Corpus Christi LNG, L.P.; Cheniere Corpus Christi Pipeline Company; Notice of Availability of the Final Environmental Impact Statement for the Proposed Cheniere Corpus Christi Lng Project, 12676 [E5-1083]
Download as PDF
12676
Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP04–37–000, CP04–44–000,
CP04–45–000, and CP04–46–000]
Corpus Christi LNG, L.P.; Cheniere
Corpus Christi Pipeline Company;
Notice of Availability of the Final
Environmental Impact Statement for
the Proposed Cheniere Corpus Christi
Lng Project
March 7, 2005.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) has prepared a final
environmental impact statement (EIS)
on the liquefied natural gas (LNG)
import terminal and natural gas pipeline
facilities in Nueces and San Patricio
Counties, Texas proposed by Corpus
Christi LNG, L.P. and Cheniere Corpus
Christi Pipeline Company (collectively
referred to as Cheniere) in the abovereferenced dockets.
The final EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act (NEPA). The
staff concludes that approval of the
proposed project with appropriate
mitigating measures as recommended,
would have limited adverse
environmental impact. The final EIS
also evaluates alternatives to the
proposal, including system alternatives,
alternative sites for the LNG import
terminal, and pipeline alternatives.
Cheniere’s proposed facilities would
have a nominal output of about 2.6
billion cubic feet of imported natural
gas per day to the U.S. market. In order
to provide LNG import, storage, and
pipeline transportation services,
Cheniere requests Commission
authorization to construct, install, and
operate an LNG terminal and natural gas
pipeline facilities.
The final EIS addresses the potential
environmental effects of the
construction and operation of the
following LNG terminal and natural gas
pipeline facilities in San Patricio and
Nueces Counties, Texas:
• A new marine basin and dredged
maneuvering area in La Quinta Channel
on the northeast shore of Corpus Christi
Bay;
• Two berths and unloading facilities
for LNG carrier ships, and a third dock
for tugs and line boats;
• Three LNG storage tanks, each with
a nominal working volume of
approximately 160,000 cubic meters
(1,006,400 barrels equivalent);
• LNG vaporization and processing
equipment;
VerDate jul<14>2003
15:31 Mar 14, 2005
Jkt 205001
• 23 miles of 48-inch-diameter
natural gas pipeline; and
• 8 interconnects with existing
intrastate and interstate pipelines, and
related meter stations.
The final EIS has been placed in the
public files of the FERC and is available
for public inspection at: Federal Energy
Regulatory Commission, Public
Reference Room, 888 First Street, NE.,
Room 2A, Washington, DC 20426, (202)
502–8371.
A limited number of copies of the
final EIS are available from the Public
Reference Room identified above. In
addition, copies of the final EIS have
been mailed to federal, state, and local
agencies; public interest groups;
individuals and affected landowners
who requested a copy of the final EIS;
libraries; newspapers, and parties to this
proceedings.
In accordance with the Council on
Environmental Quality’s (CEQ)
regulations implementing NEPA, no
agency decision on a proposed action
may be made until 30 days after the U.S.
Environmental Protection Agency
publishes a notice of availability of a
final EIS. However, the CEQ regulations
provide an exception to this rule when
an agency decision is subject to a formal
internal appeal process which allows
other agencies or the public to make
their views known. In such cases, the
agency decision may be made at the
same time the notice of the final EIS is
published, allowing both periods to run
concurrently. The Commission decision
for this proposed action is subject to a
30-day rehearing period.
Additional information about the
project is available from the
Commission’s Office of External Affairs
at 1–866–208–FERC or on the FERC
Internet Web site (https://www.ferc.gov)
using the ‘‘eLibrary’’ link. Click on the
‘‘eLibrary’’ link, click on ‘‘General
Search’’ and enter the docket number
excluding the last three digits in the
Docket Number field. Be sure you have
selected the appropriate date range. For
assistance, please contact FERC Online
Support at FercOnlineSupport@ferc.gov
or toll free at 1–866–208–3676, or for
TTY, contact 1–202–502–8659. The
‘‘eLibrary’’ link on the FERC Internet
Web site also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rule makings.
In addition, the Commission now
offers a free service called eSubscription
which allows you to keep track of all
formal issuances and submittals in
specific dockets. This can reduce the
amount of time you spend researching
proceedings by automatically providing
you with notification of these filings,
PO 00000
Frm 00032
Fmt 4703
Sfmt 4703
document summaries, and direct links
to the documents. Go to the
‘‘eSubscription’’ link on the FERC
Internet Web site.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–1083 Filed 3–14–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP05–64–000]
Florida Gas Transmission Company;
Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Turkey Point Project and
Request for Comments on
Environmental Issues
March 8, 2005.
The staff of the Federal Energy
Regulatory Commission (FERC or
Commission) will prepare an
environmental assessment (EA) that will
discuss the environmental impacts of
the Turkey Point Project involving
abandonment, construction and
operation of facilities by Florida Gas
Transmission (FGT) in Miami-Dade
County, Florida. These facilities would
consist of the construction and
operation of a new 17,000 horsepower
Compressor Station, and the installation
of a 24-inch Tee and Side Valve on the
existing FGT lateral on the grounds of
the Turkey Point Power Plant owned by
Florida Power and Light (FPL). The EA
will be used by the Commission in its
decisionmaking process to determine
whether the project is in the public
convenience and necessity.
Summary of the Proposed Project
FGT is requesting authorization to
abandon facilities and to construct,
own, and operate facilities consisting of
a new 17,000 horsepower (hp) electric
Compressor Station No. 22 (CS 22) and
appurtenant facilities located in MiamiDade County, Florida, on the existing
FGT 24-inch Turkey Point Lateral
within the existing Turkey Point Power
Plant owned by FPL. Specifically, FGT
plans to:
• Construct a 1,600-foot extension of
the existing 18-inch mainline at
approximate milepost (MP) 907.7 to the
proposed Compressor Station 22, and
back to the 18-inch mainline tie in;
• Abandon approximately 50 feet of
the existing 18-inch mainline at MP
907.7 near the intersection of NW., 72nd
Avenue (Milam Dairy Road) and NW.,
64th Street;
E:\FR\FM\15MRN1.SGM
15MRN1
Agencies
[Federal Register Volume 70, Number 49 (Tuesday, March 15, 2005)]
[Notices]
[Page 12676]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-1083]
[[Page 12676]]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. CP04-37-000, CP04-44-000, CP04-45-000, and CP04-46-000]
Corpus Christi LNG, L.P.; Cheniere Corpus Christi Pipeline
Company; Notice of Availability of the Final Environmental Impact
Statement for the Proposed Cheniere Corpus Christi Lng Project
March 7, 2005.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a final environmental impact statement (EIS)
on the liquefied natural gas (LNG) import terminal and natural gas
pipeline facilities in Nueces and San Patricio Counties, Texas proposed
by Corpus Christi LNG, L.P. and Cheniere Corpus Christi Pipeline
Company (collectively referred to as Cheniere) in the above-referenced
dockets.
The final EIS was prepared to satisfy the requirements of the
National Environmental Policy Act (NEPA). The staff concludes that
approval of the proposed project with appropriate mitigating measures
as recommended, would have limited adverse environmental impact. The
final EIS also evaluates alternatives to the proposal, including system
alternatives, alternative sites for the LNG import terminal, and
pipeline alternatives.
Cheniere's proposed facilities would have a nominal output of about
2.6 billion cubic feet of imported natural gas per day to the U.S.
market. In order to provide LNG import, storage, and pipeline
transportation services, Cheniere requests Commission authorization to
construct, install, and operate an LNG terminal and natural gas
pipeline facilities.
The final EIS addresses the potential environmental effects of the
construction and operation of the following LNG terminal and natural
gas pipeline facilities in San Patricio and Nueces Counties, Texas:
A new marine basin and dredged maneuvering area in La
Quinta Channel on the northeast shore of Corpus Christi Bay;
Two berths and unloading facilities for LNG carrier ships,
and a third dock for tugs and line boats;
Three LNG storage tanks, each with a nominal working
volume of approximately 160,000 cubic meters (1,006,400 barrels
equivalent);
LNG vaporization and processing equipment;
23 miles of 48-inch-diameter natural gas pipeline; and
8 interconnects with existing intrastate and interstate
pipelines, and related meter stations.
The final EIS has been placed in the public files of the FERC and
is available for public inspection at: Federal Energy Regulatory
Commission, Public Reference Room, 888 First Street, NE., Room 2A,
Washington, DC 20426, (202) 502-8371.
A limited number of copies of the final EIS are available from the
Public Reference Room identified above. In addition, copies of the
final EIS have been mailed to federal, state, and local agencies;
public interest groups; individuals and affected landowners who
requested a copy of the final EIS; libraries; newspapers, and parties
to this proceedings.
In accordance with the Council on Environmental Quality's (CEQ)
regulations implementing NEPA, no agency decision on a proposed action
may be made until 30 days after the U.S. Environmental Protection
Agency publishes a notice of availability of a final EIS. However, the
CEQ regulations provide an exception to this rule when an agency
decision is subject to a formal internal appeal process which allows
other agencies or the public to make their views known. In such cases,
the agency decision may be made at the same time the notice of the
final EIS is published, allowing both periods to run concurrently. The
Commission decision for this proposed action is subject to a 30-day
rehearing period.
Additional information about the project is available from the
Commission's Office of External Affairs at 1-866-208-FERC or on the
FERC Internet Web site (https://www.ferc.gov) using the ``eLibrary''
link. Click on the ``eLibrary'' link, click on ``General Search'' and
enter the docket number excluding the last three digits in the Docket
Number field. Be sure you have selected the appropriate date range. For
assistance, please contact FERC Online Support at
FercOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or for TTY,
contact 1-202-502-8659. The ``eLibrary'' link on the FERC Internet Web
site also provides access to the texts of formal documents issued by
the Commission, such as orders, notices, and rule makings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to the ``eSubscription'' link on the FERC Internet
Web site.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-1083 Filed 3-14-05; 8:45 am]
BILLING CODE 6717-01-P