Supplemental Environmental Impact Statement on the AB Lateral Hydropower Project in Montrose County, CO, 9968 [05-3896]
Download as PDF
9968
Federal Register / Vol. 70, No. 39 / Tuesday, March 1, 2005 / Notices
• State Water Resources Control Board,
Division of Water Rights, 1001 I
Street, 14th Floor, Sacramento, CA
95814, (916) 341–5300
Public Disclosure Statement
Comments, including names and
home addresses of respondents, will be
made available for public review.
Individual respondents may request that
their home address be withheld from
public disclosure, which will be
honored to the extent allowable by law.
There may be circumstances in which a
respondent’s identity may also be
withheld from public disclosure, as
allowable by law. If you wish to have
your name and/or address withheld,
you must state this prominently at the
beginning of your comment. All
submissions from organizations or
businesses, and from individuals
identifying themselves as
representatives or officials of
organizations or businesses, will be
made available for public disclosure in
their entirety.
Dated: January 7, 2005.
Kirk C. Rodgers,
Regional Director, Mid-Pacific Region.
[FR Doc. 05–3930 Filed 2–28–05; 8:45 am]
BILLING CODE 4310–MN–P
Dated: February 9, 2005.
Connie L. Rupp,
Assistant Regional Director—UC Region,
Bureau of Reclamation.
[FR Doc. 05–3896 Filed 2–28–05; 8:45 am]
BILLING CODE 4310–MN–P
INTERNATIONAL TRADE
COMMISSION
[Inv. No. 337–TA–486 Enforcement
Proceedings]
Certain Agricultural Tractors, Lawn
Tractors, Riding Lawnmowers, and
Components Thereof; Notice of a
Commission Determination Not To
Review an Initial Determination Finding
Two Respondents in Default
International Trade
Commission.
ACTION: Notice.
Bureau of Reclamation
Supplemental Environmental Impact
Statement on the AB Lateral
Hydropower Project in Montrose
County, CO
Bureau of Reclamation,
Interior.
ACTION: Notice of cancellation.
AGENCY:
SUMMARY: The Bureau of Reclamation is
canceling plans to prepare a
supplemental environmental impact
statement (EIS) on the AB Lateral
Hydropower Project. The hydropower
project planned to use existing facilities
of the Uncompahgre Valley Reclamation
Project and would have been located in
Montrose County, Colorado. The reason
for canceling is that the project
proponents, including the Uncompahgre
Valley Water User’s Association, have
elected not to pursue approval of the
project at this time.
FOR FURTHER INFORMATION CONTACT: Mr.
Steve McCall, Chief, Environmental
Staff, Bureau of Reclamation, Western
Colorado Area Office, 2764 Compass
Drive, Suite 106, Grand Junction,
Colorado 81506, telephone, (970) 248–
0638.
14:21 Feb 28, 2005
Reclamation filed a final EIS on the
project in 1990 and the supplemental
EIS was planned to address changes in
the project plan and changes in resource
evaluations. The primary federal actions
on this project would have been
execution of a lease of power privilege
(a type of contract) with Reclamation
and the granting of a Section 404 permit
under the Clean Water Act from the U.S.
Army Corps of Engineers.
AGENCY:
DEPARTMENT OF THE INTERIOR
VerDate jul<14>2003
SUPPLEMENTARY INFORMATION:
Jkt 205001
SUMMARY: Notice is hereby given that
the U.S. International Trade
Commission has determined not to
review an initial determination (ID) of
the presiding administrative law judge
(ALJ) in the above-captioned
investigation finding two respondents,
Beiqi Foton Motor Co., Ltd. and
Shandong Worldbest Shantou Co., Ltd.,
in default, and to have waived their
respective rights to appear, to be served
with documents, and to contest the
allegations at issue in the investigation.
FOR FURTHER INFORMATION CONTACT:
Michael K. Haldenstein, Esq., telephone
202–205–3041, Office of the General
Counsel, U.S. International Trade
Commission, 500 E Street, SW.,
Washington, DC 20436. Copies of all
nonconfidential documents filed in
connection with this investigation are or
will be available for inspection during
official business hours (8:45 a.m. to 5:15
p.m.) in the Office of the Secretary, U.S.
International Trade Commission, 500 E
Street, SW., Washington, DC 20436,
telephone 202–205–2000. General
information concerning the Commission
may also be obtained by accessing its
Internet server (https://www.usitc.gov).
The public record for this investigation
may be viewed on the Commission’s
PO 00000
Frm 00059
Fmt 4703
Sfmt 4703
electronic docket (EDIS–ON–LINE) at
https://edis.usitc.gov. Hearing-impaired
persons are advised that information on
the matter can be obtained by contacting
the Commission’s TDD terminal on 202–
205–1810.
SUPPLEMENTARY INFORMATION: On
August, 2, 2004, the complainant, CNH
America LLC, filed a complaint seeking
enforcement proceedings of the limited
exclusion order issued in Certain
Agricultural Tractors, Inv. No. 337–TA–
486. The complainant asserted that the
recipient of the limited order, now
known as Beiqi Foton Motor Co., Ltd.,
continues to export infringing tractors to
the United States. Complainant also
requested that the Commission modify
the limited exclusion order by replacing
it with a general exclusion order and
various cease and desist orders in order
to prevent alleged circumvention of the
limited exclusion order.
On November 19, 2004, the
Commission instituted formal
enforcement proceedings to determine
whether Beiqi Foton Motor Co. Ltd. and
Shandong Worldbest Shantou Co., Ltd.,
an allegedly related company, are in
violation of the Commission’s limited
exclusion order issued in the
investigation, and what if any
enforcement measures are appropriate.
The Commission set a seven-month
deadline for issuance of the enforcement
initial determination by the ALJ and
named the following entities as parties
to the enforcement proceeding: (1)
Complainant CNH America LLC; (2)
respondent Beiqi Foton Motor Co., Ltd.;
(3) respondent Shandong Worldbest
Shantou Co., Ltd.; and (4) a Commission
investigative attorney (IA) to be
designated by OUII. 69 FR 67757 (Nov.
19, 2004). The Commission
subsequently set a target date of
November 21, 2005 for completion of
the investigation.
The complaint was mailed to the two
respondents on November 17, 2004, and
they were notified in the letter
accompanying the complaint that they
could be found in default if they failed
to respond. When they did not respond,
the ALJ issued a show cause order
(Order 1E) on December 29, 2004, which
required the two respondents to show
cause why they should not be found in
default. A deadline of January 18, 2005,
was set for the respondents to respond
to that order. While respondents did not
respond to the show cause order,
complainant and the IA responded on
January 18, 2005, and urged the ALJ to
find the two respondents in default.
The ALJ issued the subject ID (Order
2E) on February 4, 2005. The ALJ found
in the ID that the two respondents did
E:\FR\FM\01MRN1.SGM
01MRN1
Agencies
[Federal Register Volume 70, Number 39 (Tuesday, March 1, 2005)]
[Notices]
[Page 9968]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-3896]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
Bureau of Reclamation
Supplemental Environmental Impact Statement on the AB Lateral
Hydropower Project in Montrose County, CO
AGENCY: Bureau of Reclamation, Interior.
ACTION: Notice of cancellation.
-----------------------------------------------------------------------
SUMMARY: The Bureau of Reclamation is canceling plans to prepare a
supplemental environmental impact statement (EIS) on the AB Lateral
Hydropower Project. The hydropower project planned to use existing
facilities of the Uncompahgre Valley Reclamation Project and would have
been located in Montrose County, Colorado. The reason for canceling is
that the project proponents, including the Uncompahgre Valley Water
User's Association, have elected not to pursue approval of the project
at this time.
FOR FURTHER INFORMATION CONTACT: Mr. Steve McCall, Chief, Environmental
Staff, Bureau of Reclamation, Western Colorado Area Office, 2764
Compass Drive, Suite 106, Grand Junction, Colorado 81506, telephone,
(970) 248-0638.
SUPPLEMENTARY INFORMATION: Reclamation filed a final EIS on the project
in 1990 and the supplemental EIS was planned to address changes in the
project plan and changes in resource evaluations. The primary federal
actions on this project would have been execution of a lease of power
privilege (a type of contract) with Reclamation and the granting of a
Section 404 permit under the Clean Water Act from the U.S. Army Corps
of Engineers.
Dated: February 9, 2005.
Connie L. Rupp,
Assistant Regional Director--UC Region, Bureau of Reclamation.
[FR Doc. 05-3896 Filed 2-28-05; 8:45 am]
BILLING CODE 4310-MN-P