DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. TX02-1-002]

 
Pinnacle West Capital Corp.; Notice of Technical Conference

October 29, 2009.
    On July 15, 2008, Electrical District No. 3 of the County of Pinal, 
State of Arizona (ED-3) submitted for filing, pursuant to sections 211 
and 212 of the Federal Power Act,\1\ a change to the transmission 
service agreement (service agreement) between ED-3 and Pinnacle West 
Capital Corporation (Pinnacle West). Take notice that the Commission 
staff will hold a technical conference on November 19, 2009, from 9 
a.m. to 5 p.m. (Eastern Time) in room 3M-3 at the Federal Energy 
Regulatory Commission, 888 First Street, NE., Washington, DC 20426.
---------------------------------------------------------------------------

    \1\ 16 U.S.C. 824j, 824k (2006).
---------------------------------------------------------------------------

    The purpose of this technical conference is to obtain additional 
information regarding ED-3's submittal in order that the Commission 
staff is able to develop a complete record for review. Specifically, 
the conference is to focus on issues related to the degree of 
integration of the ED-3 transmission and distribution system. In order 
to facilitate this discussion, the Commission staff will seek 
additional information regarding, but not limited to, the following:
    1. The topology and operational characteristics of ED-3's 
transmission and distribution systems.
    2. How ED-3 delineates transmission and distribution facilities;
    3. The point(s) of receipt for energy received from the Arizona 
Public Service Company (APS) system; the point(s) of interconnection 
where energy is delivered to APS customers; the location of lines 
(indicate voltage levels), transformers, breakers, switches, meters 
used to serve such customers; APS extensions used to serve APS load 
outside of the ED-3 system; and the location of facilities currently 
under construction and planned for the next five years;
    4. Whether there are there any customers other than APS served 
simultaneously from the point(s) or connected to the line(s) where APS 
customers receive energy; and,
    5. Identification of all paths by which APS customers are served 
and the identification of any alternative paths by which APS customers 
may be served in both normal system state and during contingencies.
    ED-3 should be prepared to provide a brief presentation to address 
the above information as well as provide any necessary support for each 
response. Support for the issues identified above should include color-
coded system-wide and voltage level specific one-line diagrams, power 
flow and other completed system studies, long-term transmission plans, 
load forecast studies and any additional information that will assist 
the Commission staff. This information should be filed with the 
Commission at least ten days prior to the date of the technical 
conference. The opportunity for comments on any additionally filed 
supplemental information will be governed by a future Commission notice 
regarding that filing.
    Commission conferences are accessible under section 508 of the 
Rehabilitation Act of 1973. For accessibility accommodations, please 
send an e-mail to accessibility@ferc.gov or call toll free 1-866-208-
3372 (voice) or 202-208-1659 (TTY), or send a FAX to 202-208-2106 with 
the required accommodations.
    For more information about this conference, please contact 
Christopher Thomas, 202-502-8412, christopher.thomas@ferc.gov, 
regarding substantive concerns.

Kimberly D. Bose,
Secretary.