Alabama Power Company; Notice of Availability of Environmental Assessment, 12675 [E5-1082]

Download as PDF Federal Register / Vol. 70, No. 49 / Tuesday, March 15, 2005 / Notices Imbalance Service as an ancillary service; (2) to revise Section 10 of its OATT in order to provide more extensive liability protection under its OATT; (3) to revise section 34 of its OATT in order to resolve the problem of associated with adjusting for point-topoint reservations when the reservations are on an RTO, not an individual Transmission Owner basis; (4) to modify Schedule 9 of its OATT to provide Transmission Owners taking Network Integration Transmission Service under the OATT the opportunity to not pay otherwise applicable monthly demand charges if such Transmission Owners would have received, pursuant to Attachment L of the OATT, the amount they seek not to pay; (5) to put in place a new Attachment AC providing for a one-year experimental process allowing customers requesting short-term firm point-to- point service to obtain service through redispatch which otherwise would have been rejected due to a lack of capacity; and (6) to modify several portions of its OATT in order to correct various zone name references. SPP requests an effective date of May 1, 2005 for the proposed revisions. SPP states that it has served a copy of its transmittal letter upon each of its embers and customers. SPP further states that a complete copy of this filing will be posted on the SPP Web site https://www.spp.org, and is also being served on all affected state commissions. Comment Date: 5 p.m. eastern time on March 22, 2005. 7. Commonwealth Edison Company [Docket No. ER05–672–000] Take notice that on March 1, 2005, Exelon Corporation, on behalf of its subsidiary Commonwealth Edison Company, submitted a notice of cancellation for Service Agreement No. C1055 under PJM Interconnection L.L.C.’s FERC Electric Tariff, Sixth Revised Volume No. 1, with Titan Land Development Company, L.L.C., to be effective March 1, 2005. Exelon Corporation states that the filing has been served on Titan Land Development Company, L.L.C., PJM Interconnection, L.L.C. and the Illinois Commerce Commission. Comment Date: 5 p.m. eastern time on March 22, 2005. 8. Commonwealth Edison Company [Docket No. ER05–673–000] Take notice that on March 1, 2005, Exelon Corporation, on behalf of its subsidiary Commonwealth Edison Company, submitted a notice of cancellation for Service Agreement No. VerDate jul<14>2003 15:31 Mar 14, 2005 Jkt 205001 12675 C1054 under PJM Interconnection L.L.C.’s FERC Electric Tariff, Sixth Revised Volume No. 1, with Kendall New Century Development, L.L.C., to be effective March 1, 2005. Exelon Corporation states that the filing has been served on Kendall New Century Development, L.L.C., PJM Interconnection, L.L.C. and the Illinois Commerce Commission. Comment Date: 5 p.m. eastern time on March 22, 2005. docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. 9. Southwest Power Pool, Inc. DEPARTMENT OF ENERGY [Docket Nos. RT04–1–010 and ER04–48–010] Federal Energy Regulatory Commission Take notice that on March 1, 2005, Southwest Power Pool, Inc. (SPP) resubmitted the Independent Market Monitoring Services Agreement filed on November 1, 2004, and accepted by the Commission in an order issued January 24, 2005, in Docket Nos. RT04–1–006 and ER04–48–006. SPP states that the tariff revisions, with appropriate page designations pursuant to the Commission’s Order No. 614, were resubmitted in accordance with the Commission staff’s request. Comment Date: 5 p.m. eastern time on March 22, 2005. Standard Paragraph Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant and all parties to this proceeding. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed PO 00000 Frm 00031 Fmt 4703 Sfmt 4703 Linda Mitry, Deputy Secretary. [FR Doc. E5–1120 Filed 3–14–05; 8:45 am] BILLING CODE 6717–01–P [Project No. 349–091] Alabama Power Company; Notice of Availability of Environmental Assessment March 8, 2005. An environmental assessment (EA) is available for public review. The EA analyzes the environmental impacts of allowing Harbor Pointe Development to use Martin Dam Project lands for the expansion and renovation of the Harbor Pointe Marina. The project is located on Lake Martin, Tallapoosa River, Tallapoosa County, Alabama. The project is licensed to Alabama Power Company. The EA was written by staff in the Office of Energy Projects, Federal Energy Regulatory Commission. Commission staff concludes that approving the expansion and renovations would not constitute a major Federal action significantly affecting the quality of the human environment. A copy of the EA is attached to a March 7, 2005 Commission order titled ‘‘Order Modifying and Approving Non-Project Use of Project Lands and Waters,’’ which is available for review at the Commission or on the Commission’s Web site at https:// www.ferc.gov, using the ‘‘eLibrary’’ link. Enter the docket number excluding the last three digits in the docket number field to access the document. For assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov or tollfree at (866) 208–3676, or for TTY, contact (202) 502–8659. If you have any questions regarding this notice, please call Jean Potvin at (202) 502–8928. Linda Mitry, Deputy Secretary. [FR Doc. E5–1082 Filed 3–14–05; 8:45 am] BILLING CODE 6717–01–P E:\FR\FM\15MRN1.SGM 15MRN1

Agencies

[Federal Register Volume 70, Number 49 (Tuesday, March 15, 2005)]
[Notices]
[Page 12675]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-1082]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 349-091]


Alabama Power Company; Notice of Availability of Environmental 
Assessment

March 8, 2005.
    An environmental assessment (EA) is available for public review. 
The EA analyzes the environmental impacts of allowing Harbor Pointe 
Development to use Martin Dam Project lands for the expansion and 
renovation of the Harbor Pointe Marina. The project is located on Lake 
Martin, Tallapoosa River, Tallapoosa County, Alabama. The project is 
licensed to Alabama Power Company.
    The EA was written by staff in the Office of Energy Projects, 
Federal Energy Regulatory Commission. Commission staff concludes that 
approving the expansion and renovations would not constitute a major 
Federal action significantly affecting the quality of the human 
environment. A copy of the EA is attached to a March 7, 2005 Commission 
order titled ``Order Modifying and Approving Non-Project Use of Project 
Lands and Waters,'' which is available for review at the Commission or 
on the Commission's Web site at https://www.ferc.gov, using the 
``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC Online Support at FERCOnlineSupport@ferc.gov 
or toll-free at (866) 208-3676, or for TTY, contact (202) 502-8659.
    If you have any questions regarding this notice, please call Jean 
Potvin at (202) 502-8928.

Linda Mitry,
Deputy Secretary.
[FR Doc. E5-1082 Filed 3-14-05; 8:45 am]
BILLING CODE 6717-01-P