Florida Gas Transmission Company; Notice of Intent To Prepare an Environmental Assessment for the Proposed Turkey Point Project and Request for Comments on Environmental Issues, 12676-12678 [E5-1084]
Download as PDF
12676
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP04–37–000, CP04–44–000,
CP04–45–000, and CP04–46–000]
Corpus Christi LNG, L.P.; Cheniere
Corpus Christi Pipeline Company;
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed Cheniere Corpus Christi
Lng Project
March 7, 2005.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a final
environmental impact statement (EIS)
on the liquefied natural gas (LNG)
import terminal and natural gas pipeline
facilities in Nueces and San Patricio
Counties, Texas proposed by Corpus
Christi LNG, L.P. and Cheniere Corpus
Christi Pipeline Company (collectively
referred to as Cheniere) in the abovereferenced dockets.
The final EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act (NEPA). The
staff concludes that approval of the
proposed project with appropriate
mitigating measures as recommended,
would have limited adverse
environmental impact. The final EIS
also evaluates alternatives to the
proposal, including system alternatives,
alternative sites for the LNG import
terminal, and pipeline alternatives.
Cheniere’s proposed facilities would
have a nominal output of about 2.6
billion cubic feet of imported natural
gas per day to the U.S. market. In order
to provide LNG import, storage, and
pipeline transportation services,
Cheniere requests Commission
authorization to construct, install, and
operate an LNG terminal and natural gas
pipeline facilities.
The final EIS addresses the potential
environmental effects of the
construction and operation of the
following LNG terminal and natural gas
pipeline facilities in San Patricio and
Nueces Counties, Texas:
• A new marine basin and dredged
maneuvering area in La Quinta Channel
on the northeast shore of Corpus Christi
Bay;
• Two berths and unloading facilities
for LNG carrier ships, and a third dock
for tugs and line boats;
• Three LNG storage tanks, each with
a nominal working volume of
approximately 160,000 cubic meters
(1,006,400 barrels equivalent);
• LNG vaporization and processing
equipment;
VerDate jul<14>2003
15:31 Mar 14, 2005
Jkt 205001
• 23 miles of 48-inch-diameter
natural gas pipeline; and
• 8 interconnects with existing
intrastate and interstate pipelines, and
related meter stations.
The final EIS has been placed in the
public files of the FERC and is available
for public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street, NE.,
Room 2A, Washington, DC 20426, (202)
502–8371.
A limited number of copies of the
final EIS are available from the Public
Reference Room identified above. In
addition, copies of the final EIS have
been mailed to federal, state, and local
agencies; public interest groups;
individuals and affected landowners
who requested a copy of the final EIS;
libraries; newspapers, and parties to this
proceedings.
In accordance with the Council on
Environmental Quality’s (CEQ)
regulations implementing NEPA, no
agency decision on a proposed action
may be made until 30 days after the U.S.
Environmental Protection Agency
publishes a notice of availability of a
final EIS. However, the CEQ regulations
provide an exception to this rule when
an agency decision is subject to a formal
internal appeal process which allows
other agencies or the public to make
their views known. In such cases, the
agency decision may be made at the
same time the notice of the final EIS is
published, allowing both periods to run
concurrently. The Commission decision
for this proposed action is subject to a
30-day rehearing period.
Additional information about the
project is available from the
Commission’s Office of External Affairs
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the ‘‘eLibrary’’ link. Click on the
‘‘eLibrary’’ link, click on ‘‘General
Search’’ and enter the docket number
excluding the last three digits in the
Docket Number field. Be sure you have
selected the appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact 1–202–502–8659. The
‘‘eLibrary’’ link on the FERC Internet
Web site also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rule makings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
document summaries, and direct links
to the documents. Go to the
‘‘eSubscription’’ link on the FERC
Internet Web site.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–1083 Filed 3–14–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP05–64–000]
Florida Gas Transmission Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Turkey Point Project and
Request for Comments on
Environmental Issues
March 8, 2005.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Turkey Point Project involving
abandonment, construction and
operation of facilities by Florida Gas
Transmission (FGT) in Miami-Dade
County, Florida. These facilities would
consist of the construction and
operation of a new 17,000 horsepower
Compressor Station, and the installation
of a 24-inch Tee and Side Valve on the
existing FGT lateral on the grounds of
the Turkey Point Power Plant owned by
Florida Power and Light (FPL). The EA
will be used by the Commission in its
decisionmaking process to determine
whether the project is in the public
convenience and necessity.
Summary of the Proposed Project
FGT is requesting authorization to
abandon facilities and to construct,
own, and operate facilities consisting of
a new 17,000 horsepower (hp) electric
Compressor Station No. 22 (CS 22) and
appurtenant facilities located in MiamiDade County, Florida, on the existing
FGT 24-inch Turkey Point Lateral
within the existing Turkey Point Power
Plant owned by FPL. Specifically, FGT
plans to:
• Construct a 1,600-foot extension of
the existing 18-inch mainline at
approximate milepost (MP) 907.7 to the
proposed Compressor Station 22, and
back to the 18-inch mainline tie in;
• Abandon approximately 50 feet of
the existing 18-inch mainline at MP
907.7 near the intersection of NW., 72nd
Avenue (Milam Dairy Road) and NW.,
64th Street;
E:\FR\FM\15MRN1.SGM
15MRN1
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
• Construct Compressor Station 22
with two 8,500 hp electric driven
compressors designed for unmanned
operation on the existing FGT 18-inch
mainline located in unincorporated
Miami-Dade County, Florida on FPLowned property located northeast of the
intersection of NW., 72nd Avenue
(Milam Dairy Rd) and NW., 64th Street;
• Install a motor control center, gas
after-cooling, an oily water storage tank,
facility blowdown, a pipeline liquids
storage tank, at the fully fenced
Compressor Station 22; and
• Install a new 24-inch Tee and Side
Valve on the existing FGT 24-inch
Turkey Point Lateral at FPL’s new 24inch lateral to the FGT system.
The location of the proposed site is
shown in Appendix 1.1
Land Requirements for Construction
Construction of the proposed facilities
would require about 14.68 acres of land.
Following construction, about 6.86 acres
would be maintained as new
aboveground facility sites and pipeline
right-of-way. The remaining 0.92 acre of
land would be restored and allowed to
revert to its former use.
The EA Process
The National Environmental Policy
Act (NEPA) requires the Commission to
take into account the environmental
impacts that could result from an action
whenever it considers the issuance of a
Certificate of Public Convenience and
Necessity. NEPA also requires us to
discover and address concerns the
public may have about proposals. This
process is referred to as ‘‘scoping.’’ The
main goal of the scoping process is to
focus the analysis in the EA on the
important environmental issues. By this
Notice of Intent, the Commission staff
requests public comments on the scope
of the issues to address in the EA. All
comments received are considered
during the preparation of the EA. State
and local government representatives
are encouraged to notify their
constituents of this proposed action and
encourage them to comment on their
areas of concern.
Our independent analysis of the
issues will be in the EA. Depending on
the comments received during the
scoping process, the EA may be
published and mailed to Federal, state
1 The appendices referenced in this notice are not
being printed in the Federal Register. Copies of all
appendices, other than Appendix 1 (maps), are
available on the Commission’s Web site at the
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, N.E., Washington,
D.C. 20426, or call (202) 502–8371. For instructions
on connecting to eLibrary refer to the last page of
this notice. Copies of the appendices were sent to
all those receiving this notice in the mail.
VerDate jul<14>2003
15:31 Mar 14, 2005
Jkt 205001
and local agencies, public interest
groups, interested individuals, affected
landowners, newspapers, libraries, and
the Commission’s official service list for
this proceeding. A comment period will
be allotted for review if the EA is
published. We will consider all
comments on the EA before we make
our recommendations to the
Commission.
In the EA we 2 will discuss impacts
that could occur as a result of the
construction and operation of the
proposed project under these general
headings:
• Geology and soils
• Land use
• Water resources, fisheries, and
wetlands
• Cultural resources
• Vegetation and wildlife
• Air quality and noise
• Endangered and threatened species
• Reliability and safety
We will also evaluate reasonable
alternatives to the proposed project or
portions of the project, and make
recommendations on how to lessen or
avoid impacts on the various resource
areas.
To ensure your comments are
considered, please carefully follow the
instructions in the public participation
section below.
Public Participation
You can make a difference by
providing us with your specific
comments or concerns about the project.
By becoming a commentor, your
concerns will be addressed in the EA
and considered by the Commission. You
should focus on the potential
environmental effects of the proposal,
alternatives to the proposal (including
alternative locations and routes), and
measures to avoid or lessen
environmental impact. The more
specific your comments, the more useful
they will be. Please carefully follow
these instructions to ensure that your
comments are received in time and
properly recorded:
• Send an original and two copies of
your letter to: Magalie R. Salas,
Secretary, Federal Energy Regulatory
Commission, 888 First St., NE., Room
1A, Washington, DC 20426.
• Label one copy of the comments for
the attention of Gas Branch 3.
• Reference Docket No. CP05–64–
000.
• Mail your comments so that they
will be received in Washington, DC on
or before April 8, 2005.
2 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the
environmental staff of the Office of Energy Projects
(OEP).
PO 00000
Frm 00033
Fmt 4703
Sfmt 4703
12677
Please note that we are continuing to
experience delays in mail deliveries
from the U.S. Postal Service. As a result,
we will include all comments that we
receive within a reasonable time frame
in our environmental analysis of this
project. However, the Commission
strongly encourages electronic filing of
any comments or interventions or
protests to this proceeding. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
https://www.ferc.gov under the ‘‘eFiling’’ link and the link to the User’s
Guide. Before you can file comments
you will need to create a free account
which can be created on-line.
We might mail the EA for comment.
If you are interested in receiving it,
please return the Information Request
(Appendix 4). If you do not return the
Information Request, you will be taken
off the mailing list.
Becoming an Intervenor
In addition to involvement in the EA
scoping process, you may want to
become an official party to the
proceeding known as an ‘‘intervenor.’’
Intervenors play a more formal role in
the process. Among other things,
intervenors have the right to receive
copies of case-related Commission
documents and filings by other
intervenors. Likewise, each intervenor
must send one electronic copy (using
the Commission’s eFiling system) or 14
paper copies of its filings to the
Secretary of the Commission and must
send a copy of its filings to all other
parties on the Commission’s service list
for this proceeding. If you want to
become an intervenor you must file a
motion to intervene according to Rule
214 of the Commission’s Rules of
Practice and Procedure (18 CFR
385.214) (see Appendix 2).3 Only
intervenors have the right to seek
rehearing of the Commission’s decision.
Affected landowners and parties with
environmental concerns may be granted
intervenor status upon showing good
cause by stating that they have a clear
and direct interest in this proceeding
which would not be adequately
represented by any other parties. You do
not need intervenor status to have your
environmental comments considered.
Environmental Mailing List
An effort is being made to send this
notice to all individuals, organizations,
and government entities interested in
and/or potentially affected by the
proposed project. This includes all
landowners who are potential right-of3 Interventions may also be filed electronically.
See previous discussion on electronic filing.
E:\FR\FM\15MRN1.SGM
15MRN1
12678
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
way grantors, whose property may be
used temporarily for project purposes,
or who own homes within distances
defined in the Commission’s regulations
of certain aboveground facilities. By this
notice we are also asking governmental
agencies, especially those in Appendix
3, to express their interest in becoming
cooperating agencies for the preparation
of the EA.
Additional Information
Additional information about the
project is available from the
Commission’s Office of External Affairs,
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the eLibrary link. Click on the
eLibrary link, click on ‘‘General Search’’
and enter the docket number excluding
the last three digits in the Docket
Number field. Be sure you have selected
an appropriate date range. For
assistance, please contact FERC Online
Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or for TTY,
contact (202) 502–8659.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
document summaries and direct links to
the documents. Go to https://
www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits
will be posted on the Commission’s
calendar located at https://www.ferc.gov/
EventCalendar/EventsList.aspx along
with other related information.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–1084 Filed 3–14–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
FEDERAL ENERGY REGULATORY
COMMISSION
[Project No. 7758–004]
The City of Holyoke Gas & Electric
Department; Notice of Application
Tendered for Filing With the
Commission, Soliciting Additional
Study Requests and Establishing
Procedural Schedule for Relicensing
and a Deadline for Submission of Final
Amendments
March 8, 2005.
Take notice that the following
hydroelectric application has been filed
VerDate jul<14>2003
15:31 Mar 14, 2005
Jkt 205001
with the Commission and is available
for public inspection.
a. Type of Application: Subsequent
Licensing.
b. Project No.: 7758–004.
c. Date Filed: February 25, 2005.
d. Applicant: The City of Holyoke Gas
& Electric Department.
e. Name of Project: Holyoke No. 4
Hydro Project.
f. Location: On the Holyoke Canal
(Connecticut River), Hampden County,
Massachusetts. The project does not use
lands of the United States.
g. Filed Pursuant to: Federal Power
Act 16 U.S.C. 791 (a)–825(r).
h. Applicant Contact: Nancy J.
Skancke, Law Offices of GKRSE, 1500 K
St. NW., Suite 330, Washington, DC
20005, (202) 408–5400.
i. FERC Contact: Jack Hannula,
john.hannula@ferc.gov, (202) 502–8917.
j. Cooperating Agencies: We are
asking Federal, state, and local agencies
and Indian tribes with jurisdiction and/
or special expertise with respect to
environmental issues to cooperate with
us in the preparation of the
environmental document. Agencies who
would like to request cooperating status
should follow the instructions for filing
comments described in item l. below.
k. Pursuant to section 4.32(b)(7) of 18
CFR of the Commission’s regulations, if
any resource agency, Indian tribe, or
person believes that an additional
scientific study should be conducted in
order to form an adequate factual basis
for a complete analysis of the
application on its merit, the resource
agency, Indian tribe, or person must file
a request for a study with the
Commission not later than 60 days from
the date of filing of the application, and
serve a copy of the request on the
applicant.
l. Deadline for Filing Additional
Study Requests and Requests for
Cooperating Agency Status: April 25,
2005.
All documents (original and eight
copies) should be filed with: Magalie R.
Salas, Secretary, Federal Energy
Regulatory Commission, 888 First
Street, NE., Washington, DC 20426.
The Commission’s Rules of Practice
require all intervenors filing documents
with the Commission to serve a copy of
that document on each person on the
official service list for the project.
Further, if an intervenor files comments
or documents with the Commission
relating to the merits of an issue that
may affect the responsibilities of a
particular resource agency, they must
also serve a copy of the document on
that resource agency.
Additional study requests and
requests for cooperating agency status
PO 00000
Frm 00034
Fmt 4703
Sfmt 4703
may be filed electronically via the
Internet in lieu of paper. The
Commission strongly encourages
electronic filings. See 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site at
(https://www.ferc.gov) under the ‘‘eFiling’’ link.
m. This application is not ready for
environmental analysis at this time.
n. Description of Project: The Holyoke
No. 4 Project consists of: (a) Two 7-footdiameter and 76-foot-long penstocks
drawing water from the first level canal
of the Holyoke Canal System; (b) a
powerhouse with 2 turbine-generator
units with a total rated capacity of 760
kW in the first floor of a 3-story brick
building; (c) two 13-foot-wide and 300foot-long tailraces discharging into the
second level canal; (d) a 4.8-kV, 25-footlong transmission line; (e) the 0.48-kV
generator leads; (f) the 0.48/4.8-kV
transformer; and (g) appurtenant
facilities.
o. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the three digits in the
docket number field to access the
document. For assistance, contact FERC
Online Support at
FERCOnlineSupport@FERC.gov or toll
free at 1–866–208–3076 or for TTY,
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h above.
You may also register online at
https://ferc.gov/docs-filing/
esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
p. With this notice, we are initiating
consultation with the Massachusetts
State Historic Preservation Officer
(SHPO), as required by section 106,
National Historic Preservation Act, and
the regulations of the Advisory Council
on Historic Preservation, 36, CFR., at
§ 800.4.
q. Procedural schedule and final
amendments: The application will be
processed according to the following
Hydro Licensing Schedule. Revisions to
the schedule will be made as
appropriate.
Issue Acceptance or Deficiency Letter:
April 2005.
Issue Scoping Document for Comments:
May 2005.
Notice that application is ready for
environmental analysis: August 2005.
Notice of the availability of the EA:
February 2006.
E:\FR\FM\15MRN1.SGM
15MRN1
Agencies
[Federal Register Volume 70, Number 49 (Tuesday, March 15, 2005)]
[Notices]
[Pages 12676-12678]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-1084]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP05-64-000]
Florida Gas Transmission Company; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Turkey Point Project and
Request for Comments on Environmental Issues
March 8, 2005.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Turkey Point Project involving
abandonment, construction and operation of facilities by Florida Gas
Transmission (FGT) in Miami-Dade County, Florida. These facilities
would consist of the construction and operation of a new 17,000
horsepower Compressor Station, and the installation of a 24-inch Tee
and Side Valve on the existing FGT lateral on the grounds of the Turkey
Point Power Plant owned by Florida Power and Light (FPL). The EA will
be used by the Commission in its decisionmaking process to determine
whether the project is in the public convenience and necessity.
Summary of the Proposed Project
FGT is requesting authorization to abandon facilities and to
construct, own, and operate facilities consisting of a new 17,000
horsepower (hp) electric Compressor Station No. 22 (CS 22) and
appurtenant facilities located in Miami-Dade County, Florida, on the
existing FGT 24-inch Turkey Point Lateral within the existing Turkey
Point Power Plant owned by FPL. Specifically, FGT plans to:
Construct a 1,600-foot extension of the existing 18-inch
mainline at approximate milepost (MP) 907.7 to the proposed Compressor
Station 22, and back to the 18-inch mainline tie in;
Abandon approximately 50 feet of the existing 18-inch
mainline at MP 907.7 near the intersection of NW., 72nd Avenue (Milam
Dairy Road) and NW., 64th Street;
[[Page 12677]]
Construct Compressor Station 22 with two 8,500 hp electric
driven compressors designed for unmanned operation on the existing FGT
18-inch mainline located in unincorporated Miami-Dade County, Florida
on FPL-owned property located northeast of the intersection of NW.,
72nd Avenue (Milam Dairy Rd) and NW., 64th Street;
Install a motor control center, gas after-cooling, an oily
water storage tank, facility blowdown, a pipeline liquids storage tank,
at the fully fenced Compressor Station 22; and
Install a new 24-inch Tee and Side Valve on the existing
FGT 24-inch Turkey Point Lateral at FPL's new 24-inch lateral to the
FGT system.
The location of the proposed site is shown in Appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice are not being
printed in the Federal Register. Copies of all appendices, other
than Appendix 1 (maps), are available on the Commission's Web site
at the ``eLibrary'' link or from the Commission's Public Reference
Room, 888 First Street, N.E., Washington, D.C. 20426, or call (202)
502-8371. For instructions on connecting to eLibrary refer to the
last page of this notice. Copies of the appendices were sent to all
those receiving this notice in the mail.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed facilities would require about 14.68
acres of land. Following construction, about 6.86 acres would be
maintained as new aboveground facility sites and pipeline right-of-way.
The remaining 0.92 acre of land would be restored and allowed to revert
to its former use.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
to discover and address concerns the public may have about proposals.
This process is referred to as ``scoping.'' The main goal of the
scoping process is to focus the analysis in the EA on the important
environmental issues. By this Notice of Intent, the Commission staff
requests public comments on the scope of the issues to address in the
EA. All comments received are considered during the preparation of the
EA. State and local government representatives are encouraged to notify
their constituents of this proposed action and encourage them to
comment on their areas of concern.
Our independent analysis of the issues will be in the EA. Depending
on the comments received during the scoping process, the EA may be
published and mailed to Federal, state and local agencies, public
interest groups, interested individuals, affected landowners,
newspapers, libraries, and the Commission's official service list for
this proceeding. A comment period will be allotted for review if the EA
is published. We will consider all comments on the EA before we make
our recommendations to the Commission.
In the EA we \2\ will discuss impacts that could occur as a result
of the construction and operation of the proposed project under these
general headings:
\2\ ``We'', ``us'', and ``our'' refer to the environmental staff
of the Office of Energy Projects (OEP).
---------------------------------------------------------------------------
Geology and soils
Land use
Water resources, fisheries, and wetlands
Cultural resources
Vegetation and wildlife
Air quality and noise
Endangered and threatened species
Reliability and safety
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
To ensure your comments are considered, please carefully follow the
instructions in the public participation section below.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. By becoming a commentor, your
concerns will be addressed in the EA and considered by the Commission.
You should focus on the potential environmental effects of the
proposal, alternatives to the proposal (including alternative locations
and routes), and measures to avoid or lessen environmental impact. The
more specific your comments, the more useful they will be. Please
carefully follow these instructions to ensure that your comments are
received in time and properly recorded:
Send an original and two copies of your letter to: Magalie
R. Salas, Secretary, Federal Energy Regulatory Commission, 888 First
St., NE., Room 1A, Washington, DC 20426.
Label one copy of the comments for the attention of Gas
Branch 3.
Reference Docket No. CP05-64-000.
Mail your comments so that they will be received in
Washington, DC on or before April 8, 2005.
Please note that we are continuing to experience delays in mail
deliveries from the U.S. Postal Service. As a result, we will include
all comments that we receive within a reasonable time frame in our
environmental analysis of this project. However, the Commission
strongly encourages electronic filing of any comments or interventions
or protests to this proceeding. See 18 CFR 385.2001(a)(1)(iii) and the
instructions on the Commission's Web site at https://www.ferc.gov under
the ``e-Filing'' link and the link to the User's Guide. Before you can
file comments you will need to create a free account which can be
created on-line.
We might mail the EA for comment. If you are interested in
receiving it, please return the Information Request (Appendix 4). If
you do not return the Information Request, you will be taken off the
mailing list.
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an official party to the proceeding known as an
``intervenor.'' Intervenors play a more formal role in the process.
Among other things, intervenors have the right to receive copies of
case-related Commission documents and filings by other intervenors.
Likewise, each intervenor must send one electronic copy (using the
Commission's eFiling system) or 14 paper copies of its filings to the
Secretary of the Commission and must send a copy of its filings to all
other parties on the Commission's service list for this proceeding. If
you want to become an intervenor you must file a motion to intervene
according to Rule 214 of the Commission's Rules of Practice and
Procedure (18 CFR 385.214) (see Appendix 2).\3\ Only intervenors have
the right to seek rehearing of the Commission's decision.
---------------------------------------------------------------------------
\3\ Interventions may also be filed electronically. See previous
discussion on electronic filing.
---------------------------------------------------------------------------
Affected landowners and parties with environmental concerns may be
granted intervenor status upon showing good cause by stating that they
have a clear and direct interest in this proceeding which would not be
adequately represented by any other parties. You do not need intervenor
status to have your environmental comments considered.
Environmental Mailing List
An effort is being made to send this notice to all individuals,
organizations, and government entities interested in and/or potentially
affected by the proposed project. This includes all landowners who are
potential right-of-
[[Page 12678]]
way grantors, whose property may be used temporarily for project
purposes, or who own homes within distances defined in the Commission's
regulations of certain aboveground facilities. By this notice we are
also asking governmental agencies, especially those in Appendix 3, to
express their interest in becoming cooperating agencies for the
preparation of the EA.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the eLibrary link.
Click on the eLibrary link, click on ``General Search'' and enter the
docket number excluding the last three digits in the Docket Number
field. Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact (202) 502-8659.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries and direct links to
the documents. Go to https://www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at https://www.ferc.gov/EventCalendar/
EventsList.aspx along with other related information.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-1084 Filed 3-14-05; 8:45 am]
BILLING CODE 6717-01-P