San Diego Gas & Electric Company, Complainants v. Sellers of Energy and Ancillary Services Into Markets Operated by the California Independent System Operator and the California Power Exchange, Respondents; Investigation of Practices of the California Independent System Operator and the California Power Exchange; Notice of Compliance Filing, 9635 [E5-787]
Download as PDF
Federal Register / Vol. 70, No. 38 / Monday, February 28, 2005 / Notices
[FR Doc. 05–3782 Filed 2–25–05; 8:45 am]
BILLING CODE 6450–01–C
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket Nos. EL00–95–125 and EL00–98–
112]
Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call
(866) 208–3676 (toll free). For TTY, call
(202) 502–8659.
Comment Date: 5 p.m. eastern time on
March 4, 2005.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5–787 Filed 2–25–05; 8:45 am]
BILLING CODE 6717–01–P
San Diego Gas & Electric Company,
Complainants v. Sellers of Energy and
Ancillary Services Into Markets
Operated by the California
Independent System Operator and the
California Power Exchange,
Respondents; Investigation of
Practices of the California Independent
System Operator and the California
Power Exchange; Notice of
Compliance Filing
February 18, 2005.
On February 11, 2005, the City of
Pasadena (Pasadena) submitted its
emissions calculations in compliance
with the Commission’s Order issued
November 23, 2004, in Docket Nos.
EL00–95–100 and EL00–98–088, 109
FERC ¶ 61,218.
Any person desiring to intervene or to
protest this filing must file in
accordance with Rules 211 and 214 of
the Commission’s Rules of Practice and
Procedure (18 CFR 385.211, 385.214).
Protests will be considered by the
Commission in determining the
appropriate action to be taken, but will
not serve to make protestants parties to
the proceeding. Any person wishing to
become a party must file a notice of
intervention or motion to intervene, as
appropriate. Such notices, motions, or
protests must be filed on or before the
comment date. Anyone filing a motion
to intervene or protest must serve a copy
of that document on the Applicant and
all the parties in this proceeding.
The Commission encourages
electronic submission of protests and
interventions in lieu of paper using the
‘‘eFiling’’ link at https://www.ferc.gov.
Persons unable to file electronically
should submit an original and 14 copies
of the protest or intervention to the
Federal Energy Regulatory Commission,
888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at
https://www.ferc.gov, using the
‘‘eLibrary’’ link and is available for
review in the Commission’s Public
Reference Room in Washington, DC.
There is an ‘‘eSubscription’’ link on the
Web site that enables subscribers to
receive e-mail notification when a
document is added to a subscribed
docket(s). For assistance with any FERC
VerDate jul<14>2003
16:34 Feb 25, 2005
Jkt 205001
9635
3. Idaho Power Company
[Docket No. ER97–1481–007]
Take notice that on February 17, 2005,
Idaho Power (IPC) submitted an
amendment to its January 19, 2005,
filing regarding IPC’s revised generation
market power screen analysis.
Comment Date: 5 p.m. eastern time on
February 25, 2005.
4. PacifiCorp PPM Energy, Inc.
[Docket No. ER97–2801–005 and ER03–478–
004]
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. EC05–20–000, et al.]
PPL Sundance Energy, LLC, et al.;
Electric Rate and Corporate Filings
February 18, 2005.
The following filings have been made
with the Commission. The filings are
listed in ascending order within each
docket classification.
Take notice that on February 14, 2005,
PacifiCorp and PPM Energy, Inc.
tendered for filing an updated market
power analysis.
Comment Date: 5 p.m. eastern time on
March 4, 2005.
5. Pacific Gas and Electric Company
[Docket No. ER03–1091–007]
[Docket No. EC05–20–000]
Take notice that on February 11, 2005,
PPL Sundance Energy, LLC (PPL
Sundance), PPL Energy Plus, LLC and
Arizona Public Service Company (APS)
(collectively, Applicants) filed with the
Federal Energy Regulatory Commission
a response to a deficiency letter issued
on January 28, 2005, by Jamie L. Simler,
Director, Division of Tariffs and Market
Development—West, in connection with
a section 203 application filed for
authorization to acquire a 450 megawatt
generating facility owned by PPL
Sundance. Applicants request
confidential treatment of certain
supporting data contained in the filing.
Comment Date: 5 p.m. eastern time on
March 2, 2005.
Take notice that on February 11, 2005,
Pacific Gas and Electric Company
(PG&E) tendered for filing an
amendment to its December 30, 2004,
compliance filing regarding a Generator
Special Facilities Agreement and
Generator Interconnection Agreement
between PG&E and Duke Energy Morro
Bay LLC (Duke Morro Bay).
PG&E states that copies of this filing
have been served upon Duke Morro Bay,
the California Independent System
Operator Corporation and the California
Public Utilities Commission.
Comment Date: 5 p.m. eastern time on
March 4, 2005.
6. The Detroit Edison Company
1. PPL Sundance Energy, LLC, PPL
Energy Plus, LLC, Arizona Public
Service Company
[Docket Nos. ER04–14–006 and EL04–29–
006]
2. Duke Power, a Division of Duke
Power Corporation
Take notice that on February 11, 2005,
The Detroit Edison Company (Detroit
Edison) filed an amendment to its
Ancillary Services Tariff, First Revised
Volume No. 5, filed on December 2,
2004 to repaginate the tariff sheets in
compliance with Order No. 614.
Comment Date: 5 p.m. eastern time on
March 4, 2005.
[Docket Nos. ER96–110–013 and EL05–4–
000]
7. California Independent System
Operator Corporation
Take notice that on February 14, 2005,
Duke Power, a division of Duke Energy
Corporation (Duke Power) submitted a
filing in compliance with the
Commission’s order issued December
15, 2004, in Docket No. ER96–110–010,
et al., 109 FERC ¶ 61,270.
Duke Power states that copies of the
filing were served on parties on the
official service list in the abovecaptioned proceed as well as its State
commissions.
Comment Date: 5 p.m. eastern time on
March 4, 2005.
PO 00000
Frm 00028
Fmt 4703
Sfmt 4703
[Docket No. ER05–277–001]
Take notice that on February 14, 2005,
the California Independent System
Operator Corporation (ISO) submitted a
filing in compliance with the
Commission’s order issued January 28,
2005, in Docket No. ER05–277–000, 110
FERC ¶ 61,082.
The ISO states that the filing has been
served on all parties on the official
service list for this proceeding. In
addition, the ISO states that it has
posting the filing on the ISO home page.
E:\FR\FM\28FEN1.SGM
28FEN1
Agencies
[Federal Register Volume 70, Number 38 (Monday, February 28, 2005)]
[Notices]
[Page 9635]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-787]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket Nos. EL00-95-125 and EL00-98-112]
San Diego Gas & Electric Company, Complainants v. Sellers of
Energy and Ancillary Services Into Markets Operated by the California
Independent System Operator and the California Power Exchange,
Respondents; Investigation of Practices of the California Independent
System Operator and the California Power Exchange; Notice of Compliance
Filing
February 18, 2005.
On February 11, 2005, the City of Pasadena (Pasadena) submitted its
emissions calculations in compliance with the Commission's Order issued
November 23, 2004, in Docket Nos. EL00-95-100 and EL00-98-088, 109 FERC
] 61,218.
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Applicant and all the parties in this proceeding.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at https://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
FERCOnlineSupport@ferc.gov, or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Comment Date: 5 p.m. eastern time on March 4, 2005.
Linda Mitry,
Deputy Secretary.
[FR Doc. E5-787 Filed 2-25-05; 8:45 am]