioning
external sinking fund are no longer approved for recovery in rates by a
competent rate regulating authority.
This exemption is effective upon satisfaction of Condition 1 above,
and shall cease being effective in the event Condition 2 above is
triggered.
Further Information: Supporting documentation, with respect to this
exemption request, is available for
[[Page 15371]]
inspection at NRC's Public Electronic Reading Room at https://
www.nrc.gov/reading-rm/ADAMS.html. A copy of the PGE request for NRC
approval of a partial exemption from the provision of 10 CFR
72.30(c)(5), dated April 29, 2004, can be found at this site using the
Agencywide Documents Access and Management System (ADAMS) accession No.
ML041260470. Any questions should be referred to Christopher M. Regan,
Spent Fuel Project Office, Office of Nuclear Material Safety and
Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 20555,
Mailstop O 13D13, telephone (301) 415-8500, fax (301) 415-8555.
Dated at Rockville, Maryland this 17th day of March, 2005.
For the Nuclear Regulatory Commission.
Christopher M. Regan,
Senior Project Manager, Licensing Section, Spent Fuel Project Office,
Office of Nuclear Material Safety and Safeguards.
[FR Doc. 05-5901 Filed 3-24-05; 8:45 am]
BILLING CODE 7590-01-P