Download as PDF Federal Register / Vol. 70, No. 3 / Wednesday, January 5, 2005 / Notices should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Comment Date: January 22, 2005. addition, the ISO further states that it has posted this filing on the ISO home page. Comment Date: 5 p.m. Eastern Time on January 10, 2005. 3. Intercom Energy, Inc. [Docket No. ER02–267–002] Take notice that on December 17, 2004, Intercom Energy, Inc. submitted for filing with the Federal Energy Regulatory Commission its triennial updated market analysis in accordance with the Commission’s rules and regulations. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 4. Kansas City Power & Light Company [Docket No. ER04–982–001] Buckeye Power, Inc., et al.; Electric Rate and Corporate Filings Take notice that on December 17, 2004, Kansas City Power & Light Company (KCPL) submitted a compliance filing pursuant to the Commission’s Letter Order issued August 5, 2004, in Docket No. ER04– 982–000. KCPL states that copies of the filing were served upon The Empire District Electric Company as well as the Missouri Public Service Commission and the State Corporation Commission of Kansas. Comment Date: 5 p.m. Eastern Time on January 7, 2005. December 27, 2004. 5. Illinois Power Company Magalie R. Salas, Secretary. [FR Doc. E4–3927 Filed 1–4–05; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Docket No. EL05–20–001, et al.] The following filings have been made with the Commission. The filings are listed in ascending order within each docket classification. 1. Buckeye Power, Inc. [Docket No. EL05–20–001] Take notice that on December 20, 2004, Buckeye Power, Inc. (Buckeye) filed additional information regarding its November 3, 2004, filing in Docket No. EL05–20–000, in response to the Commission’s November 30, 2004, deficiency letter. Buckeye states that a copy of the filing has been served on PJM. Comment Date: 5 p.m. Eastern Time on January 3, 2005. 2. California Independent System Operator Corporation [Docket No. ER98–3760–011] Take notice that on December 20, 2004, the California Independent System Operator Corporation (ISO) submitted a filing in compliance with the order issued in Docket No. ER98– 3760–000 on November 19, 2004, 109 FERC ¶ 61,183. The ISO states that this filing has been served upon all parties on the official service list for the captioned docket. In VerDate jul<14>2003 17:49 Jan 04, 2005 Jkt 205001 [Docket No. ER05–173–000] Take notice that on December 22, 2004, Illinois Power Company tendered for filing a Notice of Withdrawal of its November 2, 2004, filing of a ‘‘Tariff for Limited Sales of Excess Energy at Market-Based Rates’’ in the above referenced proceeding. Comment Date: 5 p.m. Eastern Time on January 12, 2005. 6. PSEG Power New York Inc. [Docket No. ER05–323–001] Take notice that on December 17, 2004, PSEG Power New York Inc. (PSEG Power NY), filed an amendment of its December 10, 2004, filing in Docket No. ER05–323–000. PSEG Power NY states it has served a copy of this supplemental filing on the New York Public Service Commission and the parties to the Commission’s official service list for this docket. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 7. PSEG Fossil LLC, PSEG Nuclear LLC [Docket No. ER05–324–001] Take notice that on December 17, 2004, PSEG Fossil LLC (PSEG Fossil) and PSEG Nuclear LLC (PSEG Nuclear) PO 00000 Frm 00027 Fmt 4703 Sfmt 4703 803 (collectively, the Applicants), filed a supplement to correct their December 10, 2004 filing in Docket No. ER05–324– 000. Applicants state they have served a copy of this supplemental filing on the New Jersey Board of Public Utilities, the Pennsylvania Public Utilities Commission and the parties to the Commission’s official service list for this docket. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 8. Southern California Edison Company [Docket No. ER05–352–000] Take notice that on December 17, 2004, Southern California Edison Company (SCE) submitted for filing a Letter Agreement which amends the Interconnection Facilities Agreement (IFA) between Eurus Energy America Corporation (Eurus Energy) and SCE, Service Agreement No. 25 under SCE’s Transmission Owner Tariff FERC Electric Tariff, Second Revised Volume No. 6. SCE states that copies of the filing were served upon the Public Utilities Commission of the State of California and Oasis Power Partners, LLC. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 9. Pacific Gas and Electric Company [Docket No. ER05–353–000] Take notice that on December 17, 2004, Pacific Gas and Electric Company (PG&E) tendered for filing an annual rate update, including rate schedule sheet revisions, to become effective January 1, 2005, to its Reliability MustRun Service Agreements (RMR Agreements) with the California Independent System Operator Corporation (ISO) for Helms Power Plant (PG&E First Revised Rate Schedule FERC No. 207), San Joaquin Power Plant (PG&E First Revised Rate Schedule FERC No. 211) and Kings River Watershed (PG&E Rate Schedule FERC No. 226). PG&E states that copies of the filing have been served upon the ISO, the California Electricity Oversight Board and the California Public Utilities Commission. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 10. San Diego Gas & Electric Company [Docket No. ER05–354–000] Take notice that on December 17, 2004, San Diego Gas & Electric Company (SDG&E) tendered for filing changes to its Transmission Owner Tariff Reliability Services Rates. SDG&E requests an effective date of January 1, 2005 for the proposed rate changes. E:\FR\FM\05JAN1.SGM 05JAN1 804 Federal Register / Vol. 70, No. 3 / Wednesday, January 5, 2005 / Notices SDG&E states that copies of the filing have been served on the California Public Utilities Commission and the California Independent System Operator. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 11. Horsehead Corp. [Docket No. ER05–355–000] Take notice that on December 17, 2004, Horsehead Corp. filed with the Commission a Notice of Succession adopting the Rate Schedule FERC No. 1 of St. Joe Minerals Corporation as superseded, amended, and conformed to the requirements of Order No. 614, Designation of Electric Rate Schedule Sheets, 90 FERC ¶ 61,352 (2000). Comment Date: 5 p.m. Eastern Time on January 7, 2005. 12. Entergy Services, Inc. [Docket No. ER05–356–000] Take notice that on December 17, 2004, Entergy Services, Inc., (Entergy Services) on behalf of Entergy Arkansas, Inc., Entergy Gulf States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and Entergy New Orleans, Inc., tendered for filing the Fifth Revised Network Integration Transmission Service Agreement between Entergy Services and East Texas Electric Cooperative, Inc., Sam Rayburn G&T Electric Cooperative, Inc., and Tex-La Electric Cooperative, Inc. Entergy Services requests an effective date of January 1, 2005. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 13. MidAmerican Energy Company [Docket No. ER05–357–000] Take notice that on December 17, 2004, MidAmerican Energy Company (MidAmerican), filed with the Commission an amended Network Integration Transmission Service Agreement between MidAmerican Energy Company and the City of Sergeant Bluff, Iowa (Sergeant Bluff). MidAmerican requests an effective date of January 1, 2005. MidAmerican states that it has served a copy of the filing on Sergeant Bluff, the Iowa Utilities Board, the Illinois Commerce Commission and the South Dakota Public Utilities Commission. Comment Date: 5 p.m. Eastern Time on January 7, 2005. 14. PacifiCorp [Docket No. ER05–358–000] Take notice that on December 20, 2004, PacifiCorp tendered for filing revisions to its Open Access Transmission Tariff to change VerDate jul<14>2003 17:49 Jan 04, 2005 Jkt 205001 PacifiCorp’s mailing address applicable to all written notifications to PacifiCorp under the Open Access Transmission Tariff. PacifiCorp states that copies of this filing were supplied to the Public Utility Commission of Oregon and the Washington Utilities and Transportation Commission. PacifiCorp’s further states that the existing transmission customers were notified by e-mail. Comment Date: 5 p.m. Eastern Time on January 10, 2005. short-notice intra-hour scheduling of energy transactions between the New England and New York control areas. NEPOOL requests an effective date of January 1, 2005. The NEPOOL Participants Committee states that copies of these materials were sent to the NEPOOL Participants and the New England state governors and regulatory commissions. Comment Date: 5 p.m. Eastern Time on January 10, 2005. 15. Western Systems Power Pool, Inc. 18. DTE Energy Marketing, Inc. [Docket No. ER05–359–000] [Docket No. ER05–362–000] Take notice that on December 20, 2004, the Western Systems Power Pool, Inc. (WSPP) requested amendment of the WSPP Agreement to include East Texas Electric Cooperative, Inc. (ETEC) as a participant. The WSPP seeks an effective date of January 1, 2005, for ETEC’s membership. WSPP states that copies of this filing will be served upon John H. Butts, Manager of ETEC, and Frederick H. Ritts of Brickfield, Burchette, Ritts & Stone, P.C., counsel to ETEC and copies will be e-mailed to WSPP members who have supplied e-mail addresses for the Contract Committee and Contacts lists. Comment Date: 5 p.m. Eastern Time on January 10, 2005. Take notice that on December 20, 2004, DTE Energy Marketing, Inc. (DEM) tendered for filing a Notice of Cancellation of its Market Rate Tariff, designated as FERC Electric Rate Schedule No. 1. DEM requests an effective date of December 21, 2004. Comment Date: 5 p.m. Eastern Time on January 10, 2005. 16. Old Dominion Electric Cooperative [Docket No. ER05–360–000] Take notice that on December 20, 2004, Old Dominion Electric Cooperative (Old Dominion) filed an application under section 205 of the Federal Power Act and 35.13 of the Commission’s Rules and Regulations, for approval of Old Dominion’s Application for Acceptance of Changes to Rate Formula That Do Not Provide for a Rate Increase, and Request for Waivers. Old Dominion requests an effective date of January 1, 2004. Old Dominion states that a copy of the filing was served upon each of the Member Cooperatives and the public service commissions in the Commonwealth of Virginia and the states of Delaware, Maryland and West Virginia. Comment Date: 5 p.m. Eastern Time on January 10, 2005. 17. New England Power Pool [Docket No. ER05–361–000] Take notice that on December 20, 2004, the New England Power Pool (NEPOOL) Participants Committee submitted an amendment to NEPOOL Market Rule 1 to provide for implementation of a test program for a seams reduction initiative involving PO 00000 Frm 00028 Fmt 4703 Sfmt 4703 Standard Paragraph Any person desiring to intervene or to protest this filing must file in accordance with Rules 211 and 214 of the Commission’s Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be considered by the Commission in determining the appropriate action to be taken, but will not serve to make protestants parties to the proceeding. Any person wishing to become a party must file a notice of intervention or motion to intervene, as appropriate. Such notices, motions, or protests must be filed on or before the comment date. Anyone filing a motion to intervene or protest must serve a copy of that document on the Applicant and all parties to this proceeding. The Commission encourages electronic submission of protests and interventions in lieu of paper using the ‘‘eFiling’’ link at https://www.ferc.gov. Persons unable to file electronically should submit an original and 14 copies of the protest or intervention to the Federal Energy Regulatory Commission, 888 First Street, NE., Washington, DC 20426. This filing is accessible on-line at https://www.ferc.gov, using the ‘‘eLibrary’’ link and is available for review in the Commission’s Public Reference Room in Washington, DC. There is an ‘‘eSubscription’’ link on the Web site that enables subscribers to receive e-mail notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please e-mail FERCOnlineSupport@ferc.gov, or call E:\FR\FM\05JAN1.SGM 05JAN1 Federal Register / Vol. 70, No. 3 / Wednesday, January 5, 2005 / Notices Federal Energy Regulatory Commission Cooperative, Inc. (Wolverine Power), submitted a compliance filing pursuant to the Commission’s order issued November 22, 2004, in Docket Nos. ER04–132–000 and EL04–38–000, 109 FERC ¶ 61,191. Wolverine Power states that a copy of this filing has been served upon each person designated on the official service list. Comment Date: 5 p.m. Eastern Time on January 11, 2005. [Docket No. ER03–1079–003, et al.] 4. Delmarva Power & Light Company (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Linda Mitry, Deputy Secretary. [FR Doc. E4–3943 Filed 1–4–05; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Aquila, Inc., et al.; Electric Rate and Corporate Filings December 28, 2004. The following filings have been made with the Commission. The filings are listed in ascending order within each docket classification. 1. Aquila, Inc.; Aquila Long Term, Inc.; Aquila Merchant Services, Inc.; Aquila Piatt County L.L.C.; MEP Clarksdale Power, LLC; MEP Flora Power, LLC; MEP Investments, LLC; MEP Pleasant Hill Operating, LLC; Pleasant Hill Marketing, LLC [Docket Nos. ER03–1079–003, ER02–47–003, ER95–216–023, ER03–725–003, ER02–309– 003, ER02–1016–001, ER99–2322–003, ER01–905–003, ER00–1851–003] Take notice that on December 21, 2004, Aquila, Inc., Aquila Long Term, Inc., Aquila Merchant Services, Inc., Aquila Piatt County L.L.C., MEP Clarksdale Power, LLC, MEP Flora Power, LLC, MEP Investments, LLC, MEP Pleasant Hill Operating, LLC, and Pleasant Hill Marketing, LLC (collectively, Applicants) submitted for filing a joint triennial market power analysis pursuant to Acadia Power Partners LLC, et al., 107 FERC ¶ 61,168 (2004). In addition, Applicants request the Commission to synchronize their future triennial market power analyses. Comment Date: 5 p.m. Eastern Time on January 11, 2005. 2. FirstEnergy Service Corporation [Docket No. ER03–1276–003] Take notice that on December 21, 2004, FirstEnergy Serice Company submitted a compliance filing pursuant to the Commission’s Letter Order issued October 1, 2004, in Docket No. ER03– 1276–003. Comment Date: 5 p.m. Eastern Time on January 11, 2005. 3. Wolverine Power Supply Cooperative, Inc. [Docket Nos. ER04–132–003, EL04–38–004] Take notice that on December 21, 2004, Wolverine Power Supply VerDate jul<14>2003 17:49 Jan 04, 2005 Jkt 205001 [Docket No. ER04–509–002, ER04–1250–001] Take notice that on December 21, 2004, Delaware Municipal Electric Corporation, Inc. submitted a filing providing information requested by the Commission in the deficiency letter issued November 23, 2004, in Docket Nos. ER04–509–000, 001 and ER04– 1250–000 regarding the September 24, 2004, filing of Delmarva Power & Light Company. Comment Date: 5 p.m. Eastern Time on January 11, 2005. 5. Midwest Independent Transmission System Operator, Inc. [Docket No. ER04–961–003] Take notice that, on December 20, 2004, the Midwest Independent Transmission System Operator, Inc. (Midwest ISO) submitted Substitute Tariff Sheets to amend the compliance filing submitted on November 1, 2004 in Docket No. ER04–961–002. The Midwest ISO states that it has electronically served a copy of this filing, with attachments, upon all Midwest ISO Members, Member representatives of Transmission Owners and Non-Transmission Owners, the Midwest ISO Advisory Committee participants, as well as all state commissions within the region. In addition, Midwest ISO states that the filing has been electronically posted on the Midwest ISO’s Web site at https:// www.midwestiso.org under the heading ‘‘Filings to FERC’’ for other interested parties in this matter. The Midwest ISO also states that it will provide hard copies to any interested parties upon request. Comment Date: 5 p.m. Eastern Time on January 10, 2005. 6. Virginia Electric and Power Company [Docket No. ER05–187–001] Take notice that on December 21, 2004, Virginia Electric and Power Company (Dominion) tendered for filing an amendment to its November 5, 2004, filing of an amended Appendix E–2 for the service agreement under its open PO 00000 Frm 00029 Fmt 4703 Sfmt 4703 805 access transmission tariff, FERC Electric Tariff Second Revised Volume No. 5. Dominion requests that the Commission allow the amendment to become effective on November 5, 2004. Dominion states that copies of this filing were served upon the North Carolina Electric Membership Corporation, the North Carolina Utilities Commission and the Virginia State Corporation Commission. Comment Date: 5 p.m. Eastern Time on January 11, 2005. 7. El Segundo Power, LLC [Docket No. ER05–363–000] Take notice that on December 21, 2004, El Segundo Power, LLC (El Segundo) submitted for filing its Rate Schedule No. 2, a Reliability Must-Run Service Agreement (RMR Agreement) between El Segundo and the California Independent System Operator Corporation (CAISO), as well as a letter agreement dated December 20, 2004, between ESP and the CAISO setting forth additional terms and conditions that affect the RMR Agreement. El Segundo states that copies of the filing were served upon the CAISO, Southern California Edison Company, the California Electricity Oversight Board, and the California Public Utilities Commission. Comment Date: 5 p.m. Eastern Time on January 11, 2005. 8. Elk River Windfarm LLC [Docket No. ER05–365–000] Take notice that on December 21, 2004, Elk River Windfarm LLC (Elk River) filed an application for authorization to sell energy, capacity and ancillary services at market-based rates. Elk River states it is developing and will own and operate a wind energy facility in Butler County, Kansas. Elk River requests that the Commission grant waivers and blanket approvals provided to applicants that receive authority for market-based rates. El River requests an effective date of May 5, 2005. Comment Date: 5 p.m. Eastern Time on January 11, 2005. 9. Sierra Pacific Power Company [Docket No. ER05–366–000] Take notice that on December 21, 2004, Sierra Pacific Power Company tendered for filing an executed Standard Large Generator Interconnection Agreement between Sierra Pacific Power Company and Barrick Goldstrike Mines Inc. Sierra Pacific Power Company requests an effective date of July 1, 2005. Comment Date: 5 p.m. Eastern Time on January 11, 2005. E:\FR\FM\05JAN1.SGM 05JAN1

Agencies

[Federal Register Volume 70, Number 3 (Wednesday, January 5, 2005)]
[Notices]
[Pages 803-805]
From the Federal Register Online via the Government Printing Office [www.gpo.gov]
[FR Doc No: E4-3943]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL05-20-001, et al.]


Buckeye Power, Inc., et al.; Electric Rate and Corporate Filings

December 27, 2004.
    The following filings have been made with the Commission. The 
filings are listed in ascending order within each docket 
classification.

1. Buckeye Power, Inc.

[Docket No. EL05-20-001]

    Take notice that on December 20, 2004, Buckeye Power, Inc. 
(Buckeye) filed additional information regarding its November 3, 2004, 
filing in Docket No. EL05-20-000, in response to the Commission's 
November 30, 2004, deficiency letter.
    Buckeye states that a copy of the filing has been served on PJM.
    Comment Date: 5 p.m. Eastern Time on January 3, 2005.

2. California Independent System Operator Corporation

[Docket No. ER98-3760-011]

    Take notice that on December 20, 2004, the California Independent 
System Operator Corporation (ISO) submitted a filing in compliance with 
the order issued in Docket No. ER98-3760-000 on November 19, 2004, 109 
FERC ] 61,183.
    The ISO states that this filing has been served upon all parties on 
the official service list for the captioned docket. In addition, the 
ISO further states that it has posted this filing on the ISO home page.
    Comment Date: 5 p.m. Eastern Time on January 10, 2005.

3. Intercom Energy, Inc.

[Docket No. ER02-267-002]

    Take notice that on December 17, 2004, Intercom Energy, Inc. 
submitted for filing with the Federal Energy Regulatory Commission its 
triennial updated market analysis in accordance with the Commission's 
rules and regulations.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

4. Kansas City Power & Light Company

[Docket No. ER04-982-001]

    Take notice that on December 17, 2004, Kansas City Power & Light 
Company (KCPL) submitted a compliance filing pursuant to the 
Commission's Letter Order issued August 5, 2004, in Docket No. ER04-
982-000.
    KCPL states that copies of the filing were served upon The Empire 
District Electric Company as well as the Missouri Public Service 
Commission and the State Corporation Commission of Kansas.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

5. Illinois Power Company

[Docket No. ER05-173-000]

    Take notice that on December 22, 2004, Illinois Power Company 
tendered for filing a Notice of Withdrawal of its November 2, 2004, 
filing of a ``Tariff for Limited Sales of Excess Energy at Market-Based 
Rates'' in the above referenced proceeding.
    Comment Date: 5 p.m. Eastern Time on January 12, 2005.

6. PSEG Power New York Inc.

[Docket No. ER05-323-001]

    Take notice that on December 17, 2004, PSEG Power New York Inc. 
(PSEG Power NY), filed an amendment of its December 10, 2004, filing in 
Docket No. ER05-323-000.
    PSEG Power NY states it has served a copy of this supplemental 
filing on the New York Public Service Commission and the parties to the 
Commission's official service list for this docket.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

7. PSEG Fossil LLC, PSEG Nuclear LLC

[Docket No. ER05-324-001]

    Take notice that on December 17, 2004, PSEG Fossil LLC (PSEG 
Fossil) and PSEG Nuclear LLC (PSEG Nuclear) (collectively, the 
Applicants), filed a supplement to correct their December 10, 2004 
filing in Docket No. ER05-324-000.
    Applicants state they have served a copy of this supplemental 
filing on the New Jersey Board of Public Utilities, the Pennsylvania 
Public Utilities Commission and the parties to the Commission's 
official service list for this docket.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

8. Southern California Edison Company

[Docket No. ER05-352-000]

    Take notice that on December 17, 2004, Southern California Edison 
Company (SCE) submitted for filing a Letter Agreement which amends the 
Interconnection Facilities Agreement (IFA) between Eurus Energy America 
Corporation (Eurus Energy) and SCE, Service Agreement No. 25 under 
SCE's Transmission Owner Tariff FERC Electric Tariff, Second Revised 
Volume No. 6.
    SCE states that copies of the filing were served upon the Public 
Utilities Commission of the State of California and Oasis Power 
Partners, LLC.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

9. Pacific Gas and Electric Company

[Docket No. ER05-353-000]

    Take notice that on December 17, 2004, Pacific Gas and Electric 
Company (PG&E) tendered for filing an annual rate update, including 
rate schedule sheet revisions, to become effective January 1, 2005, to 
its Reliability Must-Run Service Agreements (RMR Agreements) with the 
California Independent System Operator Corporation (ISO) for Helms 
Power Plant (PG&E First Revised Rate Schedule FERC No. 207), San 
Joaquin Power Plant (PG&E First Revised Rate Schedule FERC No. 211) and 
Kings River Watershed (PG&E Rate Schedule FERC No. 226).
    PG&E states that copies of the filing have been served upon the 
ISO, the California Electricity Oversight Board and the California 
Public Utilities Commission.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

10. San Diego Gas & Electric Company

[Docket No. ER05-354-000]

    Take notice that on December 17, 2004, San Diego Gas & Electric 
Company (SDG&E) tendered for filing changes to its Transmission Owner 
Tariff Reliability Services Rates. SDG&E requests an effective date of 
January 1, 2005 for the proposed rate changes.

[[Page 804]]

    SDG&E states that copies of the filing have been served on the 
California Public Utilities Commission and the California Independent 
System Operator.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

11. Horsehead Corp.

[Docket No. ER05-355-000]

    Take notice that on December 17, 2004, Horsehead Corp. filed with 
the Commission a Notice of Succession adopting the Rate Schedule FERC 
No. 1 of St. Joe Minerals Corporation as superseded, amended, and 
conformed to the requirements of Order No. 614, Designation of Electric 
Rate Schedule Sheets, 90 FERC ] 61,352 (2000).
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

12. Entergy Services, Inc.

[Docket No. ER05-356-000]

    Take notice that on December 17, 2004, Entergy Services, Inc., 
(Entergy Services) on behalf of Entergy Arkansas, Inc., Entergy Gulf 
States, Inc., Entergy Louisiana, Inc., Entergy Mississippi, Inc., and 
Entergy New Orleans, Inc., tendered for filing the Fifth Revised 
Network Integration Transmission Service Agreement between Entergy 
Services and East Texas Electric Cooperative, Inc., Sam Rayburn G&T 
Electric Cooperative, Inc., and Tex-La Electric Cooperative, Inc. 
Entergy Services requests an effective date of January 1, 2005.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

13. MidAmerican Energy Company

[Docket No. ER05-357-000]

    Take notice that on December 17, 2004, MidAmerican Energy Company 
(MidAmerican), filed with the Commission an amended Network Integration 
Transmission Service Agreement between MidAmerican Energy Company and 
the City of Sergeant Bluff, Iowa (Sergeant Bluff). MidAmerican requests 
an effective date of January 1, 2005.
    MidAmerican states that it has served a copy of the filing on 
Sergeant Bluff, the Iowa Utilities Board, the Illinois Commerce 
Commission and the South Dakota Public Utilities Commission.
    Comment Date: 5 p.m. Eastern Time on January 7, 2005.

14. PacifiCorp

[Docket No. ER05-358-000]

    Take notice that on December 20, 2004, PacifiCorp tendered for 
filing revisions to its Open Access Transmission Tariff to change 
PacifiCorp's mailing address applicable to all written notifications to 
PacifiCorp under the Open Access Transmission Tariff.
    PacifiCorp states that copies of this filing were supplied to the 
Public Utility Commission of Oregon and the Washington Utilities and 
Transportation Commission. PacifiCorp's further states that the 
existing transmission customers were notified by e-mail.
    Comment Date: 5 p.m. Eastern Time on January 10, 2005.

15. Western Systems Power Pool, Inc.

[Docket No. ER05-359-000]

    Take notice that on December 20, 2004, the Western Systems Power 
Pool, Inc. (WSPP) requested amendment of the WSPP Agreement to include 
East Texas Electric Cooperative, Inc. (ETEC) as a participant. The WSPP 
seeks an effective date of January 1, 2005, for ETEC's membership.
    WSPP states that copies of this filing will be served upon John H. 
Butts, Manager of ETEC, and Frederick H. Ritts of Brickfield, 
Burchette, Ritts & Stone, P.C., counsel to ETEC and copies will be e-
mailed to WSPP members who have supplied e-mail addresses for the 
Contract Committee and Contacts lists.
    Comment Date: 5 p.m. Eastern Time on January 10, 2005.

16. Old Dominion Electric Cooperative

[Docket No. ER05-360-000]

    Take notice that on December 20, 2004, Old Dominion Electric 
Cooperative (Old Dominion) filed an application under section 205 of 
the Federal Power Act and 35.13 of the Commission's Rules and 
Regulations, for approval of Old Dominion's Application for Acceptance 
of Changes to Rate Formula That Do Not Provide for a Rate Increase, and 
Request for Waivers. Old Dominion requests an effective date of January 
1, 2004.
    Old Dominion states that a copy of the filing was served upon each 
of the Member Cooperatives and the public service commissions in the 
Commonwealth of Virginia and the states of Delaware, Maryland and West 
Virginia.
    Comment Date: 5 p.m. Eastern Time on January 10, 2005.

17. New England Power Pool

[Docket No. ER05-361-000]

    Take notice that on December 20, 2004, the New England Power Pool 
(NEPOOL) Participants Committee submitted an amendment to NEPOOL Market 
Rule 1 to provide for implementation of a test program for a seams 
reduction initiative involving short-notice intra-hour scheduling of 
energy transactions between the New England and New York control areas. 
NEPOOL requests an effective date of January 1, 2005.
    The NEPOOL Participants Committee states that copies of these 
materials were sent to the NEPOOL Participants and the New England 
state governors and regulatory commissions.
    Comment Date: 5 p.m. Eastern Time on January 10, 2005.

18. DTE Energy Marketing, Inc.

[Docket No. ER05-362-000]

    Take notice that on December 20, 2004, DTE Energy Marketing, Inc. 
(DEM) tendered for filing a Notice of Cancellation of its Market Rate 
Tariff, designated as FERC Electric Rate Schedule No. 1. DEM requests 
an effective date of December 21, 2004.
    Comment Date: 5 p.m. Eastern Time on January 10, 2005.

Standard Paragraph

    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. Such notices, 
motions, or protests must be filed on or before the comment date. 
Anyone filing a motion to intervene or protest must serve a copy of 
that document on the Applicant and all parties to this proceeding.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at https://
www.ferc.gov. Persons unable to file electronically should submit an 
original and 14 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    This filing is accessible on-line at https://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
FERCOnlineSupport@ferc.gov, or call

[[Page 805]]

(866) 208-3676 (toll free). For TTY, call (202) 502-8659.

Linda Mitry,
Deputy Secretary.
[FR Doc. E4-3943 Filed 1-4-05; 8:45 am]
BILLING CODE 6717-01-P