Summit Hydropower, Inc.; Aspinook Hydro, LLC; Notice of Application for Transfer of License and Soliciting Comments, Motions To Intervene, and Protests, 26222 [2016-10141]
Download as PDF
srobinson on DSK5SPTVN1PROD with NOTICES
26222
Federal Register / Vol. 81, No. 84 / Monday, May 2, 2016 / Notices
acre; (3) a 20-foot by 10-foot enclosed
concrete intake structure; (4) a 7,258foot-long pipeline and a 5,230-foot-long
penstock with a net head of 791 feet; (5)
a 50-foot by 50-foot powerhouse
containing one generating unit with a
5,000-kilowatt capacity; (6) a 50-foot by
50-foot substation area; (7) a 40-foot by
35-foot switchyard; (8) 100-foot by 100foot multipurpose area; and (9) a new
12-mile-long, 60-kilovolt transmission
line. The project is estimated to produce
approximately 25,000,000 kilowatt
hours annually.
m. A copy of the application is
available for review at the Commission
in the Public Reference Room or may be
viewed on the Commission’s Web site at
https://www.ferc.gov using the
‘‘eLibrary’’ link. Enter the docket
number excluding the last three digits in
the docket number field to access the
document. For assistance, contact FERC
Online Support. A copy is also available
for inspection and reproduction at the
address in item h above.
All filings must (1) bear in all capital
letters the title ‘‘COMMENTS’’, ‘‘REPLY
COMMENTS’’,
‘‘RECOMMENDATIONS,’’ ‘‘TERMS
AND CONDITIONS,’’ or
‘‘PRESCRIPTIONS;’’ (2) set forth in the
heading the name of the applicant and
the project number of the application to
which the filing responds; (3) furnish
the name, address, and telephone
number of the person submitting the
filing; and (4) otherwise comply with
the requirements of 18 CFR 385.2001
through 385.2005. All comments,
recommendations, terms and conditions
or prescriptions must set forth their
evidentiary basis and otherwise comply
with the requirements of 18 CFR 4.34(b).
Agencies may obtain copies of the
application directly from the applicant.
Each filing must be accompanied by
proof of service on all persons listed on
the service list prepared by the
Commission in this proceeding, in
accordance with 18 CFR 4.34(b), and
385.2010.
You may also register online at https://
www.ferc.gov/docs-filing/
esubscription.asp to be notified via
email of new filings and issuances
related to this or other pending projects.
For assistance, contact FERC Online
Support.
n. Public notice of the filing of the
initial development application, which
has already been given, established the
due date for filing competing
applications or notices of intent. Under
the Commission’s regulations, any
competing development application
must be filed in response to and in
compliance with public notice of the
initial development application. No
VerDate Sep<11>2014
20:30 Apr 29, 2016
Jkt 238001
competing applications or notices of
intent may be filed in response to this
notice.
o. Procedural Schedule: The
application will be processed according
to the following revised Hydro
Licensing Schedule. Revisions to the
schedule may be made as appropriate.
Milestone
Target
Notice that application is
ready for environmental
analysis.
Filing of comments, recommendations, terms
and conditions, and prescriptions.
Filing of reply comments ...
Notice of the availability of
the draft EIS.
Initiate 10(j) process ..........
Notice of the availability of
the final EIS.
April 2016.
June 2016.
July 2016.
October 2016.
December 2016.
May 2017.
p. A license applicant must file no
later than 60 days following the date of
issuance of this notice: (1) A copy of the
water quality certification; (2) a copy of
the request for certification, including
proof of the date on which the certifying
agency received the request; or (3)
evidence of waiver of water quality
certification.
Dated: April 25, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016–10096 Filed 4–29–16; 8:45 am]
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
Federal Energy Regulatory
Commission
dbroatch@earthlink.net and Ms. Katie
McGinnes, Day Pitney LLP, 242
Trumbull Street, Hartford, CT 06103–
1212. For transferee: Mr. Mark
Boumansour, Aspinook Hydro, LLC,
c/o Gravity Renewables, Inc., 1401
Walnut Street, Suite 220, Boulder, CO
80302, telephone: 303–440–3378, email:
mark@gravityrenewables.com and
copies to: Mr. Karl F. Kumli, III, Dietze
and Davis, P.C., 2060 Broadway, Suite
400, Boulder, CO 80302 and Mr. Robert
A. Panasci, Esq., Young/Sommer, LLC
Executive Woods, 5 Palisades Drive,
Albany, NY 12205.
FERC Contact: Patricia W. Gillis, (202)
502–8735, patricia.gillis@ferc.gov.
Deadline for filing comments, motions
to intervene, and protests: 30 days from
the date that the Commission issues this
notice. The Commission strongly
encourages electronic filing. Please file
comments, motions to intervene, and
protests using the Commission’s eFiling
system at https://www.ferc.gov/docsfiling/efiling.asp. Commenters can
submit brief comments up to 6,000
characters, without prior registration,
using the eComment system at https://
www.ferc.gov/docs-filing/
ecomment.asp. You must include your
name and contact information at the end
of your comments. For assistance,
please contact FERC Online Support at
FERCOnlineSupport@ferc.gov, (866)
208–3676 (toll free), or (202) 502–8659
(TTY). In lieu of electronic filing, please
send a paper copy to: Secretary, Federal
Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426.
The first page of any filing should
include docket number P–3472–022.
Dated: April 21, 2016.
Kimberly D. Bose,
Secretary.
[Project No. 3472–022]
Summit Hydropower, Inc.; Aspinook
Hydro, LLC; Notice of Application for
Transfer of License and Soliciting
Comments, Motions To Intervene, and
Protests
[FR Doc. 2016–10141 Filed 4–29–16; 8:45 am]
On April 12, 2016, Summit
Hydropower, Inc. (transferor) and
Aspinook Hydro, LLC (transferee) filed
an application for transfer of license of
the Wyre Wynd Project No. 3472. The
project is located on the Quinebaug
River in New London County,
Connecticut. The project does not
occupy Federal lands.
The applicants seek Commission
approval to transfer the license for the
Wyre Wynd Project from the transferor
to the transferee.
Applicant Contact: For transferor: Mr.
Duncan Broatch, Summit Hydropower,
Inc., 6 Far Hills Drive, Avon, CT 06001,
telephone: 860–255–7744, email:
Federal Energy Regulatory
Commission
PO 00000
Frm 00025
Fmt 4703
Sfmt 4703
BILLING CODE 6717–01–P
DEPARTMENT OF ENERGY
[Docket No. ER16–1406–000]
Peak View Wind Energy LLC;
Supplemental Notice That Initial
Market-Based Rate Filing Includes
Request for Blanket Section 204
Authorization
This is a supplemental notice in the
above-referenced proceeding of Peak
View Wind Energy LLC‘s application for
market-based rate authority, with an
accompanying rate tariff, noting that
such application includes a request for
blanket authorization, under 18 CFR
E:\FR\FM\02MYN1.SGM
02MYN1
Agencies
[Federal Register Volume 81, Number 84 (Monday, May 2, 2016)]
[Notices]
[Page 26222]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-10141]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 3472-022]
Summit Hydropower, Inc.; Aspinook Hydro, LLC; Notice of
Application for Transfer of License and Soliciting Comments, Motions To
Intervene, and Protests
On April 12, 2016, Summit Hydropower, Inc. (transferor) and
Aspinook Hydro, LLC (transferee) filed an application for transfer of
license of the Wyre Wynd Project No. 3472. The project is located on
the Quinebaug River in New London County, Connecticut. The project does
not occupy Federal lands.
The applicants seek Commission approval to transfer the license for
the Wyre Wynd Project from the transferor to the transferee.
Applicant Contact: For transferor: Mr. Duncan Broatch, Summit
Hydropower, Inc., 6 Far Hills Drive, Avon, CT 06001, telephone: 860-
255-7744, email: dbroatch@earthlink.net and Ms. Katie McGinnes, Day
Pitney LLP, 242 Trumbull Street, Hartford, CT 06103-1212. For
transferee: Mr. Mark Boumansour, Aspinook Hydro, LLC, c/o Gravity
Renewables, Inc., 1401 Walnut Street, Suite 220, Boulder, CO 80302,
telephone: 303-440-3378, email: mark@gravityrenewables.com and copies
to: Mr. Karl F. Kumli, III, Dietze and Davis, P.C., 2060 Broadway,
Suite 400, Boulder, CO 80302 and Mr. Robert A. Panasci, Esq., Young/
Sommer, LLC Executive Woods, 5 Palisades Drive, Albany, NY 12205.
FERC Contact: Patricia W. Gillis, (202) 502-8735,
patricia.gillis@ferc.gov.
Deadline for filing comments, motions to intervene, and protests:
30 days from the date that the Commission issues this notice. The
Commission strongly encourages electronic filing. Please file comments,
motions to intervene, and protests using the Commission's eFiling
system at https://www.ferc.gov/docs-filing/efiling.asp. Commenters can
submit brief comments up to 6,000 characters, without prior
registration, using the eComment system at https://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information
at the end of your comments. For assistance, please contact FERC Online
Support at FERCOnlineSupport@ferc.gov, (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. The first page of any filing should
include docket number P-3472-022.
Dated: April 21, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-10141 Filed 4-29-16; 8:45 am]