Drawbridge Operation Regulations: Newtown Creek, Dutch Kills, English Kills, and Their Tributaries, NY, 4014 [05-1561]
Download as PDF
4014
Federal Register / Vol. 70, No. 18 / Friday, January 28, 2005 / Rules and Regulations
until 4 p.m. on Wednesday, February
16, 2005.
DEPARTMENT OF HOMELAND
SECURITY
Materials referred to in this
document are available for inspection or
copying at the office of the Eighth Coast
Guard District, Bridge Administration
Branch, Hale Boggs Federal Building,
room 1313, 500 Poydras Street, New
Orleans, Louisiana 70130–3310 between
7 a.m. and 3 p.m., Monday through
Friday, except Federal holidays. The
telephone number is (504) 589–2965.
The Bridge Administration Branch of
the Eighth Coast Guard District
maintains the public docket for this
temporary deviation.
Coast Guard
FOR FURTHER INFORMATION CONTACT:
The Commander, First Coast
Guard District, has issued a temporary
deviation from the drawbridge operation
regulations for the Metropolitan Avenue
Bridge, mile 3.4, across English Kills at
New York City, New York. Under this
temporary deviation the bridge may
remain closed from 6 a.m. to midnight
on the following days: January 19
through January 21; January 26 through
January 28; and January 31 through
February 5, 2005. This temporary
deviation is necessary to facilitate
bridge maintenance.
ADDRESSES:
The BNSF
RR has requested a temporary deviation
in order to remove and replace the
motor and transmission of the Bayou
Boeuf Swing Bridge across Bayou Boeuf,
mile 10.2, at Amelia, St. Mary Parish,
LA. The repairs are necessary to ensure
the proper operation of the bridge. This
temporary deviation will allow the
bridge to remain in the closed-tonavigation position from 8 a.m. until 4
p.m. on Monday, February 14, 2005,
from 7 a.m. until 5 p.m. on Tuesday,
February 15, 2005, and from 8 a.m. until
4 p.m. on Wednesday, February 16,
2005.
As the bridge has no vertical
clearance in the closed-to-navigation
position, vessels will not be able to
transit through the bridge site when the
bridge is closed. Navigation at the site
of the bridge consists mainly of tows
with barges and some recreational
pleasure craft. Due to prior experience,
as well as coordination with waterway
users, it has been determined that this
closure will not have a significant effect
on these vessels. An alternate route is
available by using the GIWW, Morgan
City to Port Allen Alternate Route.
In accordance with 33 CFR 117.35(c),
this work will be performed with all due
speed in order to return the bridge to
normal operation as soon as possible.
This deviation from the operating
regulations is authorized under 33 CFR
117.35.
SUPPLEMENTARY INFORMATION:
Dated: January 13, 2005.
Marcus Redford,
Bridge Administrator.
[FR Doc. 05–1560 Filed 1–27–05; 8:45 am]
VerDate jul<14>2003
14:20 Jan 27, 2005
Jkt 205001
BILLING CODE 4910–15–P
[CGD01–04–157]
Drawbridge Operation Regulations:
Newtown Creek, Dutch Kills, English
Kills, and Their Tributaries, NY
AGENCY:
Coast Guard, DHS.
DEPARTMENT OF HOMELAND
SECURITY
Coast Guard
33 CFR Part 117
Notice of temporary deviation
from regulations.
ACTION:
[CGD05–04–168]
RIN 1625–AA09
SUMMARY:
David Frank, Bridge Administration
Branch, telephone (504) 589–2965.
BILLING CODE 4910–15–P
33 CFR Part 117
Dated: January 12, 2005.
Gary Kassof,
Bridge Program Manager, First Coast Guard
District.
[FR Doc. 05–1561 Filed 1–27–05; 8:45 am]
This deviation is effective from
January 19, 2005 through February 5,
2005.
DATES:
Judy
Leung-Yee, Project Officer, First Coast
Guard District, at (212) 668–7195.
FOR FURTHER INFORMATION CONTACT:
The
Metropolitan Avenue Bridge has a
vertical clearance in the closed position
of 10 feet at mean high water and 15 feet
at mean low water. The existing
drawbridge operation regulations are
listed at 33 CFR 117.801(e).
SUPPLEMENTARY INFORMATION:
The owner of the bridge, New York
City Department of Transportation
(NYCDOT), requested a temporary
deviation from the drawbridge operation
regulations to facilitate rehabilitation
repairs at the bridge. The bridge must
remain in the closed position to perform
these repairs.
Under this temporary deviation the
NYCDOT Metropolitan Avenue Bridge
may remain in the closed position from
6 a.m. through midnight on the
following days: January 19 through
January 21; January 26 through January
28; and from January 31 through
February 5, 2005.
This deviation from the operating
regulations is authorized under 33 CFR
117.35, and will be performed with all
due speed in order to return the bridge
to normal operation as soon as possible.
PO 00000
Frm 00012
Fmt 4700
Sfmt 4700
Drawbridge Operation Regulations;
Christina River, Wilmington, DE
Coast Guard, DHS.
Final rule.
AGENCY:
ACTION:
SUMMARY: The Coast Guard is changing
the regulations that govern the operation
of the Norfolk Southern (NS) Railroad
Bridge across Christina River, at mile
1.4, in Wilmington, DE. The bridge will
remain open for vessel traffic, closing
only for train crossings and periodic
maintenance by an operator at a remote
location. The final rule will maintain
the bridge’s current level of operational
capabilities and continue to provide for
the reasonable needs of rail
transportation and vessel navigation.
DATES: This rule is effective February
28, 2005.
ADDRESSES: Comments and material
received from the public, as well as
documents indicated in this preamble as
being available in the docket, are part of
docket CGD05–04–168 and are available
for inspection or copying at Commander
(obr), Fifth Coast Guard District, Federal
Building, 1st Floor, 431 Crawford Street,
Portsmouth, VA 23704–5004 between 8
a.m. and 4 p.m., Monday through
Friday, except Federal holidays. The
Fifth Coast Guard District maintains the
public docket for this rulemaking.
FOR FURTHER INFORMATION CONTACT:
Anton Allen, Bridge Management
Specialist, Fifth Coast Guard District, at
(757) 398–6227.
SUPPLEMENTARY INFORMATION:
Regulatory History
On October 12, 2004, we published a
notice of proposed rulemaking (NPRM)
entitled ‘‘Drawbridge Operation
Regulations; Christina River,
Wilmington, DE’’ in the Federal
Register (69 FR 60597). We received five
letters commenting on the proposed
rule. No public meeting was requested,
and none was held.
E:\FR\FM\28JAR1.SGM
28JAR1
Agencies
[Federal Register Volume 70, Number 18 (Friday, January 28, 2005)]
[Rules and Regulations]
[Page 4014]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: 05-1561]
-----------------------------------------------------------------------
DEPARTMENT OF HOMELAND SECURITY
Coast Guard
33 CFR Part 117
[CGD01-04-157]
Drawbridge Operation Regulations: Newtown Creek, Dutch Kills,
English Kills, and Their Tributaries, NY
AGENCY: Coast Guard, DHS.
ACTION: Notice of temporary deviation from regulations.
-----------------------------------------------------------------------
SUMMARY: The Commander, First Coast Guard District, has issued a
temporary deviation from the drawbridge operation regulations for the
Metropolitan Avenue Bridge, mile 3.4, across English Kills at New York
City, New York. Under this temporary deviation the bridge may remain
closed from 6 a.m. to midnight on the following days: January 19
through January 21; January 26 through January 28; and January 31
through February 5, 2005. This temporary deviation is necessary to
facilitate bridge maintenance.
DATES: This deviation is effective from January 19, 2005 through
February 5, 2005.
FOR FURTHER INFORMATION CONTACT: Judy Leung-Yee, Project Officer, First
Coast Guard District, at (212) 668-7195.
SUPPLEMENTARY INFORMATION: The Metropolitan Avenue Bridge has a
vertical clearance in the closed position of 10 feet at mean high water
and 15 feet at mean low water. The existing drawbridge operation
regulations are listed at 33 CFR 117.801(e).
The owner of the bridge, New York City Department of Transportation
(NYCDOT), requested a temporary deviation from the drawbridge operation
regulations to facilitate rehabilitation repairs at the bridge. The
bridge must remain in the closed position to perform these repairs.
Under this temporary deviation the NYCDOT Metropolitan Avenue
Bridge may remain in the closed position from 6 a.m. through midnight
on the following days: January 19 through January 21; January 26
through January 28; and from January 31 through February 5, 2005.
This deviation from the operating regulations is authorized under
33 CFR 117.35, and will be performed with all due speed in order to
return the bridge to normal operation as soon as possible.
Dated: January 12, 2005.
Gary Kassof,
Bridge Program Manager, First Coast Guard District.
[FR Doc. 05-1561 Filed 1-27-05; 8:45 am]