City of Escondido, California, & Vista Irrigation District; Notice of Effective Date for Exemption From Licensing (Conduit), Surrender of License, and Dismissal of Relicense Application, 23562-23563 [2017-10514]

Download as PDF 23562 Federal Register / Vol. 82, No. 98 / Tuesday, May 23, 2017 / Notices eRegistration account using the eRegistration link. Select the eFiling link to log on and submit the intervention or protests. Persons unable to file electronically should submit an original and 5 copies of the intervention or protest to the Federal Energy Regulatory Commission, 888 First Street NE., Washington, DC 20426. The filings in the above-referenced proceeding are accessible in the Commission’s eLibrary system by clicking on the appropriate link in the above list. They are also available for electronic review in the Commission’s Public Reference Room in Washington, DC. There is an eSubscription link on the Web site that enables subscribers to receive email notification when a document is added to a subscribed docket(s). For assistance with any FERC Online service, please email FERCOnlineSupport@ferc.gov. or call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 17, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–10512 Filed 5–22–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project Nos. 6168–024 & 7057–009] sradovich on DSK3GMQ082PROD with NOTICES B C Hydro, Inc., Highland Hydro Constructors of California, Inc., Shamrock Utilities, LLC; Notice of Transfer of Exemption 1. By letter filed January 23, 2017, Shamrock Utilities, LLC informed the Commission that the exemption from licensing for the Cedar Flat Project No. 6168, originally issued September 28, 1982 1 located on Mill Creek in Trinity County, California and occupies lands within Shasta-Trinity National Forest; and the Clover Leaf Ranch Project No. 7057, originally issued July 12, 1983 2 located on Clover Creek in Shasta County, California have been transferred to Shamrock Utilities, LLC. The transfer of an exemption does not require Commission approval. 2. Shamrock Utilities, LLC is now the exemptee of the Cedar Flat Project No. 6168 and the Clover Leaf Ranch Project 1 Order Granting Exemption from Licensing of a Small Hydroelectric Project of 5 MW or Less. Richard Bean and Fred Castagna, 20 FERC 62,550 (1982). 2 Order Granting Exemption from Licensing of a Small Hydroelectric Project of 5 Megawatts or Less. Mega Hydro, Inc., 24 FERC 62,041. VerDate Sep<11>2014 21:15 May 22, 2017 Jkt 241001 No. 7057. All correspondence should be forwarded to: Theresa A. Ungaro, President/Owner, Shamrock Utilities, LLC, P. O. Box 859, Palo Cedro, CA 96073. Dated: May 17, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–10516 Filed 5–22–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Dated: May 16, 2017. Kimberly D. Bose, Secretary. Federal Energy Regulatory Commission [FR Doc. 2017–10523 Filed 5–22–17; 8:45 am] Combined Notice of Filings BILLING CODE 6717–01–P Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP17–743–000. Applicants: Ozark Gas Transmission, L.L.C. Description: Ozark Gas Transmission, L.L.C. submits tariff filing per 154.204: BP Energy K820104 Negotiated Rate eff 5–1–2021 to be effective 5/1/2021. Filed Date: 05/12/2017. Accession Number: 20170512–5030. Comment Date: 5:00 p.m. Eastern Time on Wednesday, May 24, 2017. Docket Numbers: RP17–744–000. Applicants: East Tennessee Natural Gas, LLC. Description: East Tennessee Natural Gas, LLC submits tariff filing per 154.204: Duke Energy Progress K410135 Neg Rate eff. 11–1–2017 to be effective 11/1/2017. Filed Date: 05/12/2017. Accession Number: 20170512–5058. Comment Date: 5:00 p.m. Eastern Time on Wednesday, May 24, 2017. Docket Numbers: RP17–745–000. Applicants: Kern River Gas Transmission Company. Description: Kern River Gas Transmission Company submits tariff filing per 154.204: 2017 Nonconforming Alt P2 and P2 Insulated TSAs to be effective 5/1/2017. Filed Date: 05/12/2017. Accession Number: 20170512–5195. Comment Date: 5:00 p.m. Eastern Time on Wednesday, May 24, 2017. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and PO 00000 Frm 00042 Fmt 4703 Sfmt 4703 § 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. DEPARTMENT OF ENERGY Federal Energy Regulatory Commission [Project Nos. 176–018; 176–035] City of Escondido, California, & Vista Irrigation District; Notice of Effective Date for Exemption From Licensing (Conduit), Surrender of License, and Dismissal of Relicense Application On September 25, 2012, the Commission issued a Conditional Order Granting Exemption from Licensing (Conduit), Accepting Surrender of License, and Dismissing Relicense Application for the Escondido Project No. 176 (the 2012 Order).1 The Escondido Project is located on the San Luis Rey River and Escondido Creek, near the city of Escondido, in San Diego County, California. The 2012 Order approved a conduit exemption for the Bear Valley Powerhouse Project No. 176 (part of the existing Escondido Project) and accepted surrender of the license for the remaining project facilities. Both the conduit exemption and the license surrender were contingent on certain conditions being met including the protection of historic properties, approval of a water rights settlement agreement, dismissal of pending court proceedings, and obtaining a rights-ofway agreement for parts of the project that would continue to occupy federal land after the surrender. The 2012 order also dismissed the relicense application for the Escondido Project, effective as of the effective date of the conduit exemption and license surrender. On May 3, 2017, the City of Escondido and Vista Irrigation District filed documentation that all conditions 1 City of Escondido and Vista Irrigation District, 140 FERC 62,226 (2012). E:\FR\FM\23MYN1.SGM 23MYN1 Federal Register / Vol. 82, No. 98 / Tuesday, May 23, 2017 / Notices in the 2012 Order have been satisfied. Therefore, the new Bear Valley Powerhouse Project No. 176 conduit exemption, the license surrender for the Escondido Project No. 176, and our dismissal of the relicensing application are all effective as of the date of this notice. Dated: May 17, 2017. Kimberly D. Bose, Secretary. [FR Doc. 2017–10514 Filed 5–22–17; 8:45 am] BILLING CODE 6717–01–P DEPARTMENT OF ENERGY Federal Energy Regulatory Commission sradovich on DSK3GMQ082PROD with NOTICES Combined Notice of Filings #1 Take notice that the Commission received the following electric rate filings: Docket Numbers: ER13–1504–003; ER10–2861–002; ER10–2866–002. Applicants: SWG Arapahoe, LLC, SWG Colorado, LLC, Fountain Valley Power, L.L.C. Description: Supplement to December 28, 2016 Triennial Market Power Analysis for the Northwest Region of the Southwest Generation Operating Company Sellers. Filed Date: 5/16/17. Accession Number: 20170516–5113. Comments Due: 5 p.m. ET 6/6/17. Docket Numbers: ER17–1612–000. Applicants: PJM Interconnection, L.L.C. Description: Tariff Cancellation: Notice of Cancellation of Service Agreement No. 3637, Queue No. Y1–084 to be effective 3/27/2017. Filed Date: 5/16/17. Accession Number: 20170516–5082. Comments Due: 5 p.m. ET 6/6/17. Docket Numbers: ER17–1613–000. Applicants: PJM Interconnection, L.L.C. Description: § 205(d) Rate Filing: Wholesale Market Participation Agreement No. 4700; Queue No. AC1– 030 to be effective 4/25/2017. Filed Date: 5/16/17. Accession Number: 20170516–5087. Comments Due: 5 p.m. ET 6/6/17. Docket Numbers: ER17–1614–000. Applicants: Duke Energy Carolinas, LLC. Description: § 205(d) Rate Filing: DECDue West RS No. 329 Revised PPA to be effective 1/1/2016. Filed Date: 5/17/17. Accession Number: 20170517–5007. Comments Due: 5 p.m. ET 6/7/17. Docket Numbers: ER17–1615–000. VerDate Sep<11>2014 21:15 May 22, 2017 Jkt 241001 Applicants: McCallum Enterprises I Limited Partnership. Description: Request for Waiver of McCallum Enterprises I Limited Partnership. Filed Date: 5/11/17. Accession Number: 20170511–5080. Comments Due: 5 p.m. ET 6/1/17. Docket Numbers: ER17–1616–000. Applicants: Solios Power Trading LLC. Description: Tariff Cancellation: Cancellation of Market Based Rate Tariff to be effective 5/22/2017. Filed Date: 5/17/17. Accession Number: 20170517–5044. Comments Due: 5 p.m. ET 6/7/17. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. Dated: May 17, 2017. Kimberly D. Bose, Secretary. DEPARTMENT OF ENERGY [FR Doc. 2017–10511 Filed 5–22–17; 8:45 am] BILLING CODE 6717–01–P Environmental Protection Agency (EPA). ACTION: Notice. Combined Notice of Filings Take notice that the Commission has received the following Natural Gas Pipeline Rate and Refund Report filings: Filings Instituting Proceedings Docket Numbers: RP17–746–000. Applicants: Gulf South Pipeline Company, LP. Description: Gulf South Pipeline Company, LP submits tariff filing per 154.204: Housekeeping Filing 5–16– 2017 to be effective 6/6/2016. Filed Date: 05/16/2017. Accession Number: 20170516–5067. Comment Date: 5:00 p.m. Eastern Time on Tuesday, May 30, 2017. Sfmt 4703 [FRL–9961–62–OA] AGENCY: Federal Energy Regulatory Commission Fmt 4703 Dated: May 17, 2017. Kimberly D. Bose, Secretary. Notification of a Public Teleconference of the Chartered Clean Air Scientific Advisory Committee (CASAC) and the CASAC Sulfur Oxides Panel BILLING CODE 6717–01–P Frm 00043 Docket Numbers: RP17–747–000. Applicants: Empire Pipeline, Inc. Description: Empire Pipeline, Inc. submits tariff filing per 154.403(d)(2): Fuel Tracker (Empire tracking Supply) to be effective 6/1/2017. Filed Date: 05/16/2017. Accession Number: 20170516–5097. Comment Date: 5:00 p.m. Eastern Time on Tuesday, May 30, 2017. The filings are accessible in the Commission’s eLibrary system by clicking on the links or querying the docket number. Any person desiring to intervene or protest in any of the above proceedings must file in accordance with Rules 211 and 214 of the Commission’s Regulations (18 CFR 385.211 and § 385.214) on or before 5:00 p.m. Eastern time on the specified comment date. Protests may be considered, but intervention is necessary to become a party to the proceeding. eFiling is encouraged. More detailed information relating to filing requirements, interventions, protests, service, and qualifying facilities filings can be found at: https://www.ferc.gov/ docs-filing/efiling/filing-req.pdf. For other information, call (866) 208–3676 (toll free). For TTY, call (202) 502–8659. ENVIRONMENTAL PROTECTION AGENCY [FR Doc. 2017–10510 Filed 5–22–17; 8:45 am] PO 00000 23563 The EPA Science Advisory Board (SAB) Staff Office announces a public teleconference of the Chartered Clean Air Scientific Advisory Committee (CASAC) and CASAC Sulfur Oxides Panel to discuss the CASAC draft review of the EPA’s Integrated Science Assessment (ISA) for Sulfur Oxides—Health Criteria (Second External Review Draft—December 2016). DATES: The teleconference will be held on Tuesday, June 20, 2017, from 1:00 p.m. to 4:00 p.m. (Eastern Time). Location: The public teleconference will be held by telephone only. SUMMARY: E:\FR\FM\23MYN1.SGM 23MYN1

Agencies

[Federal Register Volume 82, Number 98 (Tuesday, May 23, 2017)]
[Notices]
[Pages 23562-23563]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-10514]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project Nos. 176-018; 176-035]


City of Escondido, California, & Vista Irrigation District; 
Notice of Effective Date for Exemption From Licensing (Conduit), 
Surrender of License, and Dismissal of Relicense Application

    On September 25, 2012, the Commission issued a Conditional Order 
Granting Exemption from Licensing (Conduit), Accepting Surrender of 
License, and Dismissing Relicense Application for the Escondido Project 
No. 176 (the 2012 Order).\1\ The Escondido Project is located on the 
San Luis Rey River and Escondido Creek, near the city of Escondido, in 
San Diego County, California.
---------------------------------------------------------------------------

    \1\ City of Escondido and Vista Irrigation District, 140 FERC 
62,226 (2012).
---------------------------------------------------------------------------

    The 2012 Order approved a conduit exemption for the Bear Valley 
Powerhouse Project No. 176 (part of the existing Escondido Project) and 
accepted surrender of the license for the remaining project facilities. 
Both the conduit exemption and the license surrender were contingent on 
certain conditions being met including the protection of historic 
properties, approval of a water rights settlement agreement, dismissal 
of pending court proceedings, and obtaining a rights-of-way agreement 
for parts of the project that would continue to occupy federal land 
after the surrender. The 2012 order also dismissed the relicense 
application for the Escondido Project, effective as of the effective 
date of the conduit exemption and license surrender.
    On May 3, 2017, the City of Escondido and Vista Irrigation District 
filed documentation that all conditions

[[Page 23563]]

in the 2012 Order have been satisfied. Therefore, the new Bear Valley 
Powerhouse Project No. 176 conduit exemption, the license surrender for 
the Escondido Project No. 176, and our dismissal of the relicensing 
application are all effective as of the date of this notice.

    Dated: May 17, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-10514 Filed 5-22-17; 8:45 am]
BILLING CODE 6717-01-P