CER Termobahia, LLC, et al.; Electric Rate and Corporate Filings, 11002-11004 [E5-904]
Download as PDF
11002
Federal Register / Vol. 70, No. 43 / Monday, March 7, 2005 / Notices
proceeding can ask for court review of
Commission orders in the proceeding.
The Commission strongly encourages
electronic filings of comments, protests,
and interventions via the Internet in lieu
of paper. See 18 CFR 385.2001(a)(1)(iii)
and the instructions on the
Commission’s Web site (https://
www.ferc.gov) under the ‘‘e-Filing’’ link.
Comment Date: March 9, 2005.
Magalie R. Salas,
Secretary.
[FR Doc. E5–914 Filed 3–4–05; 8:45 am]
BILLING CODE 6717–01–P
3. Pinnacle West Capital Corporation,
Arizona Public Service Company,
Pinnacle West Energy Corporation, APS
Energy Services, Inc.
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EG05–47–000, et al.]
CER Termobahia, LLC, et al.; Electric
Rate and Corporate Filings
February 28, 2005.
The following filings have been made
with the Commission. The filings are
listed in ascending order within each
docket classification.
1. CER Termobahia, LLC
[Docket No. EG05–47–000]
Take notice that on February 24, 2005,
CER Termobahia, LLC, a Delaware
limited liability company (Applicant),
with its principal executive office at
1930 Burnt Boat Drive, Bismarck, North
Dakota, 58503, filed with the Federal
Energy Regulatory Commission an
application for determination of exempt
wholesale generator status pursuant to
part 365 of the Commission’s
regulations and section 32 of the Public
Utility Holding Company Act of 1935,
as amended.
Applicant states it will own, in part,
a 190 MW natural-gas fired, combinedcycle electrical generating facility
located in the State of Bahia, near
Salvador, Brazil (the facility). Applicant
further states that it will be engaged
directly and exclusively in the business
of owning and operating an eligible
facility and none of the electric energy
produced from the facility will be sold
into the United States either at retail or
otherwise.
Comment Date: 5 p.m. Eastern Time
on March 17, 2005.
2. Public Service Company of New
Mexico
[Docket Nos. ER96–1551–011, ER01–615–
008]
Take notice that on February 18, 2005,
Public Service Company of New Mexico
(PNM) submitted a filing in response to
VerDate jul<14>2003
18:15 Mar 04, 2005
Jkt 205001
the Commission’s December 20, 2004
order in the above-captioned
proceedings. Public Service Company of
New Mexico, 109 FERC ¶ 61,296 (2004)
(December 20 Order). PNM states that
the purpose of its filing is to submit
revised market power analyses and
information as required by the
Commission in the December 20 Order.
PNM states that copies of the filing
were served on parties on the official
service lists in the above-captioned
proceedings.
Comment Date: 5 p.m. Eastern Time
on March 11, 2005.
[Docket Nos. ER00–2268–010, EL05–10–000,
ER99–4124–008, EL05–11–0000, ER00–
3312–009, EL05–12–000, ER99–4122–011,
EL05–13–000]
Take notice that on February 18, 2005,
the Pinnacle West Capital Corporation
(PWCC), the Arizona Public Service
Company (APS), the Pinnacle West
Energy Corporation (PWEC) and APS
Energy Services Company, Inc. (APSES)
(collectively, Pinnacle West Companies)
filed with the Commission a response to
the Commission’s Order dated
December 20, 2004, directing Pinnacle
West Companies to provide additional
information to the Commission to
supplement its market update for
authorization to sell at market-based
rates and various tariff amendments
filed on August 11, 2004.
Comment Date: 5 p.m. Eastern Time
on March 11, 2005.
4. Frederickson Power L.P.; EPCOR
Merchant and Capital (US) Inc.; EPCOR
Power Development, Inc.; EPDC, Inc.
[Docket Nos. ER01–2262–005, ER02–783–
003, ER02–852–003, ER02–855–003]
Take notice that, on February 22,
2005, Frederickson Power L.P., EPCOR
Merchant and Capital (US), Inc., EPCOR
Power Development, Inc., and EPDC,
Inc. (collectively, the EPCOR Parties)
submitted a triennial updated marketbased rate analysis.
The EPCOR Parties state that copies of
the filing were served on parties on the
official service lists in the abovereferenced proceedings.
Comment Date: 5 p.m. Eastern
Standard Time March 15, 2005.
5. Midwest Independent Transmission
System Operator, Inc.; Public Utilities
with Grandfathered Agreements in the
Midwest ISO Region
[Docket Nos. ER04–691–027, EL04–104–026 ]
Take notice that on February 23, 2005,
the Midwest Independent Transmission
PO 00000
Frm 00068
Fmt 4703
Sfmt 4703
System Operator, Inc. (Midwest ISO)
submitted a compliance filing pursuant
to the Commission’s January 24, 2005
Order in Midwest Independent
Transmission System Operator, Inc., et
al., 110 FERC ¶ 61,049 (2005). The
Midwest ISO has requested an April 1,
2005 effective date for the tariff pages
submitted in the compliance filing.
The Midwest ISO has requested
waiver of the service requirements set
forth in 18 CFR 385.2010. The Midwest
ISO states that it has electronically
served a copy of this filing, with
attachments, upon all Midwest ISO
Members, Member representatives of
Transmission Owners and NonTransmission Owners, the Midwest ISO
Advisory Committee participants, as
well as all state commissions within the
region. In addition, Midwest states that
the filing has been electronically posted
on the Midwest ISO’s Web site at
https://www.midwestiso.org under the
heading ‘‘Filings to FERC’’ for other
interested parties in this matter. The
Midwest ISO will provide hard copies
to any interested parties upon request.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
6. New England Power Pool
[Docket No. ER04–1255–001]
Take notice that on February 18, 2005
ISO New England Inc. (the ISO) and the
New England Power Pool (NEPOOL)
Participants Committee submitted a
compliance filing, including a report
entitled The Costs and Benefits of
Implementing a Day-Ahead Load
Response Program and revisions to
Appendix E to Section III of the ISO’s
Transmission, Markets and Services
Tariff (the Tariff), in response to the
requirements of the Commission’s
December 21, 2004 order in Docket No.
ER04–1255–000. NEPOOL and the ISO
requested a June 1, 2005 effective date
for the revisions to the tariff.
The ISO and the NEPOOL
Participants Committee state that copies
of the compliance filing were sent to the
NEPOOL Participants and the New
England state governors and regulatory
commissions, as well as all parties on
the official service lists in the abovecaptioned proceeding.
Comment Date: 5 p.m. Eastern Time
on March 11, 2005.
7. Unitil Energy Systems, Inc.
[Docket No. ER05–320–001]
Take notice that on February 23, 2005,
Unitil Energy Systems, Inc. (UES)
submitted a compliance filing pursuant
to the Commission’s order issued on
February 2, 2005 in Docket No. ER05–
320–000, Unitil Energy Systems, Inc.,
110 FERC ¶ 61,089 (2005).
E:\FR\FM\07MRN1.SGM
07MRN1
Federal Register / Vol. 70, No. 43 / Monday, March 7, 2005 / Notices
UES states that copies of the filing
were served on parties on the official
service list in the above-captioned
proceeding and on the New Hampshire
Public Utility Commission.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
8. Hot Spring Power Company, LP
[Docket No. ER05–570–001]
Take notice that on February 23, 2005,
Hot Spring Power Company, LP (Hot
Spring) filed a supplement to its
application filed February 11, 2005 in
Docket No. ER05–570–000 for
authorization to make wholesale sales of
electric energy, capacity, and ancillary
services at market-based rates, to
reassign transmission capacity, and to
resell firm transmission rights.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
9. Puget Sound Energy, Inc.
[Docket No. ER05–609–000]
Take notice that on February 18, 2005,
Puget Sound Energy Inc. (PSE)
submitted revised tariff sheets to its
open access transmission tariff
incorporating the changes directed by
the Commission in Order No. 2003-B,
Standardization of Generator
Interconnection Agreements and
Procedures, 109 FERC ¶ 61,287 (2004).
PSE states that electronic copies of the
filing were served on the Washington
Utilities and Transportation
Commission and PSE’s jurisdictional
customers.
Comment Date: 5 p.m. Eastern Time
on March 11, 2005.
10. PSI Energy, Inc.
[Docket No. ER05–634–000]
Take notice that on February 22, 2005,
PSI Energy, Inc. (PSI) tendered for filing
the transmission and local facilities
agreement for calendar year 2003
reconciliation between PSI and Wabash
Valley Power Association, Inc., and
between PSI and Indiana Municipal
Power Agency, designated as PSI’s Rate
Schedule FERC No. 253.
Comment Date: 5 p.m. Eastern Time
on March 15, 2005.
11. American Electric Power Service
Corporation
[Docket No. ER05–635–000]
Take notice that on February 22, 2005,
the American Electric Power Service
Corporation (AEPSC), tendered for filing
an Interconnection and Local Delivery
Service Agreement for Blue Ridge Power
Association (Blue Ridge), designated as
Substitute Service Agreement No. 181,
to the Operating Companies of the
American Electric Power System FERC
VerDate jul<14>2003
18:15 Mar 04, 2005
Jkt 205001
Electric Tariff Third Revised Volume
No. 6. AEPSC requests an effective date
of February 1, 2005.
AEPSC states that a copy of the filing
was served upon the Party and the
Virginia Public Service Commission.
Comment Date: 5 p.m. Eastern Time
on March 15, 2005.
12. Midwest Independent Transmission
System Operator, Inc.
[Docket No. ER05–636–000]
Take notice that on February 23, 2005,
the Midwest Independent Transmission
System Operator, Inc. (Midwest ISO)
submitted a Large Generator
Interconnection Agreement among
Columbia Community Windpower LLC,
American Transmission Company LLC
and the Midwest ISO.
Midwest ISO states that a copy of this
filing was served on the parties to this
Interconnection Agreement.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
13. Wisconsin Public Service
Corporation
Take notice that on February 23, 2005,
Wisconsin Public Service Corporation
(WPSC) tendered for filing, the actual
2004 values for billing for postemployment benefits (PEB) and postemployment benefits other than
pensions (PBOP) in its formula rates for:
(1) The W–1A tariff for full
requirements service; (2) the W–2A
tariff for partial requirements service;
and (3) Rate Schedule No. 51 for partial
requirements service for the City of
Marshfield. WPSC has also requests
waiver of the notice requirements to
allow it to apply the 2004 PEB and
PBOP values to the true-up of these
wholesale customers’ estimated capacity
rate billings for service during 2004 and
for estimated billing as of April 1, 2005.
WPSC states that copies of the filing
were served upon WPSC’s affected
wholesale customers, the Public Service
Commission of Wisconsin and the
Michigan Public Service Commission.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
14. Illinois Power Company
[Docket No. ER05–638–000]
Take notice that on February 23, 2005,
Illinois Power Company (Illinois Power)
submitted a Market-Based Rate Tariff
authorizing AmerenIP to engage in the
sale of electric energy, capacity and firm
rights at market-based rates and to
reassign transmission capacity rights at
negotiated rates. Illinois Power requests
an effective date of the later of April 1,
2005, or the first day of the Midwest
Frm 00069
Fmt 4703
Sfmt 4703
ISO’s Day 2 markets (currently expected
to be April 1, 2005).
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
15. Brascan Power Piney & Deep Creek
LLC
[Docket No. ER05–639–000]
Take notice that on February 23, 2005,
Brascan Power Piney & Deep Creek LLC
(Brascan Power PDC) submitted for
filing an application for market-based
rate authorization to sell energy,
capacity, and ancillary services, and
reassign transmission capacity and
resell firm transmission rights. Brascan
Power PDC also requests the waivers
and exemptions from regulation
typically granted to the holders of
market-based rate authorization. In
addition, Brascan Power PDC requests
waiver of the 60-day prior notice
requirement and requests expedited
consideration of its application for
market-based rate authorization.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
16. Cinergy Services, Inc.
[Docket No. ER05–637–000]
PO 00000
11003
[Docket No. ER05–640–000]
Take notice that on February 23, 2005,
Cinergy Services, Inc. (Cinergy
Services), on behalf of The Cincinnati
Gas & Electric Company (CG&E), PSI
Energy, Inc. (PSI) and Cinergy Power
Investments, Inc. submitted for filing a
revised Joint Generation Dispatch
Agreement between PSI and CG&E.
Cinergy Services states that copies of
the filing were served upon the Indiana
Utility Regulatory Commission.
Comment Date: 5 p.m. Eastern Time
on March 16, 2005.
Standard Paragraph
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211 and
385.214). Protests will be considered by
the Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all parties to this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
E:\FR\FM\07MRN1.SGM
07MRN1
11004
Federal Register / Vol. 70, No. 43 / Monday, March 7, 2005 / Notices
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–904 Filed 3–4–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. CP05–32–000 and CP05–32–
001]
Northwest Pipeline Corporation; Notice
of Availability of the Draft
Environmental Impact Statement for
the Proposed Capacity Replacement
Project
March 1, 2005.
The staff of the Federal Energy
Regulatory Commission (Commission or
FERC) has prepared a draft
environmental impact statement (EIS)
on the natural gas pipeline facilities and
abandonment activities proposed by
Northwest Pipeline Corporation
(Northwest) in the above-referenced
docket. The Capacity Replacement
Project would be located in various
counties in Washington.
The draft EIS was prepared to satisfy
the requirements of the National
Environmental Policy Act (NEPA). The
FERC staff concludes that approval of
the proposed project with appropriate
mitigating measures as recommended,
would have limited adverse
environmental impact.
The U.S. Army Corps of Engineers
(COE) is participating as a cooperating
agency in the preparation of the EIS
because the project would require
permits pursuant to section 404 of the
Clean Water Act (33 United States Code
(U.S.C.) 1344) and section 10 of the
Rivers and Harbors Act (33 U.S.C. 403).
The COE would adopt the EIS pursuant
to Title 40 Code of Federal Regulations
(CFR) Section 1506.3 if, after an
VerDate jul<14>2003
18:15 Mar 04, 2005
Jkt 205001
independent review of the document, it
concludes that its comments and
suggestions have been satisfied.
The Washington State Department of
Ecology (WDOE) is participating as a
cooperating agency in the preparation of
the EIS because it has been designated
the lead agency under the State
Environmental Policy Act (SEPA) and is
responsible for compliance with SEPA
procedural requirements as well as for
compiling and assessing information on
the environmental aspects of the
proposal for all agencies with
jurisdiction in Washington. NEPA
documents may be used to meet SEPA
requirements if the requirements of the
State of Washington Administrative
Code (WAC) 197–11–610 and 197–11–
630 are met. In compliance with SEPA
requirements, this Notice of Availability
includes the information required for a
SEPA EIS Cover Letter and Fact Sheet.
When the final EIS is completed, the
WDOE would adopt it if an independent
review of the document confirms that it
meets the WDOE’s environmental
review standards.
The purpose of the Capacity
Replacement Project is to replace the
majority of the delivery capacity of
Northwest’s existing 268-mile-long, 26inch-diameter pipeline between Sumas
and Washougal, Washington in response
to a Corrective Action Order issued by
the U.S. Department of Transportation.
The proposed facilities are designed to
provide up to 360 thousand dekatherms
per day of natural gas transportation
capacity.
This draft EIS addresses the potential
environmental effects (beneficial and
adverse) of Northwest’s proposal to:
• Construct and operate 79.5 miles of
new 36-inch-diameter pipeline in 4
separate loops 1 in Whatcom, Skagit,
Snohomish, King, Pierce, and Thurston
Counties;
• Modify 5 existing compressor
stations, one each in Whatcom, Skagit,
Snohomish, Lewis, and Clark Counties
for a total of 10,760 net horsepower of
new compression;
• Install various pig 2 launchers, pig
receivers, and mainline valves;
• Abandon the existing 26-inchdiameter pipeline between Sumas and
Washougal with the exception of a short
segment within and between the
existing Jackson Prairie Meter Station
and the Chehalis Compressor Station;
and
1 A loop is a segment of pipeline that is usually
installed adjacent to an existing pipeline and
connected to it at both ends. The loop allows more
gas to be moved through the system.
2 A pig is an internal tool that can be used to
clean and dry a pipeline and/or to inspect it for
damage or corrosion.
PO 00000
Frm 00070
Fmt 4703
Sfmt 4703
• Use 13 pipe storage and contractor
yards on a temporary basis to support
construction activities.
Northwest proposes to begin
construction in March 2006 3 and place
the facilities in service by November 1,
2006. Abandonment of the 26-inchdiameter facilities that are currently in
service cannot be completed until the
Capacity Replacement Project is placed
in service. All abandonment activities
would be completed on or before
December 31, 2006.
The FERC, the COE, and the WDOE
have three alternative courses of action
in considering Northwest’s proposal.
These options include granting
authorizations with or without
conditions, denying authorizations, or
postponing action pending further
study. In accordance with the Council
on Environmental Quality (CEQ)
regulations implementing NEPA, no
agency decision on the proposed action
may be made until 30 days after the U.S.
Environmental Protection Agency (EPA)
publishes a Notice of Availability of the
final EIS in the Federal Register.
However, the CEQ regulations provide
an exception to this rule when an
agency decision is subject to a formal
internal appeal process that allows other
agencies or the public to make their
views known. This is the case at the
FERC, where any Commission decision
on the proposed action would be subject
to a 30-day rehearing period. Therefore,
the lead agency decision may be made
at the same time that notice of the final
EIS is published by the EPA, allowing
the appeal periods to run concurrently.
After notice of the final EIS is
published by the EPA, the COE would
issue its own Record of Decision (ROD)
adopting the EIS. The ROD would
include the COE’s section 404(b)(1)
analysis. After issuance of the ROD, the
COE could issue the section 404 and
section 10 permits.
After the final EIS is issued, the
WDOE would adopt it by identifying the
document and stating why it is being
adopted using the adoption form in
WAC 197–11–965. The adoption form
would be circulated to agencies with
jurisdiction and to persons or
organizations that have expressed an
interest in the proposal. No action may
be taken on the proposal until 7 days
after the statement of adoption form has
been issued. Once the 7-day waiting
period is completed, the WDOE could
begin issuing permits. Other state and
local agencies cannot issue permits until
the adoption procedure is complete.
3 Northwest has requested that three river
crossings be authorized to begin in late 2005 if
weather permits.
E:\FR\FM\07MRN1.SGM
07MRN1
Agencies
[Federal Register Volume 70, Number 43 (Monday, March 7, 2005)]
[Notices]
[Pages 11002-11004]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-904]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EG05-47-000, et al.]
CER Termobahia, LLC, et al.; Electric Rate and Corporate Filings
February 28, 2005.
The following filings have been made with the Commission. The
filings are listed in ascending order within each docket
classification.
1. CER Termobahia, LLC
[Docket No. EG05-47-000]
Take notice that on February 24, 2005, CER Termobahia, LLC, a
Delaware limited liability company (Applicant), with its principal
executive office at 1930 Burnt Boat Drive, Bismarck, North Dakota,
58503, filed with the Federal Energy Regulatory Commission an
application for determination of exempt wholesale generator status
pursuant to part 365 of the Commission's regulations and section 32 of
the Public Utility Holding Company Act of 1935, as amended.
Applicant states it will own, in part, a 190 MW natural-gas fired,
combined-cycle electrical generating facility located in the State of
Bahia, near Salvador, Brazil (the facility). Applicant further states
that it will be engaged directly and exclusively in the business of
owning and operating an eligible facility and none of the electric
energy produced from the facility will be sold into the United States
either at retail or otherwise.
Comment Date: 5 p.m. Eastern Time on March 17, 2005.
2. Public Service Company of New Mexico
[Docket Nos. ER96-1551-011, ER01-615-008]
Take notice that on February 18, 2005, Public Service Company of
New Mexico (PNM) submitted a filing in response to the Commission's
December 20, 2004 order in the above-captioned proceedings. Public
Service Company of New Mexico, 109 FERC ] 61,296 (2004) (December 20
Order). PNM states that the purpose of its filing is to submit revised
market power analyses and information as required by the Commission in
the December 20 Order.
PNM states that copies of the filing were served on parties on the
official service lists in the above-captioned proceedings.
Comment Date: 5 p.m. Eastern Time on March 11, 2005.
3. Pinnacle West Capital Corporation, Arizona Public Service Company,
Pinnacle West Energy Corporation, APS Energy Services, Inc.
[Docket Nos. ER00-2268-010, EL05-10-000, ER99-4124-008, EL05-11-0000,
ER00-3312-009, EL05-12-000, ER99-4122-011, EL05-13-000]
Take notice that on February 18, 2005, the Pinnacle West Capital
Corporation (PWCC), the Arizona Public Service Company (APS), the
Pinnacle West Energy Corporation (PWEC) and APS Energy Services
Company, Inc. (APSES) (collectively, Pinnacle West Companies) filed
with the Commission a response to the Commission's Order dated December
20, 2004, directing Pinnacle West Companies to provide additional
information to the Commission to supplement its market update for
authorization to sell at market-based rates and various tariff
amendments filed on August 11, 2004.
Comment Date: 5 p.m. Eastern Time on March 11, 2005.
4. Frederickson Power L.P.; EPCOR Merchant and Capital (US) Inc.; EPCOR
Power Development, Inc.; EPDC, Inc.
[Docket Nos. ER01-2262-005, ER02-783-003, ER02-852-003, ER02-855-003]
Take notice that, on February 22, 2005, Frederickson Power L.P.,
EPCOR Merchant and Capital (US), Inc., EPCOR Power Development, Inc.,
and EPDC, Inc. (collectively, the EPCOR Parties) submitted a triennial
updated market-based rate analysis.
The EPCOR Parties state that copies of the filing were served on
parties on the official service lists in the above-referenced
proceedings.
Comment Date: 5 p.m. Eastern Standard Time March 15, 2005.
5. Midwest Independent Transmission System Operator, Inc.; Public
Utilities with Grandfathered Agreements in the Midwest ISO Region
[Docket Nos. ER04-691-027, EL04-104-026 ]
Take notice that on February 23, 2005, the Midwest Independent
Transmission System Operator, Inc. (Midwest ISO) submitted a compliance
filing pursuant to the Commission's January 24, 2005 Order in Midwest
Independent Transmission System Operator, Inc., et al., 110 FERC ]
61,049 (2005). The Midwest ISO has requested an April 1, 2005 effective
date for the tariff pages submitted in the compliance filing.
The Midwest ISO has requested waiver of the service requirements
set forth in 18 CFR 385.2010. The Midwest ISO states that it has
electronically served a copy of this filing, with attachments, upon all
Midwest ISO Members, Member representatives of Transmission Owners and
Non-Transmission Owners, the Midwest ISO Advisory Committee
participants, as well as all state commissions within the region. In
addition, Midwest states that the filing has been electronically posted
on the Midwest ISO's Web site at https://www.midwestiso.org under the
heading ``Filings to FERC'' for other interested parties in this
matter. The Midwest ISO will provide hard copies to any interested
parties upon request.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
6. New England Power Pool
[Docket No. ER04-1255-001]
Take notice that on February 18, 2005 ISO New England Inc. (the
ISO) and the New England Power Pool (NEPOOL) Participants Committee
submitted a compliance filing, including a report entitled The Costs
and Benefits of Implementing a Day-Ahead Load Response Program and
revisions to Appendix E to Section III of the ISO's Transmission,
Markets and Services Tariff (the Tariff), in response to the
requirements of the Commission's December 21, 2004 order in Docket No.
ER04-1255-000. NEPOOL and the ISO requested a June 1, 2005 effective
date for the revisions to the tariff.
The ISO and the NEPOOL Participants Committee state that copies of
the compliance filing were sent to the NEPOOL Participants and the New
England state governors and regulatory commissions, as well as all
parties on the official service lists in the above-captioned
proceeding.
Comment Date: 5 p.m. Eastern Time on March 11, 2005.
7. Unitil Energy Systems, Inc.
[Docket No. ER05-320-001]
Take notice that on February 23, 2005, Unitil Energy Systems, Inc.
(UES) submitted a compliance filing pursuant to the Commission's order
issued on February 2, 2005 in Docket No. ER05-320-000, Unitil Energy
Systems, Inc., 110 FERC ] 61,089 (2005).
[[Page 11003]]
UES states that copies of the filing were served on parties on the
official service list in the above-captioned proceeding and on the New
Hampshire Public Utility Commission.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
8. Hot Spring Power Company, LP
[Docket No. ER05-570-001]
Take notice that on February 23, 2005, Hot Spring Power Company, LP
(Hot Spring) filed a supplement to its application filed February 11,
2005 in Docket No. ER05-570-000 for authorization to make wholesale
sales of electric energy, capacity, and ancillary services at market-
based rates, to reassign transmission capacity, and to resell firm
transmission rights.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
9. Puget Sound Energy, Inc.
[Docket No. ER05-609-000]
Take notice that on February 18, 2005, Puget Sound Energy Inc.
(PSE) submitted revised tariff sheets to its open access transmission
tariff incorporating the changes directed by the Commission in Order
No. 2003-B, Standardization of Generator Interconnection Agreements and
Procedures, 109 FERC ] 61,287 (2004).
PSE states that electronic copies of the filing were served on the
Washington Utilities and Transportation Commission and PSE's
jurisdictional customers.
Comment Date: 5 p.m. Eastern Time on March 11, 2005.
10. PSI Energy, Inc.
[Docket No. ER05-634-000]
Take notice that on February 22, 2005, PSI Energy, Inc. (PSI)
tendered for filing the transmission and local facilities agreement for
calendar year 2003 reconciliation between PSI and Wabash Valley Power
Association, Inc., and between PSI and Indiana Municipal Power Agency,
designated as PSI's Rate Schedule FERC No. 253.
Comment Date: 5 p.m. Eastern Time on March 15, 2005.
11. American Electric Power Service Corporation
[Docket No. ER05-635-000]
Take notice that on February 22, 2005, the American Electric Power
Service Corporation (AEPSC), tendered for filing an Interconnection and
Local Delivery Service Agreement for Blue Ridge Power Association (Blue
Ridge), designated as Substitute Service Agreement No. 181, to the
Operating Companies of the American Electric Power System FERC Electric
Tariff Third Revised Volume No. 6. AEPSC requests an effective date of
February 1, 2005.
AEPSC states that a copy of the filing was served upon the Party
and the Virginia Public Service Commission.
Comment Date: 5 p.m. Eastern Time on March 15, 2005.
12. Midwest Independent Transmission System Operator, Inc.
[Docket No. ER05-636-000]
Take notice that on February 23, 2005, the Midwest Independent
Transmission System Operator, Inc. (Midwest ISO) submitted a Large
Generator Interconnection Agreement among Columbia Community Windpower
LLC, American Transmission Company LLC and the Midwest ISO.
Midwest ISO states that a copy of this filing was served on the
parties to this Interconnection Agreement.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
13. Wisconsin Public Service Corporation
[Docket No. ER05-637-000]
Take notice that on February 23, 2005, Wisconsin Public Service
Corporation (WPSC) tendered for filing, the actual 2004 values for
billing for post-employment benefits (PEB) and post-employment benefits
other than pensions (PBOP) in its formula rates for: (1) The W-1A
tariff for full requirements service; (2) the W-2A tariff for partial
requirements service; and (3) Rate Schedule No. 51 for partial
requirements service for the City of Marshfield. WPSC has also requests
waiver of the notice requirements to allow it to apply the 2004 PEB and
PBOP values to the true-up of these wholesale customers' estimated
capacity rate billings for service during 2004 and for estimated
billing as of April 1, 2005.
WPSC states that copies of the filing were served upon WPSC's
affected wholesale customers, the Public Service Commission of
Wisconsin and the Michigan Public Service Commission.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
14. Illinois Power Company
[Docket No. ER05-638-000]
Take notice that on February 23, 2005, Illinois Power Company
(Illinois Power) submitted a Market-Based Rate Tariff authorizing
AmerenIP to engage in the sale of electric energy, capacity and firm
rights at market-based rates and to reassign transmission capacity
rights at negotiated rates. Illinois Power requests an effective date
of the later of April 1, 2005, or the first day of the Midwest ISO's
Day 2 markets (currently expected to be April 1, 2005).
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
15. Brascan Power Piney & Deep Creek LLC
[Docket No. ER05-639-000]
Take notice that on February 23, 2005, Brascan Power Piney & Deep
Creek LLC (Brascan Power PDC) submitted for filing an application for
market-based rate authorization to sell energy, capacity, and ancillary
services, and reassign transmission capacity and resell firm
transmission rights. Brascan Power PDC also requests the waivers and
exemptions from regulation typically granted to the holders of market-
based rate authorization. In addition, Brascan Power PDC requests
waiver of the 60-day prior notice requirement and requests expedited
consideration of its application for market-based rate authorization.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
16. Cinergy Services, Inc.
[Docket No. ER05-640-000]
Take notice that on February 23, 2005, Cinergy Services, Inc.
(Cinergy Services), on behalf of The Cincinnati Gas & Electric Company
(CG&E), PSI Energy, Inc. (PSI) and Cinergy Power Investments, Inc.
submitted for filing a revised Joint Generation Dispatch Agreement
between PSI and CG&E.
Cinergy Services states that copies of the filing were served upon
the Indiana Utility Regulatory Commission.
Comment Date: 5 p.m. Eastern Time on March 16, 2005.
Standard Paragraph
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Applicant and all parties to this proceeding.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies
[[Page 11004]]
of the protest or intervention to the Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-904 Filed 3-4-05; 8:45 am]
BILLING CODE 6717-01-P