DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
December 30, 2004.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
permit.
b. Project No.: 12555–000.
c. Date Filed: November 1, 2004.
d. Applicant: Mahoning Creek
Hydroelectric Company, LLC.
e. Name of Project: Mahoning Creek
Project.
f. Location: On Mahoning Creek, in
Armstrong County, Pennsylvania. The
dam is administered by the U.S. Army
Corps of Engineers.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Clifford
Phillip, Mahoning Creek Hydroelectric
Company, LLC, 150 North Miller Road,
Suite 450C, Fairlawn, OH 44333, (330)
869–8451.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Deadline for Filing Comments,
Protests, and Motions To Intervene: 60
days from the issuance date of this
notice.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would consist of: (1)
Proposed intake, (2) a proposed 280foot-long, 7.5-foot-diameter pentstock,
(3) an existing powerhouse containing
two generating units having a total
installed capacity of 2 megawatts, (4) an
existing 100-foot-long, 5-foot wide, 7foot-high concrete conduit tailrace, (5) a
proposed 400-foot-long, 14.y kilovolt
VerDate jul<14>2003
15:45 Jan 05, 2005
Jkt 205001
transmission line, and (6) appurtenant
facilities. The project would have an
annual generation of 10.5 gigawatthours that would be sold to a local
utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street, NE.,
Room 2A, Washington, DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or TTY, contact
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h. above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
PO 00000
Frm 00014
Fmt 4703
Sfmt 4703
1233
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies Under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To
Intervene: Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001 (a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents: Any filings must bear in all
capital letters the title ‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, or
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
A copy of any motion to intervene must
also be served upon each representative
of the Applicant specified in the
particular application.
t. Agency Comments: Federal, State,
and local agencies are invited to file
comments on the described application.
A copy of the application may be
obtained by agencies directly from the
Applicant. If an agency does not file
E:\FR\FM\06JAN1.SGM
06JAN1
1234
Federal Register / Vol. 70, No. 4 / Thursday, January 6, 2005 / Notices
comments within the time specified for
filing comments, it will be presumed to
have no comments. One copy of an
agency’s comments must also be sent to
the Applicant’s representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5–11 Filed 1–5–05; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
Notice of Application Accepted for
Filing and Soliciting Motions To
Intervene, Protests, and Comments
December 30, 2004.
Take notice that the following
hydroelectric application has been filed
with the Commission and is available
for public inspection:
a. Type of Application: Preliminary
permit.
b. Project No.: 12557–000.
c. Date Filed: November 12, 2004.
d. Applicant: SBER Royal Mills, LLC.
e. Name of Project: Royal Mills
Project.
f. Location: On the South Branch
Pawtuxet River, in Kent County, Rhode
Island. No federal land or facilities
would be used.
g. Filed Pursuant to: Federal Power
Act, 16 U.S.C. 791(a)–825(r).
h. Applicant Contact: Mr. Paul V.
Nolan, 5515 North 17th Street,
Arlington, VA 22205, (703) 534–5509.
i. FERC Contact: Robert Bell, (202)
502–6062.
j. Deadline for Filing Comments,
Protests, and Motions To Intervene: 60
days from the issuance date of this
notice.
The Commission’s Rules of Practice
and Procedure require all intervenors
filing documents with the Commission
to serve a copy of that document on
each person in the official service list
for the project. Further, if an intervenor
files comments or documents with the
Commission relating to the merits of an
issue that may affect the responsibilities
of a particular resource agency, they
must also serve a copy of the document
on that resource agency.
k. Description of Project: The
proposed project would consist of: (1)
An existing 1100-foot-long, 21-foot-high
granite block gravity dam, (2) an
existing reservoir having a surface area
of 3.8 acres with a storage capacity of
15.2 acre-feet and a maximum water
surface elevation of 79.1 feet National
Geographic Vertical Datum, (3) an
existing power canal intake, (4) an
VerDate jul<14>2003
15:45 Jan 05, 2005
Jkt 205001
existing 150-foot-long, 40-foot-wide
power canal, (5) three proposed 66-inch
diameter riveted steel penstocks 80, 110,
and 120 feet long, (6) an existing
powerhouse containing three proposed
generating units having a total installed
capacity of 200 kilowatts, (7) an existing
280-foot-long, 40-foot wide tailrace, (8)
a proposed 660-foot-long, 23 kilovolt
underground transmission line; and (9)
appurtenant facilities. The project
would have an annual generation of
1.071 gigawatt-hours that would be sold
to a local utility.
l. Locations of Applications: A copy of
the application is available for
inspection and reproduction at the
Commission in the Public Reference
Room, located at 888 First Street NE.,
Room 2A, Washington DC 20426, or by
calling (202) 502–8371. This filing may
also be viewed on the Commission’s
Web site at https://www.ferc.gov using
the ‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, please contact
FERC Online Support at
FERCOnlineSupport@ferc.gov or toll
free at 1–866–208–3676, or TTY, contact
(202) 502–8659. A copy is also available
for inspection and reproduction at the
address in item h. above.
m. Individuals desiring to be included
on the Commission’s mailing list should
so indicate by writing to the Secretary
of the Commission.
n. Competing Preliminary Permit:
Anyone desiring to file a competing
application for preliminary permit for a
proposed project must submit the
competing application itself, or a notice
of intent to file such an application, to
the Commission on or before the
specified comment date for the
particular application (see 18 CFR 4.36).
Submission of a timely notice of intent
allows an interested person to file the
competing preliminary permit
application no later than 30 days after
the specified comment date for the
particular application. A competing
preliminary permit application must
conform with 18 CFR 4.30(b) and 4.36.
o. Competing Development
Application: Any qualified development
applicant desiring to file a competing
development application must submit to
the Commission, on or before a
specified comment date for the
particular application, either a
competing development application or a
notice of intent to file such an
application. Submission of a timely
notice of intent to file a development
application allows an interested person
to file the competing application no
later than 120 days after the specified
comment date for the particular
PO 00000
Frm 00015
Fmt 4703
Sfmt 4703
application. A competing license
application must conform with 18 CFR
4.30(b) and 4.36.
p. Notice of Intent: A notice of intent
must specify the exact name, business
address, and telephone number of the
prospective applicant, and must include
an unequivocal statement of intent to
submit, if such an application may be
filed, either a preliminary permit
application or a development
application (specify which type of
application). A notice of intent must be
served on the applicant(s) named in this
public notice.
q. Proposed Scope of Studies Under
Permit: A preliminary permit, if issued,
does not authorize construction. The
term of the proposed preliminary permit
would be 36 months. The work
proposed under the preliminary permit
would include economic analysis,
preparation of preliminary engineering
plans, and a study of environmental
impacts. Based on the results of these
studies, the Applicant would decide
whether to proceed with the preparation
of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To
Intervene—Anyone may submit
comments, a protest, or a motion to
intervene in accordance with the
requirements of Rules of Practice and
Procedure, 18 CFR 385.210, .211, .214.
In determining the appropriate action to
take, the Commission will consider all
protests or other comments filed, but
only those who file a motion to
intervene in accordance with the
Commission’s Rules may become a
party to the proceeding. Any comments,
protests, or motions to intervene must
be received on or before the specified
comment date for the particular
application.
Comments, protests and interventions
may be filed electronically via the
Internet in lieu of paper; see 18 CFR
385.2001(a)(1)(iii) and the instructions
on the Commission’s Web site under ‘‘efiling’’ link. The Commission strongly
encourages electronic filing.
s. Filing and Service of Responsive
Documents—Any filings must bear in
all capital letters the title
‘‘COMMENTS’’,
‘‘RECOMMENDATIONS FOR TERMS
AND CONDITIONS’’, ‘‘PROTEST’’, OR
‘‘MOTION TO INTERVENE’’, as
applicable, and the Project Number of
the particular application to which the
filing refers. Any of the above-named
documents must be filed by providing
the original and the number of copies
provided by the Commission’s
regulations to: The Secretary, Federal
Energy Regulatory Commission, 888
First Street, NE., Washington, DC 20426.
E:\FR\FM\06JAN1.SGM
06JAN1
Agencies
[Federal Register Volume 70, Number 4 (Thursday, January 6, 2005)]
[Notices]
[Pages 1233-1234]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E5-11]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Application Accepted for Filing and Soliciting Motions
To Intervene, Protests, and Comments
December 30, 2004.
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection:
a. Type of Application: Preliminary permit.
b. Project No.: 12555-000.
c. Date Filed: November 1, 2004.
d. Applicant: Mahoning Creek Hydroelectric Company, LLC.
e. Name of Project: Mahoning Creek Project.
f. Location: On Mahoning Creek, in Armstrong County, Pennsylvania.
The dam is administered by the U.S. Army Corps of Engineers.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Mr. Clifford Phillip, Mahoning Creek
Hydroelectric Company, LLC, 150 North Miller Road, Suite 450C,
Fairlawn, OH 44333, (330) 869-8451.
i. FERC Contact: Robert Bell, (202) 502-6062.
j. Deadline for Filing Comments, Protests, and Motions To
Intervene: 60 days from the issuance date of this notice.
The Commission's Rules of Practice and Procedure require all
intervenors filing documents with the Commission to serve a copy of
that document on each person in the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. Description of Project: The proposed project would consist of:
(1) Proposed intake, (2) a proposed 280-foot-long, 7.5-foot-diameter
pentstock, (3) an existing powerhouse containing two generating units
having a total installed capacity of 2 megawatts, (4) an existing 100-
foot-long, 5-foot wide, 7-foot-high concrete conduit tailrace, (5) a
proposed 400-foot-long, 14.y kilovolt transmission line, and (6)
appurtenant facilities. The project would have an annual generation of
10.5 gigawatt-hours that would be sold to a local utility.
l. Locations of Applications: A copy of the application is
available for inspection and reproduction at the Commission in the
Public Reference Room, located at 888 First Street, NE., Room 2A,
Washington, DC 20426, or by calling (202) 502-8371. This filing may
also be viewed on the Commission's Web site at https://www.ferc.gov
using the ``eLibrary'' link. Enter the docket number excluding the last
three digits in the docket number field to access the document. For
assistance, please contact FERC Online Support at
FERCOnlineSupport@ferc.gov or toll free at 1-866-208-3676, or TTY,
contact (202) 502-8659. A copy is also available for inspection and
reproduction at the address in item h. above.
m. Individuals desiring to be included on the Commission's mailing
list should so indicate by writing to the Secretary of the Commission.
n. Competing Preliminary Permit: Anyone desiring to file a
competing application for preliminary permit for a proposed project
must submit the competing application itself, or a notice of intent to
file such an application, to the Commission on or before the specified
comment date for the particular application (see 18 CFR 4.36).
Submission of a timely notice of intent allows an interested person to
file the competing preliminary permit application no later than 30 days
after the specified comment date for the particular application. A
competing preliminary permit application must conform with 18 CFR
4.30(b) and 4.36.
o. Competing Development Application: Any qualified development
applicant desiring to file a competing development application must
submit to the Commission, on or before a specified comment date for the
particular application, either a competing development application or a
notice of intent to file such an application. Submission of a timely
notice of intent to file a development application allows an interested
person to file the competing application no later than 120 days after
the specified comment date for the particular application. A competing
license application must conform with 18 CFR 4.30(b) and 4.36.
p. Notice of Intent: A notice of intent must specify the exact
name, business address, and telephone number of the prospective
applicant, and must include an unequivocal statement of intent to
submit, if such an application may be filed, either a preliminary
permit application or a development application (specify which type of
application). A notice of intent must be served on the applicant(s)
named in this public notice.
q. Proposed Scope of Studies Under Permit: A preliminary permit, if
issued, does not authorize construction. The term of the proposed
preliminary permit would be 36 months. The work proposed under the
preliminary permit would include economic analysis, preparation of
preliminary engineering plans, and a study of environmental impacts.
Based on the results of these studies, the Applicant would decide
whether to proceed with the preparation of a development application to
construct and operate the project.
r. Comments, Protests, or Motions To Intervene: Anyone may submit
comments, a protest, or a motion to intervene in accordance with the
requirements of Rules of Practice and Procedure, 18 CFR 385.210, .211,
.214. In determining the appropriate action to take, the Commission
will consider all protests or other comments filed, but only those who
file a motion to intervene in accordance with the Commission's Rules
may become a party to the proceeding. Any comments, protests, or
motions to intervene must be received on or before the specified
comment date for the particular application.
Comments, protests and interventions may be filed electronically
via the Internet in lieu of paper; see 18 CFR 385.2001 (a)(1)(iii) and
the instructions on the Commission's Web site under ``e-filing'' link.
The Commission strongly encourages electronic filing.
s. Filing and Service of Responsive Documents: Any filings must
bear in all capital letters the title ``COMMENTS'', ``RECOMMENDATIONS
FOR TERMS AND CONDITIONS'', ``PROTEST'', or ``MOTION TO INTERVENE'', as
applicable, and the Project Number of the particular application to
which the filing refers. Any of the above-named documents must be filed
by providing the original and the number of copies provided by the
Commission's regulations to: The Secretary, Federal Energy Regulatory
Commission, 888 First Street, NE., Washington, DC 20426. A copy of any
motion to intervene must also be served upon each representative of the
Applicant specified in the particular application.
t. Agency Comments: Federal, State, and local agencies are invited
to file comments on the described application. A copy of the
application may be obtained by agencies directly from the Applicant. If
an agency does not file
[[Page 1234]]
comments within the time specified for filing comments, it will be
presumed to have no comments. One copy of an agency's comments must
also be sent to the Applicant's representatives.
Magalie R. Salas,
Secretary.
[FR Doc. E5-11 Filed 1-5-05; 8:45 am]
BILLING CODE 6717-01-P