Agency Information Collection Activities Under OMB Review, 13237-13239 [E5-1198]

Download as PDF Federal Register / Vol. 70, No. 52 / Friday, March 18, 2005 / Notices FOR FURTHER INFORMATION CONTACT: ACTION: Nancy J. Kessinger at (202) 273–7079 or FAX (202) 275–5947. SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104–13; 44 U.S.C. 3501–3521), Federal agencies must obtain approval from the Office of Management and Budget (OMB) for each collection of information they conduct or sponsor. This request for comment is being made pursuant to section 3506(c)(2)(A) of the PRA. With respect to the following collection of information, VBA invites comments on: (1) Whether the proposed collection of information is necessary for the proper performance of VBA’s functions, including whether the information will have practical utility; (2) the accuracy of VBA’s estimate of the burden of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including through the use of automated collection techniques or the use of other forms of information technology. Title: Request for Supplemental Information on Medical and Nonmedical Applications, VA Form Letter 29–615. OMB Control Number: 2900–0131. Type of Review: Extension of a currently approved collection. Abstract: VA Form 29–615 used by the insured to apply for new issue, reinstatement or change of plan on Government Life Insurance policies. Affected Public: Individuals or households. Estimated Annual Burden: 3,000 hours. Estimated Average Burden Per Respondent: 20 minutes. Frequency of Response: On occasion. Estimated Number of Respondents: 9,000. Dated: March 11, 2005. By direction of the Secretary. Loise Russell, Director, Records Management Service. [FR Doc. E5–1196 Filed 3–17–05; 8:45 am] BILLING CODE 8320–01–P DEPARTMENT OF VETERANS AFFAIRS [OMB Control No. 2900–0024] Proposed Information Collection Activity: Proposed Collection; Comment Request Veterans Benefits Administration, Department of Veterans Affairs. AGENCY: VerDate jul<14>2003 16:14 Mar 17, 2005 Jkt 205001 Notice. SUMMARY: The Veterans Benefits Administration (VBA), Department of Veterans Affairs (VA), is announcing an opportunity for public comment on the proposed collection of certain information by the agency. Under the Paperwork Reduction Act (PRA) of 1995, Federal agencies are required to publish notice in the Federal Register concerning each proposed collection of information, including each proposed extension of a currently approved collection, and allow 60 days for public comment in response to the notice. This notice solicits comments for information needed to authorize VA to deduct premiums, loans and/or lien payment. DATES: Written comments and recommendations on the proposed collection of information should be received on or before May 17, 2005. ADDRESSES: Submit written comments on the collection of information to Nancy J. Kessinger, Veterans Benefits Administration (20S52), Department of Veterans Affairs, 810 Vermont Avenue, NW., Washington, DC 20420 or e-mail: irmnkess@vba.va.gov. Please refer to ‘‘OMB Control No. 2900–0024’’ in any correspondence. FOR FURTHER INFORMATION CONTACT: Nancy J. Kessinger at (202) 273–7079 or FAX (202) 275–5947. SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104–13; 44 U.S.C. 3501–3521), Federal agencies must obtain approval from the Office of Management and Budget (OMB) for each collection of information they conduct or sponsor. This request for comment is being made pursuant to Section 3506(c)(2)(A) of the PRA. With respect to the following collection of information, VBA invites comments on: (1) Whether the proposed collection of information is necessary for the proper performance of VBA’s functions, including whether the information will have practical utility; (2) the accuracy of VBA’s estimate of the burden of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including through the use of automated collection techniques or the use of other forms of information technology. Title: Insurance Deduction Authorization (For Deduction from Benefit Payments), VA Form 29–888. OMB Control Number: 2900–0024. Type of Review: Extension of a currently approved collection. PO 00000 Frm 00079 Fmt 4703 Sfmt 4703 13237 Abstract: VA Form 29–888 is completed by the insured or their representative to authorize VA to deduct payment for premiums, loans and/or liens on his or her insurance contract from their VA compensation check. Affected Public: Individuals or households. Estimated Annual Burden: 622 hours. Estimated Average Burden Per Respondent: 10 minutes. Frequency of Response: On occasion. Estimated Number of Respondents: 3,732. Dated: March 11, 2005. By direction of the Secretary. Loise Russell, Director, Records Management Service. [FR Doc. E5–1197 Filed 3–17–05; 8:45 am] BILLING CODE 8320–01–P DEPARTMENT OF VETERANS AFFAIRS [OMB Control No. 2900–0422] Agency Information Collection Activities Under OMB Review Office of Management, Department of Veterans Affairs. ACTION: Notice. AGENCY: SUMMARY: In compliance with the Paperwork Reduction Act (PRA) of 1995 (44 U.S.C., 3501–3521), this notice announces that the Office of Management (OM), Department of Veterans Affairs, has submitted the collection of information abstracted below to the Office of Management and Budget (OMB) for review and comment. The PRA submission describes the nature of the information collection and its expected cost and burden; it includes the actual data collection instrument. DATES: Comments must be submitted on or before April 18, 2005. FOR FURTHER INFORMATION OR A COPY OF THE SUBMISSION CONTACT: Denise McLamb, Information Management Service (005E3), Department of Veterans Affairs, 810 Vermont Avenue, NW., Washington, DC 20420, (202) 273–8030 or FAX (202) 273–5981. Please refer to ‘‘OMB Control No. 2900–0422.’’ Send comments and recommendations concerning any aspect of the information collection to VA’s Desk Officer, OMB Human Resources and Housing Branch, New Executive Office Building, Room 10235, Washington, DC 20503 (202) 395–7316. Please refer to ‘‘OMB Control No. 2900– 0422’’ in any correspondence. SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104–13; 44 U.S.C. 3501–21), Federal agencies must obtain E:\FR\FM\18MRN1.SGM 18MRN1 13238 Federal Register / Vol. 70, No. 52 / Friday, March 18, 2005 / Notices approval from the Office of Management and Budget (OMB) for each collection of information they conduct or sponsor. This request for comment is being made pursuant to Section 3506(c)(2)(A) of the PRA. With respect to the following collection of information, (OM) invites comments on: (1) Whether the proposed collection of information is necessary for the proper performance of (OM)’s functions, including whether the information will have practical utility; (2) the accuracy of (OM)’s estimate of the burden of the proposed collection of information; (3) ways to enhance the quality, utility, and clarity of the information to be collected; and (4) ways to minimize the burden of the collection of information on respondents, including through the use of automated collection techniques or the use of other forms of information technology. Titles a. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–72, Performance of Work by the Contractor. b. Department of Veterans Affairs Acquisition Regulation (VAAR) Alternate I to Clause 852.236–80, Subcontracts and Work Coordination. c. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–82, Payments Under FixedPrice Construction Contracts (without NAS), including Alternate 1. d. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–83, Payments Under FixedPrice Construction Contracts (with NAS), including Alternate 1. e. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–84, Schedule of Work Progress. f. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes. OMB Control Number: 2900–0422. Type of Review: Extension of a currently approved collection. Abstract The information contained Department of Veterans Acquisition Regulation (VAAR) Clauses 852.236–72, Alternate I to 852.236–80, 852.236–82, 852.236–83, 852.236–84, and 852.236– 88 is necessary for VA to administer construction contracts, and to carry out its responsibility to construct, maintain and repair real property for the Department. a. VAAR Clause 852.236–72, Performance of Work by the Contractor, VerDate jul<14>2003 16:14 Mar 17, 2005 Jkt 205001 requires contractors awarded a construction contract containing Federal Acquisition Regulation (FAR) clause 52.236–1, to submit a statement designating the branch or branches of contract work to be performed by the contractor’s own forces. The VAAR clause implements the FAR clause by requiring the contractor to provide information to the contracting officer on how the contractor intends to fulfill this contractual obligation. The contracting officer uses this information to ensure that the contractor complies with the contract requirements. b. Alternate I to Clause 852.236–80, Work Coordination, requires construction contractors, on contracts involving complex mechanicalelectrical work, to furnish coordination drawings showing the manner in which utility lines will fit into available spaces and relate to each other and to the existing building elements. The information is used by the contracting officer and VA engineer assigned to the project to resolve any problems relating to the installation of utilities on construction contract. c. VAAR Clause 852.236–82, Payments Under Fixed-Price Construction Contracts (without NAS), requires construction contractors to submit a schedule of costs for work to be performed under the contract. If the contract includes guarantee period services, Alternate I requires contractor to submit information on the total and itemized costs of the guarantee period services and to submit a performance plan/program. The information is needed to allow the contracting officer to determine the correct amount to pay the contractor as work progresses and to properly proportion the amount paid for guarantee period services. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), requires construction contractors to submit a schedule of costs for work to be performed under the contract. If the contract includes guarantee period services, Alternate I requires contractor to submit information on the total and itemized costs of the guarantee period services and to submit a performance plan/program. The information is needed to allow the contracting officer to determine the correct amount to pay the contractor as work progresses and to properly proportion the amount paid for guarantee period services. The difference between this clause and the one above 852.236–82 is that this clause requires the contractor to use a computerized Network Analysis System (NAS) to prepare the cost estimate. PO 00000 Frm 00080 Fmt 4703 Sfmt 4703 e. VAAR Clause 852.236–84, Schedule of Work Progress, requires construction contractors, on contracts that do not require the use of a NAS, to submit a progress schedule. The information is used by the contracting officer to track the contractor’s progress under the contract and to determine whether or not the contractor is making satisfactory progress. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes. FAR Clause 52.243– 4 authorizes the contracting officer to order changes to a construction contract but does not specifically require the contractor to submit cost proposals for those changes. VAAR Clause 852.236– 88 requires contractors to submit cost proposal for changes ordered by the contracting officer or for changes proposed by the contractor. This information is needed to allow the contracting officer and the contractor to reach a mutually acceptable agreement on how much to pay the contractor for the proposed changes to the contract. It is also used by the contracting officer to determine whether or not to authorize the proposed changes or whether or not additional or alternate cost proposals for changes are needed. An agency may not conduct or sponsor, and a person is not required to respond to a collection of information unless it displays a currently valid OMB control number. The Federal Register Notice with a 60-day comment period soliciting comments on this collection of information was published on December 23, 2004, at pages 76975– 76976. Affected Public: Business or other forprofit, Individuals and households, Notfor-profit institutions. Estimated Annual Burden a. VAAR Clause 852.236–72, Performance of Work by the Contractor—36 hours. b. VAAR Alternate I to Clause 852.236–80, Subcontracts and Work Coordination—1,190 hours. c. VAAR Clause 852.236–82, Payments Under Fixed-Price Construction Contracts (without NAS), including Alternate 1—1,397. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), including Alternate 1—59 hours. e. VAAR Clause 852.236–84, Schedule of Work Progress—2,095 hours. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes—807 hours. E:\FR\FM\18MRN1.SGM 18MRN1 Federal Register / Vol. 70, No. 52 / Friday, March 18, 2005 / Notices Estimated Annual Burden Per Respondent a. VAAR Clause 852.236–72, Performance of Work by the Contractor—1 hour. b. VAAR Alternate I to Clause 852.236–80, Subcontracts and Work Coordination—10 hours. c. VAAR Clause 852.236–82, Payments Under Fixed-Price Construction Contracts (without NAS), including Alternate 1—1 hour. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), including Alternate 1—30 minutes. VerDate jul<14>2003 16:14 Mar 17, 2005 Jkt 205001 e. VAAR Clause 852.236–84, Schedule of Work Progress—1 hour. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes—3 hours. Frequency of Response: On occasion. Estimated Number of Respondents a. VAAR Clause 852.236–72, Performance of Work by the Contractor—36. b. VAAR Alternate I to Clause 852.236–80, Subcontracts and Work Coordination—119. c. Department of Veterans Affairs Acquisition Regulation (VAAR) Clause 852.236–82, Payments Under Fixed- PO 00000 Frm 00081 Fmt 4703 Sfmt 4703 13239 Price Construction Contracts (without NAS), including Alternate 1—1,397. d. VAAR Clause 852.236–83, Payments Under Fixed-Price Construction Contracts (with NAS), including Alternate 1—119. e. VAAR Clause 852.236–84, Schedule of Work Progress—1,397. f. VAAR Clause 852.236–88, Contract Changes, Supplements FAR Clause 52.243–4, Changes—269. Dated: March 10, 2005. By direction of the Secretary. Loise Russell, Director, Records Management Service. [FR Doc. E5–1198 Filed 3–17–05; 8:45 am] BILLING CODE 8320–01–P E:\FR\FM\18MRN1.SGM 18MRN1

Agencies

[Federal Register Volume 70, Number 52 (Friday, March 18, 2005)]
[Notices]
[Pages 13237-13239]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-1198]


-----------------------------------------------------------------------

DEPARTMENT OF VETERANS AFFAIRS

[OMB Control No. 2900-0422]


Agency Information Collection Activities Under OMB Review

AGENCY: Office of Management, Department of Veterans Affairs.

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: In compliance with the Paperwork Reduction Act (PRA) of 1995 
(44 U.S.C., 3501-3521), this notice announces that the Office of 
Management (OM), Department of Veterans Affairs, has submitted the 
collection of information abstracted below to the Office of Management 
and Budget (OMB) for review and comment. The PRA submission describes 
the nature of the information collection and its expected cost and 
burden; it includes the actual data collection instrument.

DATES: Comments must be submitted on or before April 18, 2005.

FOR FURTHER INFORMATION OR A COPY OF THE SUBMISSION CONTACT: Denise 
McLamb, Information Management Service (005E3), Department of Veterans 
Affairs, 810 Vermont Avenue, NW., Washington, DC 20420, (202) 273-8030 
or FAX (202) 273-5981. Please refer to ``OMB Control No. 2900-0422.''
    Send comments and recommendations concerning any aspect of the 
information collection to VA's Desk Officer, OMB Human Resources and 
Housing Branch, New Executive Office Building, Room 10235, Washington, 
DC 20503 (202) 395-7316. Please refer to ``OMB Control No. 2900-0422'' 
in any correspondence.

SUPPLEMENTARY INFORMATION: Under the PRA of 1995 (Pub. L. 104-13; 44 
U.S.C. 3501-21), Federal agencies must obtain

[[Page 13238]]

approval from the Office of Management and Budget (OMB) for each 
collection of information they conduct or sponsor. This request for 
comment is being made pursuant to Section 3506(c)(2)(A) of the PRA.
    With respect to the following collection of information, (OM) 
invites comments on: (1) Whether the proposed collection of information 
is necessary for the proper performance of (OM)'s functions, including 
whether the information will have practical utility; (2) the accuracy 
of (OM)'s estimate of the burden of the proposed collection of 
information; (3) ways to enhance the quality, utility, and clarity of 
the information to be collected; and (4) ways to minimize the burden of 
the collection of information on respondents, including through the use 
of automated collection techniques or the use of other forms of 
information technology.

Titles

    a. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-72, Performance of Work by the Contractor.
    b. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Alternate I to Clause 852.236-80, Subcontracts and Work Coordination.
    c. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-82, Payments Under Fixed-Price Construction Contracts 
(without NAS), including Alternate 1.
    d. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-83, Payments Under Fixed-Price Construction Contracts 
(with NAS), including Alternate 1.
    e. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-84, Schedule of Work Progress.
    f. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-88, Contract Changes, Supplements FAR Clause 52.243-4, 
Changes.
    OMB Control Number: 2900-0422.
    Type of Review: Extension of a currently approved collection.

Abstract

    The information contained Department of Veterans Acquisition 
Regulation (VAAR) Clauses 852.236-72, Alternate I to 852.236-80, 
852.236-82, 852.236-83, 852.236-84, and 852.236-88 is necessary for VA 
to administer construction contracts, and to carry out its 
responsibility to construct, maintain and repair real property for the 
Department.
    a. VAAR Clause 852.236-72, Performance of Work by the Contractor, 
requires contractors awarded a construction contract containing Federal 
Acquisition Regulation (FAR) clause 52.236-1, to submit a statement 
designating the branch or branches of contract work to be performed by 
the contractor's own forces. The VAAR clause implements the FAR clause 
by requiring the contractor to provide information to the contracting 
officer on how the contractor intends to fulfill this contractual 
obligation. The contracting officer uses this information to ensure 
that the contractor complies with the contract requirements.
    b. Alternate I to Clause 852.236-80, Work Coordination, requires 
construction contractors, on contracts involving complex mechanical-
electrical work, to furnish coordination drawings showing the manner in 
which utility lines will fit into available spaces and relate to each 
other and to the existing building elements. The information is used by 
the contracting officer and VA engineer assigned to the project to 
resolve any problems relating to the installation of utilities on 
construction contract.
    c. VAAR Clause 852.236-82, Payments Under Fixed-Price Construction 
Contracts (without NAS), requires construction contractors to submit a 
schedule of costs for work to be performed under the contract. If the 
contract includes guarantee period services, Alternate I requires 
contractor to submit information on the total and itemized costs of the 
guarantee period services and to submit a performance plan/program. The 
information is needed to allow the contracting officer to determine the 
correct amount to pay the contractor as work progresses and to properly 
proportion the amount paid for guarantee period services.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), requires construction contractors to submit a 
schedule of costs for work to be performed under the contract. If the 
contract includes guarantee period services, Alternate I requires 
contractor to submit information on the total and itemized costs of the 
guarantee period services and to submit a performance plan/program. The 
information is needed to allow the contracting officer to determine the 
correct amount to pay the contractor as work progresses and to properly 
proportion the amount paid for guarantee period services. The 
difference between this clause and the one above 852.236-82 is that 
this clause requires the contractor to use a computerized Network 
Analysis System (NAS) to prepare the cost estimate.
    e. VAAR Clause 852.236-84, Schedule of Work Progress, requires 
construction contractors, on contracts that do not require the use of a 
NAS, to submit a progress schedule. The information is used by the 
contracting officer to track the contractor's progress under the 
contract and to determine whether or not the contractor is making 
satisfactory progress.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes. FAR Clause 52.243-4 authorizes the contracting 
officer to order changes to a construction contract but does not 
specifically require the contractor to submit cost proposals for those 
changes. VAAR Clause 852.236-88 requires contractors to submit cost 
proposal for changes ordered by the contracting officer or for changes 
proposed by the contractor. This information is needed to allow the 
contracting officer and the contractor to reach a mutually acceptable 
agreement on how much to pay the contractor for the proposed changes to 
the contract. It is also used by the contracting officer to determine 
whether or not to authorize the proposed changes or whether or not 
additional or alternate cost proposals for changes are needed.
    An agency may not conduct or sponsor, and a person is not required 
to respond to a collection of information unless it displays a 
currently valid OMB control number. The Federal Register Notice with a 
60-day comment period soliciting comments on this collection of 
information was published on December 23, 2004, at pages 76975-76976.
    Affected Public: Business or other for-profit, Individuals and 
households, Not-for-profit institutions.

Estimated Annual Burden

    a. VAAR Clause 852.236-72, Performance of Work by the Contractor--
36 hours.
    b. VAAR Alternate I to Clause 852.236-80, Subcontracts and Work 
Coordination--1,190 hours.
    c. VAAR Clause 852.236-82, Payments Under Fixed-Price Construction 
Contracts (without NAS), including Alternate 1--1,397.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), including Alternate 1--59 hours.
    e. VAAR Clause 852.236-84, Schedule of Work Progress--2,095 hours.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes--807 hours.

[[Page 13239]]

Estimated Annual Burden Per Respondent

    a. VAAR Clause 852.236-72, Performance of Work by the Contractor--1 
hour.
    b. VAAR Alternate I to Clause 852.236-80, Subcontracts and Work 
Coordination--10 hours.
    c. VAAR Clause 852.236-82, Payments Under Fixed-Price Construction 
Contracts (without NAS), including Alternate 1--1 hour.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), including Alternate 1--30 minutes.
    e. VAAR Clause 852.236-84, Schedule of Work Progress--1 hour.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes--3 hours.
    Frequency of Response: On occasion.

Estimated Number of Respondents

    a. VAAR Clause 852.236-72, Performance of Work by the Contractor--
36.
    b. VAAR Alternate I to Clause 852.236-80, Subcontracts and Work 
Coordination--119.
    c. Department of Veterans Affairs Acquisition Regulation (VAAR) 
Clause 852.236-82, Payments Under Fixed-Price Construction Contracts 
(without NAS), including Alternate 1--1,397.
    d. VAAR Clause 852.236-83, Payments Under Fixed-Price Construction 
Contracts (with NAS), including Alternate 1--119.
    e. VAAR Clause 852.236-84, Schedule of Work Progress--1,397.
    f. VAAR Clause 852.236-88, Contract Changes, Supplements FAR Clause 
52.243-4, Changes--269.

    Dated: March 10, 2005.

    By direction of the Secretary.
Loise Russell,
Director, Records Management Service.
[FR Doc. E5-1198 Filed 3-17-05; 8:45 am]
BILLING CODE 8320-01-P