Southern Natural Gas Company, LLC; Notice of Schedule for Environmental Review of the Fairburn Expansion Project, 28652-28653 [2017-13088]
Download as PDF
asabaliauskas on DSKBBXCHB2PROD with NOTICES
28652
Federal Register / Vol. 82, No. 120 / Friday, June 23, 2017 / Notices
Description: Notice of Change in
Status of Portland General Electric
Company.
Filed Date: 6/19/17.
Accession Number: 20170619–5087.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER10–2633–033;
ER10–2717–004; ER13–55–022.
Applicants: Birchwood Power
Partners, L.P., EFS Parlin Holdings,
LLC, Homer City Generation, L.P.
Description: Updated Market Power
Analysis for the Northeast Region of
Birchwood Power Partners, L.P., et al.
Filed Date: 6/19/17.
Accession Number: 20170619–5096.
Comments Due: 5 p.m. ET 8/18/17.
Docket Numbers: ER13–1504–005;
ER10–2866–004; ER10–2861–004.
Applicants: SWG Arapahoe, LLC,
SWG Colorado, LLC, Fountain Valley
Power, L.L.C.
Description: Notice of Non-Material
Change in Status of SWG Arapahoe,
LLC, et al.
Filed Date: 6/19/17.
Accession Number: 20170619–5090.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–264–001.
Applicants: Southwest Power Pool,
Inc.
Description: Tariff Amendment:
Amended Filing in ER17–264—AEP
Formula Rate Revisions to be effective
7/1/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5081.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1671–001.
Applicants: Gulf Coast Solar Center II,
LLC.
Description: Tariff Amendment:
Amendment to Application for MBR to
be effective 5/31/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5086.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1672–001.
Applicants: Gulf Coast Solar Center
III, LLC.
Description: Tariff Amendment:
Amendment to Application for MBR to
be effective 5/31/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5092.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1850–000.
Applicants: Bishop Hill Energy LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5039.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1851–000.
Applicants: Blue Sky East, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
VerDate Sep<11>2014
19:21 Jun 22, 2017
Jkt 241001
Filed Date: 6/19/17.
Accession Number: 20170619–5041.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1852–000.
Applicants: Canandaigua Power
Partners, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5042.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1853–000.
Applicants: Canandaigua Power
Partners II, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5043.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1854–000.
Applicants: Erie Wind, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5044.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1855–000.
Applicants: Evergreen Wind Power,
LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5045.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1856–000.
Applicants: Evergreen Wind Power
III, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5046.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1857–000.
Applicants: Niagara Wind Power,
LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5047.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1858–000.
Applicants: Stetson Holdings, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5048.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1859–000.
Applicants: Stetson Wind II, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
PO 00000
Frm 00035
Fmt 4703
Sfmt 4703
Filed Date: 6/19/17.
Accession Number: 20170619–5053.
Comments Due: 5 p.m. ET 7/10/17.
Docket Numbers: ER17–1860–000.
Applicants: Vermont Wind, LLC.
Description: § 205(d) Rate Filing:
Revised Market-Based Rate Tariff to be
effective 8/19/2017.
Filed Date: 6/19/17.
Accession Number: 20170619–5058.
Comments Due: 5 p.m. ET 7/10/17.
The filings are accessible in the
Commission’s eLibrary system by
clicking on the links or querying the
docket number.
Any person desiring to intervene or
protest in any of the above proceedings
must file in accordance with Rules 211
and 214 of the Commission’s
Regulations (18 CFR 385.211 and
385.214) on or before 5:00 p.m. Eastern
time on the specified comment date.
Protests may be considered, but
intervention is necessary to become a
party to the proceeding.
eFiling is encouraged. More detailed
information relating to filing
requirements, interventions, protests,
service, and qualifying facilities filings
can be found at: https://www.ferc.gov/
docs-filing/efiling/filing-req.pdf. For
other information, call (866) 208–3676
(toll free). For TTY, call (202) 502–8659.
Dated: June 19, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–13109 Filed 6–22–17; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
[Docket No. CP17–46–000]
Southern Natural Gas Company, LLC;
Notice of Schedule for Environmental
Review of the Fairburn Expansion
Project
On February 3, 2017, Southern
Natural Gas Company, LLC (Southern)
filed an application in Docket No.
CP17–46–000 requesting a Certificate of
Public Convenience and Necessity
pursuant to section 7(c) of the Natural
Gas Act to construct and operate certain
natural gas pipeline facilities. The
proposed project is known as the
Fairburn Expansion Project, and would
add 343,164 dekatherms per day of firm
transportation service to its existing
pipeline system.
On February 17, 2017 the Federal
Energy Regulatory Commission
(Commission or FERC) issued its Notice
of Application for the Project. Among
E:\FR\FM\23JNN1.SGM
23JNN1
Federal Register / Vol. 82, No. 120 / Friday, June 23, 2017 / Notices
other things, that notice alerted agencies
issuing federal authorizations of the
requirement to complete all necessary
reviews and to reach a final decision on
a request for a federal authorization
within 90 days of the date of issuance
of the Commission staff’s Environmental
Assessment (EA) for the Project. This
instant notice identifies the FERC staff’s
planned schedule for the completion of
the EA for the Project.
Schedule for Environmental Review
Issuance of EA: August 18, 2017.
90-day Federal Authorization
Decision Deadline: November 16, 2017.
If a schedule change becomes
necessary, additional notice will be
provided so that the relevant agencies
are kept informed of the Project’s
progress.
Project Description
Southern would upgrade and
construct certain compression and
pipeline facilities in Fayetteville and
Fulton Counties, Georgia (including
installing a new 4.9-mile-long 30-inchdiameter Fairburn Lateral and the new
18,000-horsepower electric Fairburn
Compressor Station); and Clayton and
Cobb Counties Georgia.
Background
On March 20, 2017, the Commission
issued a Notice of Intent To Prepare an
Environmental Assessment for the
Proposed Fairburn Expansion Project
and Request for Comments on
Environmental Issues (NOI). The NOI
was sent to affected landowners; federal,
state, and local government agencies;
elected officials; environmental and
public interest groups; Native American
tribes; other interested parties; and local
libraries and newspapers. In response to
the NOI, the Commission received
comments from the U.S. Environmental
Protection Agency (EPA) and five
landowners. The primary issues raised
by the commentors are safety and
residential impacts during construction,
and operational safety in association
with electric power line collocation.
The EPA and the U.S. Army Corps of
Engineers are cooperating agencies in
the preparation of the EA.
asabaliauskas on DSKBBXCHB2PROD with NOTICES
Additional Information
In order to receive notification of the
issuance of the EA and to keep track of
all formal issuances and submittals in
specific dockets, the Commission offers
a free service called eSubscription. This
can reduce the amount of time you
spend researching proceedings by
automatically providing you with
notification of these filings, document
summaries, and direct links to the
VerDate Sep<11>2014
19:21 Jun 22, 2017
Jkt 241001
documents. Go to www.ferc.gov/docsfiling/esubscription.asp.
Additional information about the
Project is available from the
Commission’s Office of External Affairs
at (866) 208–FERC or on the FERC Web
site (www.ferc.gov). Using the eLibrary
link, select General Search from the
eLibrary menu, enter the selected date
range and Docket Number excluding the
last three digits (i.e., CP17–47), and
follow the instructions. For assistance
with access to eLibrary, the helpline can
be reached at (866) 208–3676, TTY (202)
502–8659, or at FERCOnlineSupport@
ferc.gov. The eLibrary link on the FERC
Web site also provides access to the
texts of formal documents issued by the
Commission, such as orders, notices,
and rule makings.
Dated: June 16, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017–13088 Filed 6–22–17; 8:45 am]
BILLING CODE 6717–01–P
ENVIRONMENTAL PROTECTION
AGENCY
[EPA–HQ–OARM–2016–0762; FRL–9963–
18–OEI]
Information Collection Request
Submitted to OMB for Review and
Approval; Comment Request; General
Administrative Requirements for
Assistance Programs (Renewal)
Environmental Protection
Agency (EPA).
ACTION: Notice.
AGENCY:
The Environmental Protection
Agency has submitted an information
collection request (ICR), General
Administrative Requirements for
Assistance Programs (Renewal), to the
Office of Management and Budget
(OMB) for review and approval in
accordance with the Paperwork
Reduction Act. This is a proposed
extension of the ICR, which is currently
approved through June 30, 2017. Public
comments were previously requested
via the Federal Register on February 8,
2017 during a 60-day comment period.
This notice allows for an additional 30
days for public comments. A fuller
description of the ICR is given below,
including its estimated burden and cost
to the public. An Agency may not
conduct or sponsor and a person is not
required to respond to a collection of
information unless it displays a
currently valid OMB control number.
DATES: Additional comments may be
submitted on or before July 24, 2017.
SUMMARY:
PO 00000
Frm 00036
Fmt 4703
Sfmt 4703
28653
Submit your comments,
referencing Docket ID Number EPA–
HQ–OARM–2016–0762, to (1) EPA
online using www.regulations.gov (our
preferred method), by email to
oei.docket@epa.gov, or by mail to: EPA
Docket Center, Environmental
Protection Agency, Mail Code 28221T,
1200 Pennsylvania Ave. NW.,
Washington, DC 20460, and (2) OMB via
email to oira_submission@omb.eop.gov.
Address comments to OMB Desk Officer
for EPA.
EPA’s policy is that all comments
received will be included in the public
docket without change including any
personal information provided, unless
the comment includes profanity, threats,
information claimed to be Confidential
Business Information (CBI) or other
information whose disclosure is
restricted by statute.
FOR FURTHER INFORMATION CONTACT:
Elizabeth January, Office of Grants and
Debarment, National Policy, Training
and Compliance Division, Mail Code:
3903R, Environmental Protection
Agency, 1200 Pennsylvania Ave. NW.,
Washington, DC 20460; telephone
number: (617) 918–8655; fax number:
(202) 565–2470; email address:
January.Elizabeth@epa.gov.
SUPPLEMENTARY INFORMATION:
Supporting documents for the General
Administrative Requirements for
Assistance Programs (EPA ICR No.
0938.21, OMB Control No. 2030–0020),
which explain in detail the information
that the EPA will be collecting are
available in the public docket for this
ICR. The docket can be viewed online
at www.regulations.gov or in person at
the EPA Docket Center, WJC West,
Room 3334, 1301 Constitution Ave.
NW., Washington, DC. The telephone
number for the Docket Center is 202–
566–1744. For additional information
about EPA’s public docket, visit https://
www.epa.gov/dockets.
Abstract: The information is collected
from applicants/recipients of EPA
assistance to monitor adherence to the
programmatic and administrative
requirements of the Agency’s financial
assistance program. It is used to make
awards, pay recipients, and collect
information on how Federal funds are
being spent. EPA needs this information
to meet its Federal stewardship
responsibilities. This ICR renewal
requests authorization for the collection
of information under EPA’s General
Regulation for Assistance Programs,
which establishes minimum
management requirements for all
recipients of EPA grants or cooperative
agreements (assistance agreements).
Recipients must respond to these
ADDRESSES:
E:\FR\FM\23JNN1.SGM
23JNN1
Agencies
[Federal Register Volume 82, Number 120 (Friday, June 23, 2017)]
[Notices]
[Pages 28652-28653]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-13088]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP17-46-000]
Southern Natural Gas Company, LLC; Notice of Schedule for
Environmental Review of the Fairburn Expansion Project
On February 3, 2017, Southern Natural Gas Company, LLC (Southern)
filed an application in Docket No. CP17-46-000 requesting a Certificate
of Public Convenience and Necessity pursuant to section 7(c) of the
Natural Gas Act to construct and operate certain natural gas pipeline
facilities. The proposed project is known as the Fairburn Expansion
Project, and would add 343,164 dekatherms per day of firm
transportation service to its existing pipeline system.
On February 17, 2017 the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among
[[Page 28653]]
other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA: August 18, 2017.
90-day Federal Authorization Decision Deadline: November 16, 2017.
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
Southern would upgrade and construct certain compression and
pipeline facilities in Fayetteville and Fulton Counties, Georgia
(including installing a new 4.9-mile-long 30-inch-diameter Fairburn
Lateral and the new 18,000-horsepower electric Fairburn Compressor
Station); and Clayton and Cobb Counties Georgia.
Background
On March 20, 2017, the Commission issued a Notice of Intent To
Prepare an Environmental Assessment for the Proposed Fairburn Expansion
Project and Request for Comments on Environmental Issues (NOI). The NOI
was sent to affected landowners; federal, state, and local government
agencies; elected officials; environmental and public interest groups;
Native American tribes; other interested parties; and local libraries
and newspapers. In response to the NOI, the Commission received
comments from the U.S. Environmental Protection Agency (EPA) and five
landowners. The primary issues raised by the commentors are safety and
residential impacts during construction, and operational safety in
association with electric power line collocation.
The EPA and the U.S. Army Corps of Engineers are cooperating
agencies in the preparation of the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC Web site (www.ferc.gov). Using the eLibrary link, select General
Search from the eLibrary menu, enter the selected date range and Docket
Number excluding the last three digits (i.e., CP17-47), and follow the
instructions. For assistance with access to eLibrary, the helpline can
be reached at (866) 208-3676, TTY (202) 502-8659, or at
FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC Web site also
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rule makings.
Dated: June 16, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-13088 Filed 6-22-17; 8:45 am]