Federal Acquisition Regulation; Elimination of Certain Subcontract Notification Requirements, 11761-11762 [05-4092]
Download as PDF
Federal Register / Vol. 70, No. 45 / Wednesday, March 9, 2005 / Rules and Regulations
flexibly-priced contracts and subcontracts as
follows:
(i) When the costs that were accumulated
under the noncompliant practice exceed the
costs that would have been accumulated
using a compliant practice (from the time the
noncompliant practice was first implemented
until the date the noncompliant practice was
replaced with a compliant practice), the
difference is increased cost to the
Government.
(ii) When the costs that were accumulated
under the noncompliant practice are less
than the costs that would have been
accumulated using a compliant practice
(from the time the noncompliant practice was
first implemented until the date the
noncompliant practice was replaced with a
compliant practice), the difference is
decreased cost to the Government.
(4) Calculate the total increase or decrease
in contract and subcontracts incentives, fees,
and profits associated with the increased or
decreased cost to the Government in
accordance with 48 CFR 9903.306(c). The
associated increase or decrease is based on
the difference between the negotiated
incentives, fees, and profits and the amounts
that would have been negotiated had the
Contractor used a compliant practice.
(5) Calculate the increased cost to the
Government in the aggregate.
(j) If the Contractor does not submit the
information required by paragraph (b) or (c)
of this clause within the specified time, or
any extension granted by the CFAO, the
CFAO may take one or both of the following
actions:
(1) Withhold an amount not to exceed 10
percent of each subsequent amount payment
to the Contractor’s affected CAS-covered
contracts, (up to the estimated general dollar
magnitude of the cost impact), until such
time as the Contractor provides the required
information to the CFAO.
(2) Issue a final decision in accordance
with FAR 33.211 and unilaterally adjust the
contract(s) by the estimated amount of the
cost impact.
(k) Agree to—
(1) Contract modifications to reflect
adjustments required in accordance with
paragraph (a)(4)(ii) or (a)(5) of the clauses at
FAR 52.230–2 and 52.230–5; or with
paragraph (a)(3)(i) or (a)(4) of the clause at
FAR 52.230–3; and
(2) Repay the Government for any aggregate
increased cost paid to the Contractor.
(l) For all subcontracts subject to the
clauses at FAR 52.230–2, 52.230–3, or
52.230–5—
(1) So state in the body of the subcontract,
in the letter of award, or in both (do not use
self-deleting clauses);
(2) Include the substance of this clause in
all negotiated subcontracts; and
(3) Within 30 days after award of the
subcontract, submit the following
information to the Contractor’s CFAO:
(i) Subcontractor’s name and subcontract
number.
(ii) Dollar amount and date of award.
(iii) Name of Contractor making the award.
(m) Notify the CFAO in writing of any
adjustments required to subcontracts under
this contract and agree to an adjustment to
VerDate jul<14>2003
16:48 Mar 08, 2005
Jkt 205001
this contract price or estimated cost and fee.
The Contractor shall—
(1) Provide this notice within 30 days after
the Contractor receives the proposed
subcontract adjustments; and
(2) Include a proposal for adjusting the
higher-tier subcontract or the contract
appropriately.
(n) For subcontracts containing the clause
or substance of the clause at FAR 52.230–2,
FAR 52.230–3, or FAR 52.230–5, require the
subcontractor to comply with all Standards
in effect on the date of award or of final
agreement on price, as shown on the
subcontractor’s signed Certificate of Current
Cost or Pricing Data, whichever is earlier.
(End of clause)
9. Add section 52.230–7 to read as
follows:
I
52.230–7 Proposal Disclosure—Cost
Accounting Practice Changes.
As prescribed in 30.201–3(c), insert
the following provision:
Proposal Disclosure—Cost Accounting
Practice Changes (Apr 2005)
The offeror shall check ‘‘yes’’ below if the
contract award will result in a required or
unilateral change in cost accounting practice,
including unilateral changes requested to be
desirable changes.
b Yes
b No
If the offeror checked ‘‘Yes’’ above, the
offeror shall—
(1) Prepare the price proposal in response
to the solicitation using the changed practice
for the period of performance for which the
practice will be used; and
(2) Submit a description of the changed
cost accounting practice to the Contracting
Officer and the Cognizant Federal Agency
Official as pricing support for the proposal.
(End of provision)
[FR Doc. 05–4093 Filed 3–8–05; 8:45 am]
BILLING CODE 6820–EP–P
DEPARTMENT OF DEFENSE
GENERAL SERVICES
ADMINISTRATION
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
48 CFR Parts 44 and 52
[FAC 2005–01; FAR Case 2003–024; Item
VII]
11761
Interim rule with request for
comments.
ACTION:
SUMMARY: The Civilian Agency
Acquisition Council and the Defense
Acquisition Regulations Council (the
Councils) have agreed to amend the
Federal Acquisition Regulation language
regarding advance notification
requirements. This change is required to
implement Section 842 of the National
Defense Authorization Act for Fiscal
Year 2004, Public Law 108–136, which
resulted in revisions to 10 U.S.C.
2306(e).
Effective Date: March 9, 2005.
Comment Date: Interested parties
should submit comments to the FAR
Secretariat at the address shown below
on or before May 9, 2005 to be
considered in the formulation of a final
rule.
ADDRESSES: Submit comments
identified by FAC 2005–01, FAR case
2003–024 by any of the following
methods:
• Federal eRulemaking Portal: https://
www.regulations.gov. Follow the
instructions for submitting comments.
• Agency Web Site: https://
www.acqnet.gov/far/ProposedRules/
proposed.htm. Click on the FAR case
number to submit comments.
• E-mail: farcase.2003–024@gsa.gov.
Include FAC 2005–01, FAR case 2003–
024 in the subject line of the message.
• Fax: 202–501–4067.
• Mail: General Services
Administration, Regulatory Secretariat
(VIR), 1800 F Street, NW., Room 4035,
ATTN: Laurieann Duarte, Washington,
DC 20405.
Instructions: Please submit comments
only and cite FAC 2005–01, FAR case
2003–024, in all correspondence related
to this case. All comments received will
be posted without change to https://
www.acqnet.gov/far/ProposedRules/
proposed.htm, including any personal
information provided.
FOR FURTHER INFORMATION CONTACT The
FAR Secretariat at (202) 501–4755, for
information pertaining to status or
publication schedules. For clarification
of content, contact Ms. Rhonda Cundiff,
at (202) 501–0044. Please cite FAC
2005–01, FAR case 2003–024.
SUPPLEMENTARY INFORMATION:
DATES:
RIN 9000–AK10
A. Background
Federal Acquisition Regulation;
Elimination of Certain Subcontract
Notification Requirements
This rule revises FAR 44.201–2,
Advance notification requirements, and
amends Alternate I of FAR clause
52.244–2, Subcontracts. This change is
required in order to implement Section
842 of the National Defense
Authorization Act for Fiscal Year 2004,
Public Law 108–136. Section 842
AGENCIES: Department of Defense (DoD),
General Services Administration (GSA),
and National Aeronautics and Space
Administration (NASA).
PO 00000
Frm 00027
Fmt 4701
Sfmt 4700
E:\FR\FM\09MRR2.SGM
09MRR2
11762
Federal Register / Vol. 70, No. 45 / Wednesday, March 9, 2005 / Rules and Regulations
removes the requirement for contractors
under cost-reimbursement contracts
with the Department of Defense (DoD),
Coast Guard, and National Aeronautics
and Space Administration (NASA) to
notify the agency before the award of
any cost-plus-fixed-fee subcontract or
any fixed-price subcontract that exceeds
the greater of the simplified acquisition
threshold or 5 percent of the total
estimated cost of the contract if the
contractor maintains a purchasing
system approved by the contracting
officer for the contract.
In addition, the rule makes a technical
amendment to Alternate II of FAR
clause 52.244–2, Subcontracts. The rule
deletes the reference to paragraph (c)
from paragraph (f)(2) of Alternate II
because paragraph (c) applies to fixed
price type contracts, whereas Alternate
II applies to cost-reimbursement
contracts.
This is not a significant regulatory
action and, therefore, was not subject to
review under Section 6(b) of Executive
Order 12866, Regulatory Planning and
Review, dated September 30, 1993. This
rule is not a major rule under 5 U.S.C.
804.
B. Regulatory Flexibility Act
This interim rule is not expected to
have a significant economic impact on
a substantial number of small entities
within the meaning of the Regulatory
Flexibility Act, 5 U.S.C. 601, et seq.,
because it will have a small positive
effect. Also, small businesses do not
usually hold prime contracts which are
cost-reimbursement contracts, so this
section would not apply to them, and
any changes would not apply.
Therefore, an Initial Regulatory
Flexibility Analysis has not been
performed. We invite comments from
small business concerns and other
interested parties. The Councils will
consider comments from small entities
concerning the affected FAR Parts 44
and 52 in accordance with 5 U.S.C. 610.
Interested parties must submit such
comments separately and should cite 5
U.S.C 601, et seq. (FAC 2005–01, FAR
case 2003–024), in correspondence.
C. Paperwork Reduction Act
The Paperwork Reduction Act does
not apply because the changes to the
FAR do not impose information
collection requirements that require the
approval of the Office of Management
and Budget under 44 U.S.C. 3501, et
seq.
D. Determination to Issue an Interim
Rule
A determination has been made under
the authority of the Secretary of Defense
VerDate jul<14>2003
16:48 Mar 08, 2005
Jkt 205001
(DoD), the Administrator of General
Services (GSA), and the Administrator
of the National Aeronautics and Space
Administration (NASA) that urgent and
compelling reasons exist to promulgate
this interim rule without prior
opportunity for public comment. This
action is necessary to implement
Section 842 of the National Defense
Authorization Act for Fiscal Year 2004,
Public Law 108–136, which went into
effect November 24, 2003, and which
resulted in revisions to 10 U.S.C. 2306
(e). However, pursuant to Public Law
98–577 and FAR 1.501, the Councils
will consider public comments received
in response to this interim rule in the
formation of the final rule.
List of Subjects in 48 CFR Parts 44 and
52
Government procurement.
Dated: February 24, 2005.
Rodney P. Lantier,
Director, Contract Policy Division.
Therefore, DoD, GSA, and NASA
amend 48 CFR parts 44 and 52 as set
forth below:
I 1. The authority citation for 48 CFR
parts 44 and 52 is revised to read as
follows:
I
Authority: 40 U.S.C. 121(c); 10 U.S.C.
chapter 137; and 42 U.S.C. 2473(c).
PART 44—SUBCONTRACTING
POLICIES AND PROCEDURES
2. Revise section 44.201–2 to read as
follows:
I
Under cost-reimbursement contracts,
the contractor is required by statute to
notify the contracting officer as follows:
(a) For the Department of Defense, the
Coast Guard, and the National
Aeronautics and Space Administration,
unless the contractor maintains an
approved purchasing system, 10 U.S.C.
2306 requires notification before the
award of any cost-plus-fixed-fee
subcontract, or any fixed-price
subcontract that exceeds the greater of
the simplified acquisition threshold or 5
percent of the total estimated cost of the
contract.
(b) For civilian agencies other than
the Coast Guard and the National
Aeronautics and Space Administration,
even if the contractor has an approved
purchasing system, 41 U.S.C. 254(b)
requires notification before the award of
any cost-plus-fixed-fee subcontract, or
any fixed-price subcontract that exceeds
either the simplified acquisition
threshold or 5 percent of the total
estimated cost of the contract.
Frm 00028
Fmt 4701
Sfmt 4700
3. Amend section 52.244–2—
a. In Alternate I, by removing ‘‘(Aug
1998)’’ and adding ‘‘(MAR 2005)’’ in its
place, and revising the first sentence of
paragraph (f)(2); and
I b. In Alternate II, by removing ‘‘(Aug
1998)’’ and adding ‘‘(MAR 2005)’’ in its
place, and in paragraph (f)(2) by
removing ‘‘(c), (d),’’ and adding ‘‘(d)’’ in
its place. The revised text reads as
follows:
I
I
52.244–2
Subcontracts.
*
*
*
*
*
Alternate I * * *
(f)(2) Unless the Contractor maintains
an approved purchasing system, the
Contractor shall notify the Contracting
Officer reasonably in advance of
entering into any (i) cost-plus-fixed-fee
subcontract, or (ii) fixed-price
subcontract that exceeds the greater of
the simplified acquisition threshold or 5
percent of the total estimated cost of this
contract. * * *
[FR Doc. 05–4092 Filed 3–8–05; 8:45 am]
BILLING CODE 6820–EP–S
DEPARTMENT OF DEFENSE
GENERAL SERVICES
ADMINISTRATION
NATIONAL AERONAUTICS AND
SPACE ADMINISTRATION
48 CFR Part 44
44.201–2 Advance notification
requirements.
PO 00000
PART 52—SOLICITATION PROVISIONS
AND CONTRACT CLAUSES
[FAC 2005–01; FAR Case 2002–021; Item
VIII]
RIN 9000–AJ75
Federal Acquisition Regulation; Use of
FAR Clause 52.244–6, Subcontracts for
Commercial Items
Department of Defense (DoD),
General Services Administration (GSA),
and National Aeronautics and Space
Administration (NASA).
ACTION: Final rule.
AGENCIES:
SUMMARY: The Civilian Agency
Acquisition Council and the Defense
Acquisition Regulations Council
(Councils) have agreed on a final rule
amending the Federal Acquisition
Regulation (FAR) to require that the
FAR clause, Subcontracts for
Commercial Items, be inserted in
solicitations and contracts other than
those for commercial items.
DATES: Effective Date: March 9, 2005.
FOR FURTHER INFORMATION CONTACT The
FAR Secretariat at (202) 501–4755 for
E:\FR\FM\09MRR2.SGM
09MRR2
Agencies
[Federal Register Volume 70, Number 45 (Wednesday, March 9, 2005)]
[Rules and Regulations]
[Pages 11761-11762]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-4092]
-----------------------------------------------------------------------
DEPARTMENT OF DEFENSE
GENERAL SERVICES ADMINISTRATION
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
48 CFR Parts 44 and 52
[FAC 2005-01; FAR Case 2003-024; Item VII]
RIN 9000-AK10
Federal Acquisition Regulation; Elimination of Certain
Subcontract Notification Requirements
AGENCIES: Department of Defense (DoD), General Services Administration
(GSA), and National Aeronautics and Space Administration (NASA).
ACTION: Interim rule with request for comments.
-----------------------------------------------------------------------
SUMMARY: The Civilian Agency Acquisition Council and the Defense
Acquisition Regulations Council (the Councils) have agreed to amend the
Federal Acquisition Regulation language regarding advance notification
requirements. This change is required to implement Section 842 of the
National Defense Authorization Act for Fiscal Year 2004, Public Law
108-136, which resulted in revisions to 10 U.S.C. 2306(e).
DATES: Effective Date: March 9, 2005.
Comment Date: Interested parties should submit comments to the FAR
Secretariat at the address shown below on or before May 9, 2005 to be
considered in the formulation of a final rule.
ADDRESSES: Submit comments identified by FAC 2005-01, FAR case 2003-024
by any of the following methods:
Federal eRulemaking Portal: https://www.regulations.gov.
Follow the instructions for submitting comments.
Agency Web Site: https://www.acqnet.gov/far/ProposedRules/
proposed.htm. Click on the FAR case number to submit comments.
E-mail: farcase.2003-024@gsa.gov. Include FAC 2005-01, FAR
case 2003-024 in the subject line of the message.
Fax: 202-501-4067.
Mail: General Services Administration, Regulatory
Secretariat (VIR), 1800 F Street, NW., Room 4035, ATTN: Laurieann
Duarte, Washington, DC 20405.
Instructions: Please submit comments only and cite FAC 2005-01, FAR
case 2003-024, in all correspondence related to this case. All comments
received will be posted without change to https://www.acqnet.gov/far/
ProposedRules/proposed.htm, including any personal information
provided.
FOR FURTHER INFORMATION CONTACT The FAR Secretariat at (202) 501-4755,
for information pertaining to status or publication schedules. For
clarification of content, contact Ms. Rhonda Cundiff, at (202) 501-
0044. Please cite FAC 2005-01, FAR case 2003-024.
SUPPLEMENTARY INFORMATION:
A. Background
This rule revises FAR 44.201-2, Advance notification requirements,
and amends Alternate I of FAR clause 52.244-2, Subcontracts. This
change is required in order to implement Section 842 of the National
Defense Authorization Act for Fiscal Year 2004, Public Law 108-136.
Section 842
[[Page 11762]]
removes the requirement for contractors under cost-reimbursement
contracts with the Department of Defense (DoD), Coast Guard, and
National Aeronautics and Space Administration (NASA) to notify the
agency before the award of any cost-plus-fixed-fee subcontract or any
fixed-price subcontract that exceeds the greater of the simplified
acquisition threshold or 5 percent of the total estimated cost of the
contract if the contractor maintains a purchasing system approved by
the contracting officer for the contract.
In addition, the rule makes a technical amendment to Alternate II
of FAR clause 52.244-2, Subcontracts. The rule deletes the reference to
paragraph (c) from paragraph (f)(2) of Alternate II because paragraph
(c) applies to fixed price type contracts, whereas Alternate II applies
to cost-reimbursement contracts.
This is not a significant regulatory action and, therefore, was not
subject to review under Section 6(b) of Executive Order 12866,
Regulatory Planning and Review, dated September 30, 1993. This rule is
not a major rule under 5 U.S.C. 804.
B. Regulatory Flexibility Act
This interim rule is not expected to have a significant economic
impact on a substantial number of small entities within the meaning of
the Regulatory Flexibility Act, 5 U.S.C. 601, et seq., because it will
have a small positive effect. Also, small businesses do not usually
hold prime contracts which are cost-reimbursement contracts, so this
section would not apply to them, and any changes would not apply.
Therefore, an Initial Regulatory Flexibility Analysis has not been
performed. We invite comments from small business concerns and other
interested parties. The Councils will consider comments from small
entities concerning the affected FAR Parts 44 and 52 in accordance with
5 U.S.C. 610. Interested parties must submit such comments separately
and should cite 5 U.S.C 601, et seq. (FAC 2005-01, FAR case 2003-024),
in correspondence.
C. Paperwork Reduction Act
The Paperwork Reduction Act does not apply because the changes to
the FAR do not impose information collection requirements that require
the approval of the Office of Management and Budget under 44 U.S.C.
3501, et seq.
D. Determination to Issue an Interim Rule
A determination has been made under the authority of the Secretary
of Defense (DoD), the Administrator of General Services (GSA), and the
Administrator of the National Aeronautics and Space Administration
(NASA) that urgent and compelling reasons exist to promulgate this
interim rule without prior opportunity for public comment. This action
is necessary to implement Section 842 of the National Defense
Authorization Act for Fiscal Year 2004, Public Law 108-136, which went
into effect November 24, 2003, and which resulted in revisions to 10
U.S.C. 2306 (e). However, pursuant to Public Law 98-577 and FAR 1.501,
the Councils will consider public comments received in response to this
interim rule in the formation of the final rule.
List of Subjects in 48 CFR Parts 44 and 52
Government procurement.
Dated: February 24, 2005.
Rodney P. Lantier,
Director, Contract Policy Division.
0
Therefore, DoD, GSA, and NASA amend 48 CFR parts 44 and 52 as set forth
below:
0
1. The authority citation for 48 CFR parts 44 and 52 is revised to read
as follows:
Authority: 40 U.S.C. 121(c); 10 U.S.C. chapter 137; and 42
U.S.C. 2473(c).
PART 44--SUBCONTRACTING POLICIES AND PROCEDURES
0
2. Revise section 44.201-2 to read as follows:
44.201-2 Advance notification requirements.
Under cost-reimbursement contracts, the contractor is required by
statute to notify the contracting officer as follows:
(a) For the Department of Defense, the Coast Guard, and the
National Aeronautics and Space Administration, unless the contractor
maintains an approved purchasing system, 10 U.S.C. 2306 requires
notification before the award of any cost-plus-fixed-fee subcontract,
or any fixed-price subcontract that exceeds the greater of the
simplified acquisition threshold or 5 percent of the total estimated
cost of the contract.
(b) For civilian agencies other than the Coast Guard and the
National Aeronautics and Space Administration, even if the contractor
has an approved purchasing system, 41 U.S.C. 254(b) requires
notification before the award of any cost-plus-fixed-fee subcontract,
or any fixed-price subcontract that exceeds either the simplified
acquisition threshold or 5 percent of the total estimated cost of the
contract.
PART 52--SOLICITATION PROVISIONS AND CONTRACT CLAUSES
0
3. Amend section 52.244-2--
0
a. In Alternate I, by removing ``(Aug 1998)'' and adding ``(MAR 2005)''
in its place, and revising the first sentence of paragraph (f)(2); and
0
b. In Alternate II, by removing ``(Aug 1998)'' and adding ``(MAR
2005)'' in its place, and in paragraph (f)(2) by removing ``(c), (d),''
and adding ``(d)'' in its place. The revised text reads as follows:
52.244-2 Subcontracts.
* * * * *
Alternate I * * *
(f)(2) Unless the Contractor maintains an approved purchasing
system, the Contractor shall notify the Contracting Officer reasonably
in advance of entering into any (i) cost-plus-fixed-fee subcontract, or
(ii) fixed-price subcontract that exceeds the greater of the simplified
acquisition threshold or 5 percent of the total estimated cost of this
contract. * * *
[FR Doc. 05-4092 Filed 3-8-05; 8:45 am]
BILLING CODE 6820-EP-S