Download as PDF Federal Register / Vol. 70, No. 41 / Thursday, March 3, 2005 / Notices 1. New England Power Company [Docket No. ER05–529–001] Take notice that on February 22, 2005, New England Power Company (NEP) filed an amendment to its January 31, 2005, filing in Docket No. ER05–529– 000. NEP states that the amendment consists of a substitute Second Revised Service Agreement No. 116 for network integration transmission service under NEP’s Open Access Transmission Tariff, Second Revised Volume No. 9 between NEP and USGen New England, Inc. (USGen). NEP request an effective date of January 1, 2005. NEP states that copies of this filing have been served on USGen and regulators in the States of Massachusetts and Rhode Island. Comment Date: 5 p.m. eastern time on March 15, 2005. 2. MidAmerican Energy Company [Docket No. ER05–624–000] Take notice that on February 22, 2005, MidAmerican Energy Company (MidAmerican), refiled with the Commission an amended Network Integration Transmission Service Agreement between MidAmerican and the City of Sergeant Bluff, Iowa, dated December 13, 2004, to correct a typographical error in the header of the agreement. MidAmerican has served a copy of the filing on Sergeant Bluff, the Iowa Utilities Board, the Illinois Commerce Commission and the South Dakota Public Utilities Commission. Comment Date: 5 p.m. eastern time on March 7, 2005. 3. Texas-New Mexico Power Company [Docket No. ER05–625–000] Take notice that on February 22, 2005, Texas-New Mexico Power Company (TNMP) filed new and revised tariff sheets to its open access transmission tariff (OATT) incorporating the changes directed by the Commission in Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC¶ 61,287 (2004). TNMP states that a copy of the filing has been mailed to its OATT customers as well as the New Mexico Public Regulation Commission. Comment Date: 5 p.m. eastern time on March 15, 2005. 4. Cogentrix Lawrence County, LLC [Docket No. ER05–630–000] Take notice that on February 22, 2005, Cogentrix Lawrence County, LLC (Cogentrix Lawrence) filed a Notice of Cancellation of its market-based rate electric tariff, FERC Electric Tariff, VerDate jul<14>2003 16:38 Mar 02, 2005 Jkt 205001 Original Volume No. 1, effective February 22, 2005. Comment Date: 5 p.m. eastern time on March 15, 2005. 5. Pataula Electric Membership Corporation [Docket No. ER05–631–000] Take notice that on February 22, 2005, Pataula Electric Membership Corporation (Pataula) submitted for filing with the Federal Energy Regulatory Commission a petition for authority to sell power at market-based rates, acceptance of proposed rate schedule, and granting of certain waivers. Pataula requests an effective date for its proposed rate schedule that would be 60 days from the date of filing of the petition or the date of the order accepting Pataula’s rate schedule for filing. Comment Date: 5 p.m. eastern time on March 15, 2005. 6. Complete Energy Services, Inc. [Docket No. ER05–632–000] Take notice that on February 22, 2005, Complete Energy Services, Inc. tendered for filing a Notice of Cancellation of market-based rate authority, Rate Schedule FERC No. 1 as authorized in Docket No. ER99–3033–000 on August 5, 1999. Comment Date: 5 p.m. eastern time on March 15, 2005. 10391 appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant and all parties to this proceeding. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Linda Mitry, Deputy Secretary. [FR Doc. E5–835 Filed 3–2–05; 8:45 am] BILLING CODE 6717–01–P 7. The Dayton Power and Light Company; DPL Energy, Inc. DEPARTMENT OF ENERGY [Docket Nos. ER05–633–000, ER96–2602– 008, and ER96–2601–019] Federal Energy Regulatory Commission Take notice that, on February 22, 2005, The Dayton Power and Light Company and DPL Energy, Inc. (collectively, Dayton) submitted a compliance filing pursuant to the Commission’s Order in Dayton Power and Light Company, 109 FERC ¶ 61,268 (2004). Dayton states that copies of the filing were served on parties on the official service list in the above-captioned dockets. Comment Date: 5 p.m. eastern time on March 15, 2005. Standard Paragraph Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as PO 00000 Frm 00039 Fmt 4703 Sfmt 4703 [Docket No. EL02–23–006, et al.] Consolidated Edison Company of New York Inc., et al.; Electric Rate and Corporate Filings February 24, 2005. The following filings have been made with the Commission. The filings are listed in ascending order within each docket classification. 1. Consolidated Edison Company of New York Inc. [Docket No. EL02–23–006] Take notice that on February 18, 2005, the New York Independent System Operator, Inc., PJM Interconnection, L.L.C. and Public Service Electric and Gas Company (Filing Parties) submitted a joint compliance filing pursuant to the Commission’s August 2, 2004, Opinion No. 476 in Docket No. EL02–23–000 and the Presiding Administrative Law Judge’s January 24, 2005, Order Establishing Procedures, in Docket No. El02–23–003. E:\FR\FM\03MRN1.SGM 03MRN1 10392 Federal Register / Vol. 70, No. 41 / Thursday, March 3, 2005 / Notices The Filing Parties state that copies of the filing were served on the parties on the official service list in Docket No. EL02–23–000, the New York State Public Service Commission, and all utility regulatory commissions in the PJM region. Comment Date: 5 p.m. eastern time on March 11, 2005. 2. California Independent System Operator System, Pacific Gas and Electric Company, San Diego Gas and Electric Company, Southern California Edison Company [Docket Nos. ER04–445–007, ER04–435–009, ER04–441–006, ER04–443–006] Take notice that on February 18, 2005, the California Independent System Operator Corporation, Pacific Gas and Electric Company, San Diego Gas and Electric Company, and Southern California Edison Company (collectively the Filing Parties) jointly submitted for filing a Standard Large Generator Interconnection Agreement in compliance with Order No. 2003–B, 109 FERC ¶ 61,287 (2004). The Filing Parties state that the Standard Large Generator Interconnection Agreement is intended to function as a stand alone pro forma agreement and is not intended to be incorporated into the tariffs of any of the Filing Parities. Comment Date: 5 p.m. eastern time on March 11, 2005. 3. California Independent System Operator Corporation 5. Mirant Delta, LLC and Mirant Potrero, LLC [Docket No. ER05–343–002] Take notice that, on February 18, 2005, Mirant Delta, LLC and Mirant Potrero, LLC (Mirant) submitted revised tariff sheets in compliance with the Commission’s Order in Mirant Delta, LLC and Mirant Potrero, LLC, 110 FERC ¶ 61,136 (2005) in Docket Nos. ER05– 343–000 and ER05–343–001. Mirant states that copies of the filing were served on parties on the official service list in the above-captioned proceeding. Comment Date: 5 p.m. eastern time on March 11, 2005. Entergy Mississippi, Inc., and Entergy New Orleans, Inc., submitted tariff sheets reflecting the revisions to the pro forma Standard Large Generator Interconnection Procedures and the Standard Large Generator Interconnection Agreement set out in the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). Comment Date: 5 p.m. eastern time on March 11, 2005. 9. Southwest Power Pool, Inc. [Docket No. ER05–604–000] Take notice that on February 18, 2005, Northeast Utilities Service Company (NUSCO), on behalf of The Connecticut Light and Power Company, Western Massachusetts Electric Company, Holyoke Water Power Company and Public Service Company of New Hampshire, submitted a revised Notice of Cancellation of the rate schedules for sales of electricity to the Town of Danvers Electric Division, Littleton Electric Light Department, Mansfield Municipal Electric Department, and UNITIL Power Corporation, originally filed on December 28, 2004. Comment Date: 5 p.m. eastern time on March 11, 2005. Take notice that on February 18, 2005, Southwest Power Pool, Inc. (SPP) submitted tariff sheets to its open access transmission tariff incorporating the changes directed by the Commission in Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). SPP requests an effective date of January 19, 2005. SPP states that copies of the filing have been served on the parties on the official service list in Docket no. ER04– 434–000, and on all SPP members, customers, and state commissions within the region. In addition, SPP states that the filing has been posted electronically on its Web site at https:// www.spp.org and that it will provide hard copies upon request. Comment Date: 5 p.m. eastern time on March 11, 2005. 6. Northeast Utilities Service Company [Docket No. ER05–385–001] 7. Tampa Electric Company 10. PJM Interconnection, L.L.C. [Docket No. ER04–445–008] [Docket No. ER05–602–000] [Docket No. ER05–605–000] Take notice that on February 18, 2005, the California Independent System Operator Corporation (ISO), pursuant to Order No. 2003–B, 109 FERC ¶ 61,287 (2004) submitted for filing Standard Large Generator Interconnection Procedures for incorporation into the ISO Tariff. Comment Date: 5 p.m. eastern time on March 11, 2005. Take notice that on February 18, 2005, Tampa Electric Company (Tampa Electric) submitted tariff sheets for inclusion in its open access transmission tariff revising the Large Generator Interconnection Procedures and the Large Generator Interconnection Agreement in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). Tampa Electric requests an effective date of January 19, 2005. Tampa Electric states that copies of the filing have been served on the customers under Tampa Electric’s open access transmission tariff and the Florida Public Service Commission. Comment Date: 5 p.m. eastern time on March 11, 2005. Take notice that on February 18, 2005, PJM Interconnection, L.L.C. (PJM) submitted for filing an executed interconnection service agreement and an executed construction service agreement among PJM, Pine Hurst Acres, and PPL Electric Utilities. PJM requests a January 20, 2005, effective date. PJM states that copies of the filing were served on the parties to the agreements and the state regulatory commissions within the PJM region. Comment Date: 5 p.m. eastern time on March 11, 2005. 4. PPL Electric Utilities Corporation [Docket No. ER05–104–001] Take notice that on February 18, 2005, PPL Electric Utilities Corporation (PPL Electric) submitted a response to the Commission’s deficiency letter issued on December 22, 2004, regarding PPL Electric’s October 29, 2004, filing of A Second Revised Service Agreement between PPL Electric and Metropolitan Edison Company. PPL states that copies of the filing were served upon parties on the official service list. Comment Date: 5 p.m. eastern time on March 11, 2005. VerDate jul<14>2003 16:38 Mar 02, 2005 Jkt 205001 8. Entergy Service, Inc. [Docket No. ER05–603–000] Take notice that on February 18, 2005, Entergy Services, Inc. (Entergy) on behalf of Entergy Arkansas, Inc., Entergy Gulf States, Inc., Entergy Louisiana, Inc., PO 00000 Frm 00040 Fmt 4703 Sfmt 4703 11. Idaho Power Company [Docket No. ER05–606–000] Take notice that on February 18, 2005, Idaho Power Company submitted tariff sheets to its open access transmission tariff incorporating the changes directed by the Commission in Order No. 2003– B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). Comment Date: 5 p.m. eastern time on March 11, 2005. E:\FR\FM\03MRN1.SGM 03MRN1 Federal Register / Vol. 70, No. 41 / Thursday, March 3, 2005 / Notices 12. Valley Electric Association, Inc. [Docket No. ER05–607–000] Take notice that on February 18, 2005, Valley Electric Association, Inc. submitted revised tariff sheets to its open access transmission tariff incorporating the changes directed by the Commission in Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). Comment Date: 5 p.m. eastern time on March 11, 2005. 13. Tuscon Electric Power Company and UNS Electric, Inc. [Docket No. ER05–610–000] Take notice that on February 18, 2005, Tuscon Electric Power Company and UNS Electric, Inc. submitted revised tariff sheets to its open access transmission tariff incorporating the changes directed by the Commission in Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). Comment Date: 5 p.m. eastern time on March 11, 2005. 14. Bridgeport Energy LLC [Docket No. ER05–611–000] Take notice that on February 18, 2005, Bridgeport Energy, LLC (Bridgeport) tendered for filing its proposed FERC Electric Tariff, Original Volume No. 2 and supporting costs data for Bridgeport’s cost-of-service agreement with ISO–New England, Inc. (ISO–NE) in order to receive compensation for the provision of reliability services. Bridgeport states that a copy of the filing has been served on ISO–NE. Comment Date: 5 p.m. eastern time on March 11, 2005. 15. Southern California Edison Company [Docket No. ER05–612–000] Take notice that on February 18, 2005, Southern California Edison Company (SCE) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). SCE states that copies of the filing were served on the parties on the official service list for Docket No. ER04– 435–000. Comment Date: 5 p.m. eastern time on March 11, 2005. 16. Southern Company Services, Inc. [Docket No. ER05-613-000] Take notice that on February 18, 2005, Southern Company Services, Inc. on VerDate jul<14>2003 16:38 Mar 02, 2005 Jkt 205001 behalf of Alabama Power Company, Georgia Power Company, Gulf Power Company, Mississippi Power Company and Savannah Electric and Power Company (collectively Southern Companies) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). SCS states that this filing is posted on Southern Companies’ OASIS for download by any person and that Southern Companies will provide copies of the filing upon request. Comment Date: 5 p.m. eastern time on March 11, 2005. 17. El Paso Electric Company [Docket No. ER05–614–000] Take notice that on February 18, 2005, El Paso Electric Company (EPE) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). EPE states that copies of the filing were served on all persons on the service list for Docket No. ER04–448– 000, the Public Utility Commission of Texas and the New Mexico Public Regulation Commission. Comment Date: 5 p.m. eastern Time on March 11, 2005. 18. Southern California Edison Company [Docket No. ER05–615–000] Take notice that on February 18, 2005, Southern California Edison Company (SCE) tendered for filing revisions to the facilities charges under the interconnection facilities agreement, FERC Electric Tariff, First Revised Volume No. 5, Service Agreement No. 109 and service agreement for wholesale distribution service, FERC Electric Tariff, First Revised Volume No. 5, Service Agreement No. 110 between SCE and FPL Energy Green Power Wind LLC. SCE states that copies of the filing were served on the Public Utilities Commission of the State of California and FPL Energy Green Power Wind LLC. Comment Date: 5 p.m. eastern time on March 11, 2005. 19. Xcel Energy Services Inc. [Docket No. ER05–616–000] Take notice that on February 18, 2005, Xcel Energy Services Inc. submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, PO 00000 Frm 00041 Fmt 4703 Sfmt 4703 10393 Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). Comment Date: 5 p.m. eastern time on March 11, 2005. 20. El Segundo Power, LLC [Docket No. ER05–617–000] Take notice that on February 18, 2005, El Segundo Power, LLC (El Segundo) tendered for filing an amendment to its Rate Schedule FERC No. 2, a reliability must-run agreement between El Segundo and the California Independent System Operator Corporation (CAISO). El Segundo requests an effective date of April 15, 2005. El Segundo states that copies of the filing were served on CAISO, Southern California Edison Company, the California Electricity Oversight Board, and the California Public Utilities Commission. Comment Date: 5 p.m. eastern time on March 11, 2005. 21. Midwest Independent Transmission System Operator, Inc. [Docket No. ER05–618–000] Take notice that on February 18, 2005, Midwest Independent Transmission System Operator, Inc. (Midwest ISO) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). The Midwest ISO states that it has electronically served a copy of this filing, with attachments, upon all Midwest ISO members, member representatives of transmission owners and non-transmission owners, the Midwest ISO Advisory Committee participants, as well as all state commissions within the regions. The Midwest ISO also states that the filing has been posted on Midwest ISO’s Web site at https://www.midwestiso.org under the heading ‘‘Filings to FERC.’’ Comment Date: 5 p.m. eastern time on March 11, 2005. 22. Black Hills Power, Inc.; Basin Electric Power Cooperative; Powder River Energy Corporation [Docket No. ER05–619–000] Take notice that on February 18, 2005, Black Hills Power, Inc. on behalf of itself, Basin Electric Power Cooperative, and Powder River Energy Corporation submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). E:\FR\FM\03MRN1.SGM 03MRN1 10394 Federal Register / Vol. 70, No. 41 / Thursday, March 3, 2005 / Notices Comment Date: 5 p.m. eastern time on March 11, 2005. 23. Ohio Valley Electric Corporation [Docket No. ER05–621–000] Take notice that on February 18, 2005, Ohio Valley Electric Corporation (OVEC) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). OVEC states that a copy of the filing has been mailed to its jurisdictional customers and to each state public service commission that has retail jurisdiction over such customers. Comment Date: 5 p.m. eastern time on March 11, 2005. 24. Carolina Power & Light Company, Florida Power Corporation [Docket No. ER05–622–000] Take notice that on February 18, 2005, Carolina Power & Light Company (CP&L) and Florida Power Corporation (FPC) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). CP&L and FPC state that a copy of the filing was served on their transmission customers, the North Carolina Utilities Commission, the Public Service Commission of South Carolina and the Florida Public Service Commission. Comment Date: 5 p.m. eastern time on March 11, 2005. 25. Duke Energy Washington, LLC [Docket No. ER05–623–000] Take notice that on February 18, 2005, Duke Energy Washington, LLC (Duke Washington) tendered for filing proposed tariff and supporting cost data for its monthly revenue requirement for reactive supply and voltage control from generation sources service provided to PJM Interconnection, L.L.C.(PJM). Duke Washington requests an effective date of March 1, 2005. Duke Washington states that it has served a copy of the filing on PJM. Comment Date: 5 p.m. eastern time on March 11, 2005. 26. PJM Interconnection, L.L.C. [Docket No. ER05–626–000] Take notice that on February 18, 2005, PJM Interconnection, L.L.C. (PJM) submitted revised tariff sheets in compliance with the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 VerDate jul<14>2003 16:38 Mar 02, 2005 Jkt 205001 (2004). PJM states that the revisions have an effective date of February 18, 2005. PJM states that copies of the filing have been served on all PJM members and the utility regulatory commissions in the PJM region. Comment Date: 5 p.m. eastern time on March 11, 2005. 27. FPL Energy Oklahoma Wind, LLC [Docket No. ER05–628–000] Take notice that on February 18, 2005, FPL Energy Oklahoma Wind, LLC (Oklahoma Wind) submitted a shared facilities agreement between Oklahoma Wind and FPL Energy Sooner Wind, LLC designated as Rate Schedule FERC No. 1. Oklahoma Wind requests an effective date of September 26, 2003. Oklahoma Wind states that copies of the filing were served on Oklahoma Wind’s jurisdiction customer and the Oklahoma Corporation Commission. Comment Date: 5 p.m. eastern time on March 11, 2005. 28. New York Independent System Operator, Inc. [Docket No. ER05–629–000] Take notice that on February 18, 2005, the New York Independent System Operator, Inc. (NYISO) and the New York Transmission Owners filed a joint compliance filing pursuant to the Commission’s Order No. 2003–B, Standardization of Generator Interconnection Agreements and Procedures, 109 FERC ¶ 61,287 (2004). The NYISO states that copies of the filing have been served on the parties in Docket No. ER04–449–000 and has been electronically served on the official representatives of each of its customers, each participant in its stakeholder committees, on the New York State Pubic Commission and on the electric utility regulatory agencies in New Jersey and Pennsylvania. Comment Date: 5 p.m. eastern time on March 11, 2005. Standard Paragraph Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 of that document on the Applicant and all parties to this proceeding. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Linda Mitry, Deputy Secretary. [FR Doc. E5–836 Filed 3–2–05; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. CP04–413–000] Entrega Gas Pipeline Inc.; Notice of Availability, Route Inspection, and Public Comment Meetings on the Draft Environmental Impact Statement for the Entrega Pipeline Project February 25, 2005. The environmental staff of the Federal Energy Regulatory Commission (FERC or Commission) has prepared a draft Environmental Impact Statement (EIS) on the interstate natural gas pipeline transmission facilities proposed by Entrega Gas Pipeline Inc. (Entrega) in the above-referenced dockets. The draft EIS was prepared to satisfy the requirements of the National Environmental Policy Act (NEPA). Its purpose is to inform the Commission, the public, and other permitting agencies about the potential adverse and beneficial environmental impacts associated with the proposed project and its alternatives, and to recommend practical, reasonable, and appropriate mitigation measures which would avoid or reduce any significant adverse impacts to the maximum extent practicable and, where feasible, to less than significant levels. The draft EIS E:\FR\FM\03MRN1.SGM 03MRN1

Agencies

[Federal Register Volume 70, Number 41 (Thursday, March 3, 2005)]
[Notices]
[Pages 10391-10394]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-836]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL02-23-006, et al.]


Consolidated Edison Company of New York Inc., et al.; Electric 
Rate and Corporate Filings

February 24, 2005.
    The following filings have been made with the Commission. The 
filings are listed in ascending order within each docket 
classification.

1. Consolidated Edison Company of New York Inc.

[Docket No. EL02-23-006]

    Take notice that on February 18, 2005, the New York Independent 
System Operator, Inc., PJM Interconnection, L.L.C. and Public Service 
Electric and Gas Company (Filing Parties) submitted a joint compliance 
filing pursuant to the Commission's August 2, 2004, Opinion No. 476 in 
Docket No. EL02-23-000 and the Presiding Administrative Law Judge's 
January 24, 2005, Order Establishing Procedures, in Docket No. El02-23-
003.

[[Page 10392]]

    The Filing Parties state that copies of the filing were served on 
the parties on the official service list in Docket No. EL02-23-000, the 
New York State Public Service Commission, and all utility regulatory 
commissions in the PJM region.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

2. California Independent System Operator System, Pacific Gas and 
Electric Company, San Diego Gas and Electric Company, Southern 
California Edison Company

[Docket Nos. ER04-445-007, ER04-435-009, ER04-441-006, ER04-443-006]

    Take notice that on February 18, 2005, the California Independent 
System Operator Corporation, Pacific Gas and Electric Company, San 
Diego Gas and Electric Company, and Southern California Edison Company 
(collectively the Filing Parties) jointly submitted for filing a 
Standard Large Generator Interconnection Agreement in compliance with 
Order No. 2003-B, 109 FERC ] 61,287 (2004). The Filing Parties state 
that the Standard Large Generator Interconnection Agreement is intended 
to function as a stand alone pro forma agreement and is not intended to 
be incorporated into the tariffs of any of the Filing Parities.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

3. California Independent System Operator Corporation

[Docket No. ER04-445-008]

    Take notice that on February 18, 2005, the California Independent 
System Operator Corporation (ISO), pursuant to Order No. 2003-B, 109 
FERC ] 61,287 (2004) submitted for filing Standard Large Generator 
Interconnection Procedures for incorporation into the ISO Tariff.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

4. PPL Electric Utilities Corporation

[Docket No. ER05-104-001]

    Take notice that on February 18, 2005, PPL Electric Utilities 
Corporation (PPL Electric) submitted a response to the Commission's 
deficiency letter issued on December 22, 2004, regarding PPL Electric's 
October 29, 2004, filing of A Second Revised Service Agreement between 
PPL Electric and Metropolitan Edison Company.
    PPL states that copies of the filing were served upon parties on 
the official service list.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

5. Mirant Delta, LLC and Mirant Potrero, LLC

[Docket No. ER05-343-002]

    Take notice that, on February 18, 2005, Mirant Delta, LLC and 
Mirant Potrero, LLC (Mirant) submitted revised tariff sheets in 
compliance with the Commission's Order in Mirant Delta, LLC and Mirant 
Potrero, LLC, 110 FERC ] 61,136 (2005) in Docket Nos. ER05-343-000 and 
ER05-343-001.
    Mirant states that copies of the filing were served on parties on 
the official service list in the above-captioned proceeding.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

6. Northeast Utilities Service Company

[Docket No. ER05-385-001]

    Take notice that on February 18, 2005, Northeast Utilities Service 
Company (NUSCO), on behalf of The Connecticut Light and Power Company, 
Western Massachusetts Electric Company, Holyoke Water Power Company and 
Public Service Company of New Hampshire, submitted a revised Notice of 
Cancellation of the rate schedules for sales of electricity to the Town 
of Danvers Electric Division, Littleton Electric Light Department, 
Mansfield Municipal Electric Department, and UNITIL Power Corporation, 
originally filed on December 28, 2004.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

7. Tampa Electric Company

[Docket No. ER05-602-000]

    Take notice that on February 18, 2005, Tampa Electric Company 
(Tampa Electric) submitted tariff sheets for inclusion in its open 
access transmission tariff revising the Large Generator Interconnection 
Procedures and the Large Generator Interconnection Agreement in 
compliance with the Commission's Order No. 2003-B, Standardization of 
Generator Interconnection Agreements and Procedures, 109 FERC ] 61,287 
(2004). Tampa Electric requests an effective date of January 19, 2005.
    Tampa Electric states that copies of the filing have been served on 
the customers under Tampa Electric's open access transmission tariff 
and the Florida Public Service Commission.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

8. Entergy Service, Inc.

[Docket No. ER05-603-000]

    Take notice that on February 18, 2005, Entergy Services, Inc. 
(Entergy) on behalf of Entergy Arkansas, Inc., Entergy Gulf States, 
Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and Entergy 
New Orleans, Inc., submitted tariff sheets reflecting the revisions to 
the pro forma Standard Large Generator Interconnection Procedures and 
the Standard Large Generator Interconnection Agreement set out in the 
Commission's Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004).
    Comment Date: 5 p.m. eastern time on March 11, 2005.

9. Southwest Power Pool, Inc.

[Docket No. ER05-604-000]

    Take notice that on February 18, 2005, Southwest Power Pool, Inc. 
(SPP) submitted tariff sheets to its open access transmission tariff 
incorporating the changes directed by the Commission in Order No. 2003-
B, Standardization of Generator Interconnection Agreements and 
Procedures, 109 FERC ] 61,287 (2004). SPP requests an effective date of 
January 19, 2005.
    SPP states that copies of the filing have been served on the 
parties on the official service list in Docket no. ER04-434-000, and on 
all SPP members, customers, and state commissions within the region. In 
addition, SPP states that the filing has been posted electronically on 
its Web site at https://www.spp.org and that it will provide hard copies 
upon request.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

10. PJM Interconnection, L.L.C.

[Docket No. ER05-605-000]

    Take notice that on February 18, 2005, PJM Interconnection, L.L.C. 
(PJM) submitted for filing an executed interconnection service 
agreement and an executed construction service agreement among PJM, 
Pine Hurst Acres, and PPL Electric Utilities. PJM requests a January 
20, 2005, effective date.
    PJM states that copies of the filing were served on the parties to 
the agreements and the state regulatory commissions within the PJM 
region.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

11. Idaho Power Company

[Docket No. ER05-606-000]

    Take notice that on February 18, 2005, Idaho Power Company 
submitted tariff sheets to its open access transmission tariff 
incorporating the changes directed by the Commission in Order No. 2003-
B, Standardization of Generator Interconnection Agreements and 
Procedures, 109 FERC ] 61,287 (2004).
    Comment Date: 5 p.m. eastern time on March 11, 2005.

[[Page 10393]]

12. Valley Electric Association, Inc.

[Docket No. ER05-607-000]

    Take notice that on February 18, 2005, Valley Electric Association, 
Inc. submitted revised tariff sheets to its open access transmission 
tariff incorporating the changes directed by the Commission in Order 
No. 2003-B, Standardization of Generator Interconnection Agreements and 
Procedures, 109 FERC ] 61,287 (2004).
    Comment Date: 5 p.m. eastern time on March 11, 2005.

13. Tuscon Electric Power Company and UNS Electric, Inc.

[Docket No. ER05-610-000]

    Take notice that on February 18, 2005, Tuscon Electric Power 
Company and UNS Electric, Inc. submitted revised tariff sheets to its 
open access transmission tariff incorporating the changes directed by 
the Commission in Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004).
    Comment Date: 5 p.m. eastern time on March 11, 2005.

14. Bridgeport Energy LLC

[Docket No. ER05-611-000]

    Take notice that on February 18, 2005, Bridgeport Energy, LLC 
(Bridgeport) tendered for filing its proposed FERC Electric Tariff, 
Original Volume No. 2 and supporting costs data for Bridgeport's cost-
of-service agreement with ISO-New England, Inc. (ISO-NE) in order to 
receive compensation for the provision of reliability services.
    Bridgeport states that a copy of the filing has been served on ISO-
NE.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

15. Southern California Edison Company

[Docket No. ER05-612-000]

    Take notice that on February 18, 2005, Southern California Edison 
Company (SCE) submitted revised tariff sheets in compliance with the 
Commission's Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004).
    SCE states that copies of the filing were served on the parties on 
the official service list for Docket No. ER04-435-000.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

16. Southern Company Services, Inc.

[Docket No. ER05-613-000]

    Take notice that on February 18, 2005, Southern Company Services, 
Inc. on behalf of Alabama Power Company, Georgia Power Company, Gulf 
Power Company, Mississippi Power Company and Savannah Electric and 
Power Company (collectively Southern Companies) submitted revised 
tariff sheets in compliance with the Commission's Order No. 2003-B, 
Standardization of Generator Interconnection Agreements and Procedures, 
109 FERC ] 61,287 (2004).
    SCS states that this filing is posted on Southern Companies' OASIS 
for download by any person and that Southern Companies will provide 
copies of the filing upon request.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

17. El Paso Electric Company

[Docket No. ER05-614-000]

    Take notice that on February 18, 2005, El Paso Electric Company 
(EPE) submitted revised tariff sheets in compliance with the 
Commission's Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004).
    EPE states that copies of the filing were served on all persons on 
the service list for Docket No. ER04-448-000, the Public Utility 
Commission of Texas and the New Mexico Public Regulation Commission.
    Comment Date: 5 p.m. eastern Time on March 11, 2005.

18. Southern California Edison Company

[Docket No. ER05-615-000]

    Take notice that on February 18, 2005, Southern California Edison 
Company (SCE) tendered for filing revisions to the facilities charges 
under the interconnection facilities agreement, FERC Electric Tariff, 
First Revised Volume No. 5, Service Agreement No. 109 and service 
agreement for wholesale distribution service, FERC Electric Tariff, 
First Revised Volume No. 5, Service Agreement No. 110 between SCE and 
FPL Energy Green Power Wind LLC.
    SCE states that copies of the filing were served on the Public 
Utilities Commission of the State of California and FPL Energy Green 
Power Wind LLC.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

19. Xcel Energy Services Inc.

[Docket No. ER05-616-000]

    Take notice that on February 18, 2005, Xcel Energy Services Inc. 
submitted revised tariff sheets in compliance with the Commission's 
Order No. 2003-B, Standardization of Generator Interconnection 
Agreements and Procedures, 109 FERC ] 61,287 (2004).
    Comment Date: 5 p.m. eastern time on March 11, 2005.

20. El Segundo Power, LLC

[Docket No. ER05-617-000]

    Take notice that on February 18, 2005, El Segundo Power, LLC (El 
Segundo) tendered for filing an amendment to its Rate Schedule FERC No. 
2, a reliability must-run agreement between El Segundo and the 
California Independent System Operator Corporation (CAISO). El Segundo 
requests an effective date of April 15, 2005.
    El Segundo states that copies of the filing were served on CAISO, 
Southern California Edison Company, the California Electricity 
Oversight Board, and the California Public Utilities Commission.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

21. Midwest Independent Transmission System Operator, Inc.

[Docket No. ER05-618-000]

    Take notice that on February 18, 2005, Midwest Independent 
Transmission System Operator, Inc. (Midwest ISO) submitted revised 
tariff sheets in compliance with the Commission's Order No. 2003-B, 
Standardization of Generator Interconnection Agreements and Procedures, 
109 FERC ] 61,287 (2004).
    The Midwest ISO states that it has electronically served a copy of 
this filing, with attachments, upon all Midwest ISO members, member 
representatives of transmission owners and non-transmission owners, the 
Midwest ISO Advisory Committee participants, as well as all state 
commissions within the regions. The Midwest ISO also states that the 
filing has been posted on Midwest ISO's Web site at https://
www.midwestiso.org under the heading ``Filings to FERC.''
    Comment Date: 5 p.m. eastern time on March 11, 2005.

22. Black Hills Power, Inc.; Basin Electric Power Cooperative; Powder 
River Energy Corporation

[Docket No. ER05-619-000]

    Take notice that on February 18, 2005, Black Hills Power, Inc. on 
behalf of itself, Basin Electric Power Cooperative, and Powder River 
Energy Corporation submitted revised tariff sheets in compliance with 
the Commission's Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004).

[[Page 10394]]

    Comment Date: 5 p.m. eastern time on March 11, 2005.

23. Ohio Valley Electric Corporation

[Docket No. ER05-621-000]

    Take notice that on February 18, 2005, Ohio Valley Electric 
Corporation (OVEC) submitted revised tariff sheets in compliance with 
the Commission's Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004).
    OVEC states that a copy of the filing has been mailed to its 
jurisdictional customers and to each state public service commission 
that has retail jurisdiction over such customers.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

24. Carolina Power & Light Company, Florida Power Corporation

[Docket No. ER05-622-000]

    Take notice that on February 18, 2005, Carolina Power & Light 
Company (CP&L) and Florida Power Corporation (FPC) submitted revised 
tariff sheets in compliance with the Commission's Order No. 2003-B, 
Standardization of Generator Interconnection Agreements and Procedures, 
109 FERC ] 61,287 (2004).
    CP&L and FPC state that a copy of the filing was served on their 
transmission customers, the North Carolina Utilities Commission, the 
Public Service Commission of South Carolina and the Florida Public 
Service Commission.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

25. Duke Energy Washington, LLC

[Docket No. ER05-623-000]

    Take notice that on February 18, 2005, Duke Energy Washington, LLC 
(Duke Washington) tendered for filing proposed tariff and supporting 
cost data for its monthly revenue requirement for reactive supply and 
voltage control from generation sources service provided to PJM 
Interconnection, L.L.C.(PJM). Duke Washington requests an effective 
date of March 1, 2005.
    Duke Washington states that it has served a copy of the filing on 
PJM.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

26. PJM Interconnection, L.L.C.

[Docket No. ER05-626-000]

    Take notice that on February 18, 2005, PJM Interconnection, L.L.C. 
(PJM) submitted revised tariff sheets in compliance with the 
Commission's Order No. 2003-B, Standardization of Generator 
Interconnection Agreements and Procedures, 109 FERC ] 61,287 (2004). 
PJM states that the revisions have an effective date of February 18, 
2005.
    PJM states that copies of the filing have been served on all PJM 
members and the utility regulatory commissions in the PJM region.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

27. FPL Energy Oklahoma Wind, LLC

[Docket No. ER05-628-000]

    Take notice that on February 18, 2005, FPL Energy Oklahoma Wind, 
LLC (Oklahoma Wind) submitted a shared facilities agreement between 
Oklahoma Wind and FPL Energy Sooner Wind, LLC designated as Rate 
Schedule FERC No. 1. Oklahoma Wind requests an effective date of 
September 26, 2003.
    Oklahoma Wind states that copies of the filing were served on 
Oklahoma Wind's jurisdiction customer and the Oklahoma Corporation 
Commission.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

28. New York Independent System Operator, Inc.

[Docket No. ER05-629-000]

    Take notice that on February 18, 2005, the New York Independent 
System Operator, Inc. (NYISO) and the New York Transmission Owners 
filed a joint compliance filing pursuant to the Commission's Order No. 
2003-B, Standardization of Generator Interconnection Agreements and 
Procedures, 109 FERC ] 61,287 (2004).
    The NYISO states that copies of the filing have been served on the 
parties in Docket No. ER04-449-000 and has been electronically served 
on the official representatives of each of its customers, each 
participant in its stakeholder committees, on the New York State Pubic 
Commission and on the electric utility regulatory agencies in New 
Jersey and Pennsylvania.
    Comment Date: 5 p.m. eastern time on March 11, 2005.

Standard Paragraph

    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. Such notices, 
motions, or protests must be filed on or before the comment date. 
Anyone filing a motion to intervene or protest must serve a copy of 
that document on the Applicant and all parties to this proceeding.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an 
original and 14 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.