Invenergy Cannon Falls LLC, et al.; Electric Rate and Corporate Filings, 12672-12674 [E5-1095]
Download as PDF
12672
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
regarding MGE’s updated market power
analysis filed on November 9, 2004 in
Docket No. ER00–586–003, as amended
November 15, 2004 in Docket No. ER00–
586–004.
Comment Date: 5 p.m. eastern time on
March 14, 2005.
4. Devon Power LLC
[Docket No. ER03–563–049]
Take notice that on February 28, 2005,
ISO New England Inc. (ISO–NE)
submitted a report updating progress
made in siting, permitting and
construction of transmission and
generation upgrades within the New
England control area, in compliance
with the Commission’s order issued
June 2, 2004, Devon Power LLC, et al.,
107 FERC ¶ 61,240.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
5. Wisconsin River Power Company
Take notice that Wisconsin River
Power Company, on March 2, 2005,
tendered for filing a supplement to the
market-based rate application and
revised rate schedules in preparation for
MISO Day-2 Market Operations filed on
January 14, 2005 in Docket No. ER05–
543–000.
Wisconsin River Power Company
states that copies of the filing were
served upon the official service list in
this proceeding, PJM, MISO, the
Michigan Public Service Commission
and the Public Service Commission of
Wisconsin.
Comment Date: 5 p.m. eastern time on
March 14, 2005.
6. Cleco Power LLC
[Docket No. ER05–473–001]
Take notice that on February 28, 2005,
Cleco Power LLC (Cleco Power) filed an
erratum to its January 19, 2005 Order
No. 2003–B compliance filing in Docket
No. ER05–473–000.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
7. Duke Energy Washington, LLC
[Docket No. ER05–623–001]
Take notice that on February 28, 2005,
Duke Energy Washington, LLC (Duke
Washington) submitted an errata to its
February 18, 2005 filing in Docket No.
ER05–623–000 of its proposed tariff for
reactive supply and voltage control from
generation sources service.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
8. Harvard Dedicated Energy Limited
[Docket No. ER05–658–000]
Take notice that on February 28, 2005,
Harvard Dedicated Energy Limited
15:31 Mar 14, 2005
Jkt 205001
9. Mid-Continent Area Power Pool
[Docket No. ER05–659–000]
Take notice that on February 28, 2005,
Mid-Continent Area Power Pool (MAPP)
filed a revised Restated Agreement
reflecting the changed functions of
MAPP. MAPP requested an effective
date of March 1, 2005.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
10. Mill Run Windpower LLC
[Docket Nos. ER05–660–000 and ER01–1710–
004]
[Docket No. ER05–453–001]
VerDate jul<14>2003
(HDEL) filed an application for
acceptance of HDEL Rate Schedule
FERC No. 1, the granting of certain
blanket approvals, including the
authority to sell electricity at marketbased rates, and the waiver of certain
Commission Regulations.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
Take notice that on February 28, 2005,
Mill Run Windpower LLC (Mill Run)
filed revisions to its market-based rate
tariff and code of conduct. Mill Run
states that the revisions make the tariff
compliant with Order No. 652,
Reporting Requirements for Changes in
Status for Public Utilities With MarketBased Rate Authority, 110 FERC
¶ 61,097 (2005). Mill Run requests an
effective date of April 25, 2003 for the
code of conduct and March 21, 2005 for
the Order No. 652 compliance filing.
Mill Run states that copies of the
filing were served on the official service
list for Docket No. ER01–1710 and on
the Florida Public Service Commission.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
Standard Paragraph
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all parties to this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
11. Somerset Windpower LLC
[Docket Nos. ER05–661–000 and ER01–2139–
005]
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–1094 Filed 3–14–05; 8:45 am]
BILLING CODE 6717–01–P
Take notice that on February 28, 2005,
Somerset Windpower LLC (Somerset)
filed revisions to its market-based rate
tariff and code of conduct. Somerset
states that the revisions make the tariff
compliant with Order No. 652,
Reporting Requirements for Changes in
Status for Public Utilities With MarketBased Rate Authority, 110 FERC
¶ 61,097 (2005). Somerset requests an
effective date of April 25, 2003 for the
code of conduct and March 21, 2005 for
the Order No. 652 compliance filing.
Somerset states that copies of the
filing were served on the official service
list for Docket No. ER01–2139 and on
the Florida Public Service Commission.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EG05–48–000, et al.]
Invenergy Cannon Falls LLC, et al.;
Electric Rate and Corporate Filings
March 4, 2005.
The following filings have been made
with the Commission. The filings are
listed in ascending order within each
docket classification.
1. Invenergy Cannon Falls LLC
[Docket No. EG05–48–000]
Take notice that on February 25, 2005,
Invenergy Cannon Falls LLC (Invenergy
E:\FR\FM\15MRN1.SGM
15MRN1
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
CF) filed with the Federal Energy
Regulatory Commission an application
for determination of exempt wholesale
generator status pursuant to part 365 of
the Commission’s regulations.
Invenergy CF states it is a Delaware
limited liability company that will
construct, own and operate an
approximately 357 MW electric
generation facility located in Cannon
Falls, Minnesota. Invenergy CF further
states it will sell power exclusively at
wholesale.
Comment Date: 5 p.m. eastern time on
March 18, 2005.
2. Judith Gap Energy LLC
5. Grant Energy, Inc.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
[Docket No. ER05–557–001]
Take notice that on February 28, 2005,
Grant Energy, Inc. (Grant) amended its
petition to the Commission filed
February 4, 2005 in Docket No. ER05–
557–000 for acceptance of Grant Rate
Schedule FERC No. 1; the granting of
certain blanket approvals, including the
authority to sell electricity at marketbased rates; and the waiver of certain
Commission regulations.
Comment Date: 5 p.m. eastern time on
March 14, 2005.
6. Southwest Power Pool, Inc.
[Docket No. ER05–651–000]
[Docket No. EG05–49–000]
Take notice that on February 25, 2005,
Judith Gap Energy LLC (Judith Gap)
filed with the Federal Energy Regulatory
Commission an application for
determination of exempt wholesale
generator status pursuant to part 365 of
the Commission’s regulations.
Judith Gap states it is a Montana
limited liability company that will
construct, own and operate an
approximately up to 188 MW electric
generation facility located in Wheatland
County, Montana. Judith Gap further
states it will sell power exclusively at
wholesale.
Comment Date: 5 p.m. eastern time on
March 18, 2005.
Take notice that on February 28, 2005,
Southwest Power Pool, Inc. (SPP)
submitted for filing an unexecuted large
generator interconnection agreement
between SPP, FPL Energy Cowboy
Wind, LLC (FPL Energy), and Public
Service Company of Oklahoma (PSO).
SPP seeks an effective date of March 1,
2005.
SPP states that both FPL Energy and
PSO were served with a copy of this
filing.
Comment Date: 5 p.m. eastern time
March 21, 2005.
7. Southwest Power Pool, Inc.
[Docket No. ER05–652–000]
Take notice that on February 25, 2005,
Spring Canyon Energy LLC (Spring
Canyon) filed with the Federal Energy
Regulatory Commission an application
for determination of exempt wholesale
generator status pursuant to part 365 of
the Commission’s regulations.
Spring Canyon states it is a Delaware
limited liability company that will
construct, own and operate an
approximately up to 188 MW electric
generation facility located in Logan,
County, Colorado. Spring Canyon
further states it will sell power
exclusively at wholesale.
Comment Date: 5 p.m. eastern time on
March 18, 2005.
Take notice that on February 28, 2005,
Southwest Power Pool, Inc. (SPP)
submitted a filing to revise its Open
Access Transmission Tariff to
implement a regional transmission cost
allocation proposal with regard to new
transmission upgrades. SPP states that it
also submitted its filing to comply with
the Commission’s February 10, 2004
order in Docket No. RT04–1–000. SPP
seeks an effective date of May 5, 2005
for the cost allocation proposal.
SPP states it has served a copy of this
filing on all parties to this proceeding,
as well as upon each of its members and
customers. SPP further states that a
complete copy of this filing will be
posted on the SPP Web site https://
www.spp.org, and is also being served
on all affected state commissions.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
4. The Detroit Edison Company
8. Southwest Reserve Sharing Group
[Docket Nos. EL01–51–007, ER01–1649–007]
[Docket No. ER05–653–000]
Take notice that on March 1, 2005,
The Detroit Edison Company (Detroit
Edison) filed an amendment to First
Revised Replacement Sheet No. 22 of
Detroit Edison’s Distribution
Interconnection Agreement with
Dearborn Industrial Generation, LLC.
Comment Date: 5 p.m. eastern time on
March 22, 2005.
Take notice that on February 28, 2005,
Tucson Electric Power Company
tendered for filing, on behalf of the
members of the Southwest Reserve
Sharing Group, an amendment to the
Southwest Reserve Sharing Group
Participation Agreement expanding
membership to include New Harquahala
Generating Company.
3. Spring Canyon Energy LLC
[Docket No. EG05–50–000]
VerDate jul<14>2003
15:31 Mar 14, 2005
Jkt 205001
PO 00000
Frm 00029
Fmt 4703
Sfmt 4703
12673
9. Phoenix Energy Trading, LLC
[Docket No. ER05–654–000]
Take notice that on February 28, 2005,
Phoenix Energy Trading, LLC.
(PHOENIX) petitioned the Commission
for acceptance of PHOENIX Rate
Schedule FERC No. 1; the granting of
certain blanket approvals, including the
authority to sell electricity at marketbased rates; and the waiver of certain
Commission regulations.
PHOENIX states that it intends to
engage in wholesale electric power and
energy purchases and sales as a
marketer. PHOENIX further states it is
not in the business of generating or
transmitting electric power.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
10. Midwest Independent Transmission
System Operator, Inc.
[Docket No. ER05–656–000]
Take notice that, on February 28,
2005, the Midwest Independent
Transmission System Operator, Inc.
(Midwest ISO) submitted an agreement
for compensation of generator-supplied
services by and among White Pine
Electric Power, LLC (Generator),
American Transmission Company, LLC
(Transmission Owner) and the Midwest
ISO.
The Midwest ISO states it has served
copies of this filing on the parties to this
agreement. In addition, the Midwest ISO
states it has electronically served a copy
of this filing upon all Midwest ISO
members, member representatives of
transmission owners and nontransmission owners, the Midwest ISO
Advisory Committee participants, as
well as all state commissions within the
region. In addition, Midwest ISO states
that the filing has been electronically
posted on the Midwest ISO’s Web site
at https://www.midwestiso.org under the
heading ‘‘Filings to FERC.’’
Comment Date: 5 p.m. eastern time
March 21, 2005.
11. Ocean State Power I, Ocean State
Power II
[Docket No. ER05–657–000]
Take notice that on February 28, 2005,
Ocean State Power I and Ocean State
Power II (collectively, Ocean State)
tendered for filing revised tariff sheets
to Rate Schedule FERC Nos. 1–8 to
update Ocean State’s rate of return on
equity (ROE). Ocean State also tendered
for filing changes to Rate Schedule
FERC Nos. 1 and 5 reflecting a
substitution of purchaser. Ocean State
requested an effective date of April 29,
E:\FR\FM\15MRN1.SGM
15MRN1
12674
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
2005 for the ROE changes and December
21, 2004 for the substitution of
purchaser.
Ocean State indicates that copies of
the filing have been served on Ocean
State’s power purchasers, the
Commonwealth of Massachusetts
Department of Telecommunications and
Energy and the Rhode Island Public
Utilities Commission.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
12. Birchwood Power Partners, L.P.
[Docket Nos. QF93–126–004, EL05–69–000]
Take notice that on February 28, 2005,
Birchwood Power Partners, L.P.
(Birchwood) submitted a request for
declaratory order and a petition for
limited waiver of the operating standard
for its cogeneration facility located in
King George County, Virginia for the
calendar year 2001 pursuant to section
292.205(c) of the Commission’s
regulations.
Comment Date: 5 p.m. eastern time on
March 21, 2005.
Standard Paragraph
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all parties to this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
VerDate jul<14>2003
15:31 Mar 14, 2005
Jkt 205001
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–1095 Filed 3–14–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. ER99–1522–003, et al.]
Bangor Hydro-Electric Company, et al.;
Electric Rate and Corporate Filings
March 8, 2005.
The following filings have been made
with the Commission. The filings are
listed in ascending order within each
docket classification.
1. Bangor Hydro-Electric Company,
Emera Energy Services, Inc., Emera
Energy U.S. Subsidiary No. 1, Inc.
[Docket Nos. ER99–1522–003, ER02–723–
002, and ER04–359–001]
Take notice that on March 1, 2005,
Bangor Hydro-Electric Company
(Bangor Hydro), Emera Energy Services,
Inc. (EES) and Emera Energy U.S.
Subsidiary No. 1, Inc. (Emera Energy
Sub No. 1) tendered for filing a triennial
market power analysis and tariff
revisions in compliance with Order No.
652, Reporting Requirements for
Changes in Status for Public Utilities
with Market-Based Rate Authority, 110
FERC ¶ 61,097 (2005).
Bangor Hydro, EES and Emera Energy
Sub No. 1 state that copies of the filing
were served on the parties listed on the
official service lists, their market-based
rate tariff jurisdictional customers, the
Maine Public Utilities Commission and
Maine’s Office of Public Advocate.
Comment Date: 5 p.m. eastern time on
March 22, 2005.
2. Astoria Energy LLC
[Docket No. ER01–3103–007]
Take notice that on March 1, 2005,
Astoria Energy LLC filed a triennial
updated market power analysis and
revised tariff sheets in compliance with
Order No. 652, Reporting Requirements
for Changes in Status for Public Utilities
with Market-Based Rate Authority, 110
FERC ¶ 61,097 (2005).
Comment Date: 5 p.m. eastern time on
March 22, 2005.
PO 00000
Frm 00030
Fmt 4703
Sfmt 4703
3. Devon Power LLC, Middletown
Power LLC, Montville Power LLC,
Norwalk Power LLC, NRG Power
Marketing Inc.
[Docket No. ER04–23–009]
Take notice that on March 1, 2005,
Devon Power LLC, Middletown Power
LLC, Montville Power LLC and Norwalk
Power LLC (collectively, NRG) tendered
for filing a statement showing the C–1
and C–2 costs incurred during the
period April 1, 2004, through December
31, 2004, in compliance with the
Commission’s order issued January 27,
2005, in ISO New England., et al., 110
FERC ¶ 61,079 (2005).
Comment Date: 5 p.m. eastern time on
March 22, 2005.
4. Midwest Independent Transmission
System Operator, Inc.
[Docket No. ER05–662–000]
Take notice that on March 1, 2005, the
Midwest Independent Transmission
System Operator, Inc. (Midwest ISO)
submitted a large generator
interconnection agreement among
Darlington Wind Farm, LLC, American
Transmission Company LLC and the
Midwest ISO.
Midwest ISO states that a copy of the
filing was served on the parties to the
interconnection agreement.
Comment Date: 5 p.m. eastern time on
March 22, 2005.
5. New England Power Pool
[Docket No. ER05–663–000]
Take notice that on March 1, 2005, the
New England Power Pool (NEPOOL)
Participants Committee filed for
acceptance materials to permit NEPOOL
to expand its membership to include the
Lincoln Paper and Tissue, Inc. (Lincoln
Paper), PPM Energy, Inc. (PPM Energy)
and Rentricity Inc. (Rentricity). The
Participants Committee requests
effective dates of March 1, 2005, for
Lincoln Paper, April 1, 2005, for
Rentricity and May 1, 2005, for PPM
Energy.
The Participants Committee states
that copies of the materials were sent to
the New England state governors and
regulatory commissions and the
participants in NEPOOL.
Comment Date: 5 p.m. eastern time on
March 22, 2005.
6. Southwest Power Pool, Inc.
[Docket No. ER05–666–000]
Take notice that on March 1, 2005,
Southwest Power Pool, Inc. (SPP)
submitted revisions to its regional Open
Access Transmission Tariff (OATT or
Tariff) proposing the following: (1) To
revise Section 3 of its OATT to add a
new Schedule 4–A to offer Generation
E:\FR\FM\15MRN1.SGM
15MRN1
Agencies
[Federal Register Volume 70, Number 49 (Tuesday, March 15, 2005)]
[Notices]
[Pages 12672-12674]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-1095]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EG05-48-000, et al.]
Invenergy Cannon Falls LLC, et al.; Electric Rate and Corporate
Filings
March 4, 2005.
The following filings have been made with the Commission. The
filings are listed in ascending order within each docket
classification.
1. Invenergy Cannon Falls LLC
[Docket No. EG05-48-000]
Take notice that on February 25, 2005, Invenergy Cannon Falls LLC
(Invenergy
[[Page 12673]]
CF) filed with the Federal Energy Regulatory Commission an application
for determination of exempt wholesale generator status pursuant to part
365 of the Commission's regulations.
Invenergy CF states it is a Delaware limited liability company that
will construct, own and operate an approximately 357 MW electric
generation facility located in Cannon Falls, Minnesota. Invenergy CF
further states it will sell power exclusively at wholesale.
Comment Date: 5 p.m. eastern time on March 18, 2005.
2. Judith Gap Energy LLC
[Docket No. EG05-49-000]
Take notice that on February 25, 2005, Judith Gap Energy LLC
(Judith Gap) filed with the Federal Energy Regulatory Commission an
application for determination of exempt wholesale generator status
pursuant to part 365 of the Commission's regulations.
Judith Gap states it is a Montana limited liability company that
will construct, own and operate an approximately up to 188 MW electric
generation facility located in Wheatland County, Montana. Judith Gap
further states it will sell power exclusively at wholesale.
Comment Date: 5 p.m. eastern time on March 18, 2005.
3. Spring Canyon Energy LLC
[Docket No. EG05-50-000]
Take notice that on February 25, 2005, Spring Canyon Energy LLC
(Spring Canyon) filed with the Federal Energy Regulatory Commission an
application for determination of exempt wholesale generator status
pursuant to part 365 of the Commission's regulations.
Spring Canyon states it is a Delaware limited liability company
that will construct, own and operate an approximately up to 188 MW
electric generation facility located in Logan, County, Colorado. Spring
Canyon further states it will sell power exclusively at wholesale.
Comment Date: 5 p.m. eastern time on March 18, 2005.
4. The Detroit Edison Company
[Docket Nos. EL01-51-007, ER01-1649-007]
Take notice that on March 1, 2005, The Detroit Edison Company
(Detroit Edison) filed an amendment to First Revised Replacement Sheet
No. 22 of Detroit Edison's Distribution Interconnection Agreement with
Dearborn Industrial Generation, LLC.
Comment Date: 5 p.m. eastern time on March 22, 2005.
5. Grant Energy, Inc.
[Docket No. ER05-557-001]
Take notice that on February 28, 2005, Grant Energy, Inc. (Grant)
amended its petition to the Commission filed February 4, 2005 in Docket
No. ER05-557-000 for acceptance of Grant Rate Schedule FERC No. 1; the
granting of certain blanket approvals, including the authority to sell
electricity at market-based rates; and the waiver of certain Commission
regulations.
Comment Date: 5 p.m. eastern time on March 14, 2005.
6. Southwest Power Pool, Inc.
[Docket No. ER05-651-000]
Take notice that on February 28, 2005, Southwest Power Pool, Inc.
(SPP) submitted for filing an unexecuted large generator
interconnection agreement between SPP, FPL Energy Cowboy Wind, LLC (FPL
Energy), and Public Service Company of Oklahoma (PSO). SPP seeks an
effective date of March 1, 2005.
SPP states that both FPL Energy and PSO were served with a copy of
this filing.
Comment Date: 5 p.m. eastern time March 21, 2005.
7. Southwest Power Pool, Inc.
[Docket No. ER05-652-000]
Take notice that on February 28, 2005, Southwest Power Pool, Inc.
(SPP) submitted a filing to revise its Open Access Transmission Tariff
to implement a regional transmission cost allocation proposal with
regard to new transmission upgrades. SPP states that it also submitted
its filing to comply with the Commission's February 10, 2004 order in
Docket No. RT04-1-000. SPP seeks an effective date of May 5, 2005 for
the cost allocation proposal.
SPP states it has served a copy of this filing on all parties to
this proceeding, as well as upon each of its members and customers. SPP
further states that a complete copy of this filing will be posted on
the SPP Web site https://www.spp.org, and is also being served on all
affected state commissions.
Comment Date: 5 p.m. eastern time on March 21, 2005.
8. Southwest Reserve Sharing Group
[Docket No. ER05-653-000]
Take notice that on February 28, 2005, Tucson Electric Power
Company tendered for filing, on behalf of the members of the Southwest
Reserve Sharing Group, an amendment to the Southwest Reserve Sharing
Group Participation Agreement expanding membership to include New
Harquahala Generating Company.
Comment Date: 5 p.m. eastern time on March 21, 2005.
9. Phoenix Energy Trading, LLC
[Docket No. ER05-654-000]
Take notice that on February 28, 2005, Phoenix Energy Trading, LLC.
(PHOENIX) petitioned the Commission for acceptance of PHOENIX Rate
Schedule FERC No. 1; the granting of certain blanket approvals,
including the authority to sell electricity at market-based rates; and
the waiver of certain Commission regulations.
PHOENIX states that it intends to engage in wholesale electric
power and energy purchases and sales as a marketer. PHOENIX further
states it is not in the business of generating or transmitting electric
power.
Comment Date: 5 p.m. eastern time on March 21, 2005.
10. Midwest Independent Transmission System Operator, Inc.
[Docket No. ER05-656-000]
Take notice that, on February 28, 2005, the Midwest Independent
Transmission System Operator, Inc. (Midwest ISO) submitted an agreement
for compensation of generator-supplied services by and among White Pine
Electric Power, LLC (Generator), American Transmission Company, LLC
(Transmission Owner) and the Midwest ISO.
The Midwest ISO states it has served copies of this filing on the
parties to this agreement. In addition, the Midwest ISO states it has
electronically served a copy of this filing upon all Midwest ISO
members, member representatives of transmission owners and non-
transmission owners, the Midwest ISO Advisory Committee participants,
as well as all state commissions within the region. In addition,
Midwest ISO states that the filing has been electronically posted on
the Midwest ISO's Web site at https://www.midwestiso.org under the
heading ``Filings to FERC.''
Comment Date: 5 p.m. eastern time March 21, 2005.
11. Ocean State Power I, Ocean State Power II
[Docket No. ER05-657-000]
Take notice that on February 28, 2005, Ocean State Power I and
Ocean State Power II (collectively, Ocean State) tendered for filing
revised tariff sheets to Rate Schedule FERC Nos. 1-8 to update Ocean
State's rate of return on equity (ROE). Ocean State also tendered for
filing changes to Rate Schedule FERC Nos. 1 and 5 reflecting a
substitution of purchaser. Ocean State requested an effective date of
April 29,
[[Page 12674]]
2005 for the ROE changes and December 21, 2004 for the substitution of
purchaser.
Ocean State indicates that copies of the filing have been served on
Ocean State's power purchasers, the Commonwealth of Massachusetts
Department of Telecommunications and Energy and the Rhode Island Public
Utilities Commission.
Comment Date: 5 p.m. eastern time on March 21, 2005.
12. Birchwood Power Partners, L.P.
[Docket Nos. QF93-126-004, EL05-69-000]
Take notice that on February 28, 2005, Birchwood Power Partners,
L.P. (Birchwood) submitted a request for declaratory order and a
petition for limited waiver of the operating standard for its
cogeneration facility located in King George County, Virginia for the
calendar year 2001 pursuant to section 292.205(c) of the Commission's
regulations.
Comment Date: 5 p.m. eastern time on March 21, 2005.
Standard Paragraph
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Applicant and all parties to this proceeding.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-1095 Filed 3-14-05; 8:45 am]
BILLING CODE 6717-01-P